mor

e Final ground levels should slope gently to the edge of the easement or the proposed
kerb or surrounding area such that pooling of water on the easement is avoided and
conductor ground clearances are not decreased.

« 10 metres clear access must be provided around all towers and pole structures.
« Stockpiling of spoil on the easement is prohibited.

« — Lighting structures are not permitted in the easement without prior written consent of
ENERGEX.

« Underground services should be kept to the outer edge of the easement and any
crossing of the easement should be clearly marked. Please submit the relevant design
drawings to the Principal Mains Design Engineer for review. The identification,
assessment and mitigation of any possible hazards in the service due to
electromagnetically induced voltages, is the responsibility of the developer.

° Any cut in the vicinity of a structure or between a structure and the road kerb will need
to be stabilised by a retaining wall. The retaining wall design and location is to be
submitted to ENERGEX for approval.

«Any further proposal for works or development on the easement including those
involving changes in ground level and retaining wall designs around towers and poles
must have prior approval from ENERGEX. Please submit the relevant civil designs to
the Principat Mains Design Engineer for approval.

« Access to the easement and access along the easement must be available to
ENERGEX personnel and heavy equipment at all times. ENERGEX will require the
developer / owner to supply and install gates where fencing prohibits access to and
along the easement area. To enable travel along the easement at anytime the gates
must be series locked with an ENERGEX padlock. Both the padlock and a design
drawing of an acceptable gate will be provided by ENERGEX,.

e Any costs incurred by ENERGEX as a result of the works on the easement are to be
met by the property developer / owner.

« ~ Atall times the following minimum clearance must be maintained from the top of any
machinery moving in the vicinity of energised conductors:

— 132kV and 110kV conductors — 4.5m minimum clearance

— 33kV and 11kV conductors — 3m minimum clearance

~ Should it be necessary to transport equipment or extend any equipment, such that
these clearances cannot be confidently maintained, you are required to contact our
office to ascertain whether a Safety Officer is required on-site. All operators of
machinery are to be made aware of the presence of high voltage conductors.

* Any proposal for landscaping on the easement must have prior approval from
ENERGEX. Please submit the relevant landscaping design to the Principal Mains
Design Engineer for approval. When considering landscape designs the planting of
trees must be kept to the edges of the easement and not under any overhead
conductors. When mature, plants or trees must not grow in excess of 4 metres in

Reference: HBD331064 NSID:07/L0064

Page 12 of 26

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2006.00002356.001 [As Published].pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.