SafeWorkMethodStatement QLD Demolition
Safe Work Method Statement – 16-120 POINCIANA AVE, TEWANTIN QLD 4565
Revision No: 1 Printed Date: Page 11
KHODR CIVIL PTY LTD Initial 19/02/2025
Work Sequence Potential Hazards Potential Risk Risk Score
8. Plant or 1.1 Person/s stuck by debris 8.1 Cuts and abrasions 2
equipment generated flung out from plant
projectiles.
Control Method Residual
8.1 Poor housekeeping around plant and equipment.
8.2 Debris spun off machinery wheels or tracks
8.3 Shattered concrete or masonry breakage when using hammers of picks
8.4 Unauthorised persons wander into work area
8.5 Operator not adequately protected
Work Sequence Potential Hazards Potential Risk Risk Score
9. Loading and 9.1 Dust 9.1 Inhalation, eye damage, ear damage 4
disposal of 9.2 Material falling from 9.2 Cuts and abrasions 4
demolished containers
Materials
Control Method Residual
9.1 Cover load on trucks or bins 6
Area to be closed to the public
Area to be closed to all non essential workers
Ensure correct PPE for the required task is supplied and used at all times.
9.2 Control methods as per 20.1 6
All works to be carried out to AS 2601-2001 and current OH&S regulations. QA Standard to AS9002-2000.