Part 9 of 37 Appendix 7 - Stormwater Management MCU12/0208
Very large file (52.0 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Noosa on Weyba
Stormwater Management Plan
~,.., Cardno@
5 Water Quality Objectives
5.1 Stormwater Quality Objectives
The WQOs for stormwater treatment for the site cover three main components: pollutant load removal
targets; frequent flow management; and waterway stability. These WQOs have been derived from Maroochy
Shire Council Planning Scheme Policy No.6 as well as the Urban Stormwater Quality Planning Guidelines
(DEHP, 2010). Design objectives are specified for both the construction and operational phases of
development.
CONSTRUCTION PHASE
During the construction phase of development, the water quality objectives (WQOs)for the site include:
> Coarse sediment-coarse sediment is retained on site.
> Fine sediment (T55)-site discharge during sediment basin dewatering has a TSS concentration less
than 50 mg/L. Achieve site discharge water quality through, for example, appropriate sediment basin
design and operation with flocculation as required. It is noted that on the Sunshine Coast basins are
typically designed for 125mm rainfall depth over a five day period.
> Turbidity-Site discharge during sediment basin dewatering has a turbidity (NTU)less than 10% above
receiving waters turbidity. A site-specific relationship should be developed between turbidity and
suspended solids, prior to the commencement of construction.
> Nutrients (N & P)-Nitrogen and phosphorous are managed through sediment control.
> pH-Site discharge during sediment basin dewatering has a pH range 6.5-8.5
> Litter and other waste-Prevent litter/waste entering the site, the stormwater system or watercourses
that discharge from the site. Also minimise or sufficiently contain on-site litter and waste production and
regularly clear waste bins.
> Hydrocarbons and other contaminants- no visible sheen, no detectable odour. Hydrocarbons and
other contaminants are prevented from entering the stormwater system or internal watercourses that
discharge from the site.
> Wash down water-Wash down water is prevented from entering the stormwater system or internal
watercourses that discharge from the site.
> Cations and anions-Cations and anions including aluminium, iron and sulfate are managed as required
under an approved acid sulphate soil management plan.
The focus during the construction phase will be erosion and sediment control. Appropriate measures, such
as silt fences and berms will be adopted on a lot by lot basis. The proposed bio-retention and detention
basins can also be utilised as temporary sedimentation basins. The filter media will either be protected or
not installed until the majority of construction within the catchment area has been completed. Dedicated
temporary sedimentation basins will be required in some areas. An erosion and sediment control plan will be
required for each stage of the construction.
OPERATIONAL PHASE
Pollutant Load Reduction
During the operational phase the following pollutant load removal targets are specified for the development:
> Gross Pollutants: 90 percent reduction compared to untreated runoff;
> Total Suspended Solids (TSS):80 percent reduction compared to untreated runoff;
> Total Phosphorous (TP):60 percent reduction compared to untreated runoff; and
> Total Nitrogen (TN):45 percent reduction compared to untreated runoff.
Northbrook Corporation Pty Ltd Version 2 29 November 2012
SMP_v2.docx Commercial in Confidence Page 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 9 of 37 Appendix 7 - Stormwater Management MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 52.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.