Stormwater Management Plan
                                                                                     ~,.., Cardno@

1              Introduction


The subject site, known as Noosa on Weyba, encompasses the following lots:

The Northbrook Pty Ltd land:

>   Lot 1667 on M3772                      44.4 ha

>   Lot 11 on RP893393                     40.7 ha

>   Lot 12 on RP893393                     0.61 ha

The J & K Hofmann land:


>   Lot 7 on RP46782                       1.99 ha

>   Lot 2 on RP160983                      93.1 ha

>   Lot 2 on SP 179590                     12.5 ha

>   Lot 53 on SP163571                     110.0ha

It is proposed to develop around 19 percent of this site for residential purposes, with 4 percent of the site
used    parks and lake buffer zone and the remaining 77 percent of site dedicated as greenspace and
       as

conservationareas.   The developed areas are contained within Lot 11 and 12 on RP893392, Lot 2 on
SP179590 and Lot 53 on SP163571. The concept master plan for the development is shown in Appendix A.
The development will be conducted under a Community Title Scheme.

The site ultimately drains to Lake Weyba which is a declared Fish Habitat Area. A section of the site is also
located in the Water Resource Catchment Area          as   defined
                                                              by the Maroochy Plan 2000. Therefore the
treatment of stormwater to the best possible standard is of the upmost importance. A significant portion of
the site is currently used for rural purposes, in particular the grazing of cattle.    Consequently the
development provides an opportunity to improve the quality of stormwater being discharged from the site if
appropriate measures are adopted.
To ensure that the impact of the development is minimised, the principles of water sensitive urban design

(WSUD) have been adopted. These principles (sourced from Urban Stormwater Planning Guidelines
Queensland Department of Environment and Heritage Protection (DEHP),2010) include:

>   the protection of existing natural water features;

>   the integration of public open space with stormwater drainage corridors to maximise public access and
    recreation and preserve waterway habitats and wildlife corridors;

>   the maintenance of the natural hydrologic behaviour of catchments by preserving the natural water cycle;

>   the protection of water quality environmental values;

>   the minimisation of the demand on the reticulated water supply system and utilisation of stormwater as a
    valued resource;

>   the minimisation of capital and maintenance costs of stormwater infrastructure; and

>   the integration of water into the landscape to enhance visual, social, cultural and ecological values.

The aim of this report is to determine the overall WSUD          strategy for the site.   Further analysis will be
conducted during the detailed design stage. This report will:

>   Determine the relevant water quality objectives (WQO)for the site;

>   Outline the water sensitive urban design (WSUD)measures that will be adopted for each precinct and the
    site as a whole; and

>   Conduct MUSIC modelling to determine whether WQOs can be met.




Northbrook Corporation Pty Ltd                       Version 2                                    29 November 2012

SMP_v2.docx                                   Commercial in Confidence                                       Page 1

Used in these records

About this file

File size
52.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 9 of 37 Appendix 7 - Stormwater Management MCU12_0208.pdf · 52.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.