Att9 - Waste Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Waste Weekly Recyclable Weekly
No.
Property Type Generation- Generated Generation- Generated
Occupants
Rate Waste Rate Recyclable
Reception and
Central Hall
N/A 10L/100m2 / 233 10L/100m2 / 233
day day
Village 1 100 4800 1600
60L/ occupant/ 20L/ occupant/
Village 2 140 6720 2240
week week
Village 3 60 2880 960
10L/100m2 / 10L/100m2 /
Amenities N/A 14 14
day day
Maintenance 10L/100m2 / 10L/100m2 /
N/A 233 233
sheds day day
Staff
20 40L/ bed/ week 800 20L/ bed/ week 400
Accommodation
Weekly Waste Weekly
15680 5680
(L) Recyclable (L)
Table 2 Estimated Waste and Recyclable Generation
• The Villages are assumed to have an occupancy of 80% throughout the week to reflect the temporal
nature of the camping and recreational facility.
• The rates utilised for the Villages align with the uses of Shared Residential: Tourist Park and
Boarding Guest House in the GRC and MBRC PSPs.
• These rates do not account for compostable material that can be diverted from the general waste
stream and reduce the generation of weekly generated waste. Due to the nature of the facility and
the emphasis on future agriculture and permaculture use, it is likely that the actual rates of weekly
waste will be less than estimated in Table 2.
As the Villages are the greatest generator of waste and recyclable streams, the receptacles for these should
be located close to these buildings accounting for:
• Amenity for facility users – including noise impacts when bins are being collected by the Waste
Collection Service Provider (Service Provider)
• Access for the Service Provider using the facilities internal roadway, minimising the distance of
reversing required and complying with SC6.10 - Appendix 3 – Refuse vehicle specifications.
Further details of these aspects can be found in Section 4 Bin Storage.
The above waste volumes equate to number of bins requiring emptying each week as provided in Table 3.
Project number 20220146 File 20220146-59 Kabi RD WMP R0.docx, 2022-09-06 Revision 1 4