28. Mobile Plant
Woollam Constructions shall ensure all mobile plant entering or performing work on a Woollam Constructions
site, is safe to use, is being appropriately serviced and maintained in accordance with the Manufacturers
recommendations, Australian Standards, Regulatory requirements and is fit for purpose.
Woollam Constructions shall ensure that the operator of mobile plant holds a current qualification gain
through training with a Registered Training Organisation. See 28.2 for qualification requirements.
Mobile Plant includes, but is not limited to;
• Cranes • Excavators / trenchers • Trucks
• Elevated Work Platforms (EWP’s) • Graders • Forklifts
• Scissor Lifts • Dozers • Backhoes
• Skid Steer Loader • Tractors • Bobcats
Woollam Constructions will ensure that a Plant Risk Assessment and a Safe Work Method Statement is
completed for each item of mobile plant prior to undertaking any activities on site. The Plant Risk Assessment
and Safe Work Method Statement must cover the safe operating procedures for the plant including
maintenance, service, inspection details and any commissioning on site prior to use.
The relevant Contract Partner must complete the Mobile Plant Checklist prior to equipment being used on site.
Where any element of this checklist is not acceptable, the plant owner shall ensure rectification prior to the
mobile plants use on site. The completed Mobile Plant Checklist shall be saved as on a cloud-based software
system and linked to Site Diary Equipment Section.
Woollam Constructions shall ensure plant onsite is maintained by regularly reviewing the scheduled
maintenance requirements documented on the Mobile Plant Checklist and in the Site Diary Equipment
Section. If maintenance is undertaken whilst on site, then the Mobile Plant Checklist and Site Diary Equipment
Section should be updated to include the next scheduled maintenance date.
Further to this Woollam Constructions will inspect daily prestart checklists completed for each plant. In some
cases, copies of these checklists will be kept with the plant operator’s SMWS.
28.1 Mandatory Mobile Plant Inspections
Following is a list of required inspection and maintenance for Contract Partners to provide for specific items of
Mobile Plant:
Mobile Plant Inspection and Servicing Requirements
Inspection frequency and
Plant Type Person responsible for inspection Australian Standard
record requirements
Operator (daily), Mechanic Daily, Monthly,
Concrete Line Pump AS 2550.15 COP
Engineer with relevant experience Yearly, 6 yearly
Operator (daily), Mechanic Daily, Monthly,
Concrete Boom Pump AS 2550.15 COP
Engineer with relevant experience Yearly, 6 yearly
Upon installation,
Construction wiring Licensed Electrician AS3012
then every 6 months
Daily Monthly,
Crane- mobile Operator (daily), Mechanic AS 2550 Independent yearly,
Crane – mobile >10t Engineer with relevant experience AS 1418 independent 10 yearly (5
yearly thereafter)
WHS Management Plan / Page 49
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.