                   Safe Work Method Statement – 16-120 POINCIANA AVE, TEWANTIN QLD 4565
                                                                                                Revision No: 1   Printed Date:     Page 9
                   KHODR CIVIL PTY LTD                                                          Initial          19/02/2025

   Work Sequence                 Potential Hazards                                       Potential Risk                          Risk Score
4. Check                 4.1    Electricity                      4.1    Electrocution                                                1
   disconnection of      4.2    Gas                              4.2    Inhalation / Explosion / Fire / Burns                        1
   Services              4.3    Water                            4.3    Flooding                                                     1
                                                       Control Method                                                            Residual
4.1    Disconnection by Principal Contractor                                                                                         5
       Certification of disconnection to be given to demolition contractor
4.2    Disconnection by Principal Contractor                                                                                         5
       Certification of disconnection to be given to demolition contractor
4.3    Disconnection by Principal Contractor                                                                                         5
       Certification of disconnection to be given to demolition contractor

   Work Sequence                 Potential Hazards                                       Potential Risk                          Risk Score
5.  Removal of           5.1   Falling objects                   5.1    Cuts and abrasions                                           3
    existing ceilings    5.2   Falling Personnel                 5.2    Broken bones                                                 3
    & ceiling            5.3   Dust                              5.3    Inhalation, eye damage, ear damage.                          2
    structures
                                                       Control Method                                                            Residual
5.1   Dust masks to be worn while removing ceilings                                                                                  5

      Area to be closed to the public
      Area to be closed to non essential workers                                                                                     5
      Ensure correct PPE for the required task is supplied and used at all times                                                     4
5.2   Ladders and access scaffolds to be braced and on suitable footing
5.3   Control methods as per 5.1
      Materials to be handled in a workmanlike manner
      Materials to be stockpiled in an orderly manner.
      Provide clean, fresh water for flushing eyes at the workplace.
Log in to download the original file

SafeWorkMethodStatement QLD Demolition.pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.