1.3 Legal Requirements Register
The Legal Requirements Register, below, is to be completed by the Regional HSE Coordinator during the
Project Start Up Meeting to identify the health and safety legislation, codes of practice and Australian
standards relevant for the scope of works for this project. (Remove non-relevant documents from table below)

                                    Legislation and Other Legal Requirements

 Queensland WH&S Act 2011                                  NSW WH&S Act 2017

 Queensland WH&S Regulation 2011                           NSW WH&S Regulation 2017

 Environmental Protection Act and Regulation               Induction for Construction Work – National CoP

 Electrical Safety Act 2002 (Qld)                          Hazardous Manual Tasks CoP

 Electrical Safety Legislation 2002 (Qld)                  How to Safely Remove Asbestos CoP

 Electrical Safety CoP 2010 – Working near overhead        How to Manage and Control Asbestos in the Workplace
 and underground services (Qld)                            CoP

 Electrical Safety CoP 2013 – Managing Electrical Risks    Work Health and Safety Consultation, Co-operation,
 in the Workplace (Qld)                                    and Co-ordination CoP

 Electrical Safety CoP 2010 – Works (Qld)                  How to Manage Work Health & Safety Risks CoP

                                                           Managing the Risks of Hazardous Chemicals in the
 Managing Electrical Risks at the Workplace CoP (NSW)
                                                           Workplace CoP

 Work Near Overhead Power Lines CoP (NSW)                  Managing Noise & Preventing Hearing Loss CoP

 Managing the risk of falls at Workplaces CoP              First Aid in the Workplace CoP

 Managing the Work Environment & Facilities CoP            Managing the Risks of Plant in the Workplace CoP

 Confined Spaces CoP                                       Welding Processes CoP

 Excavation Work CoP                                       Demolition Work CoP

 Formwork CoP (Qld)                                        Safe Design of Structures CoP

 Scaffolding CoP (Qld)                                     Tilt up and Pre-cast Construction CoP (Qld)

 Mobile Crane CoP (Qld)                                    Tower Crane CoP (Qld)

 Steel Construction CoP (Qld)                              Preventing Falls in Housing Construction CoP (NSW)

 Concrete Pumping CoP (Qld)                                Construction Work CoP (NSW)

 Children and Young Workers CoP (Qld)                      AS/NZS 3000 Electrical Installations

 Traffic Management for Construction or Maintenance        AS/NZS 3012 Electrical Installations- Construction &
 Work CoP (Qld)                                            Demolition Sites




                                                                                 WHS Management Plan / Page 9

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads -.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.