NOOSA COUNCIL IDAS Development Application Decision Notice                                                           4


          In this regard and as an indication only - the site should have a Minimum Floor Height of RL 2.5 (AHD).
          These levels however are subject to change and verification shall be made to Council’s Land
          Development Section prior to obtaining a Development Permit for Building Works.

13.       A vehicular access driveway to serve the development shall be constructed from the Edward Street
          frontage of the site with a maximum width of 4.5 metres.

          The driveway shall be designed and constructed to Council’s design standards and to grades that prevent
          vehicles from scraping and/or bottoming. Should any driveways be constructed to grades that do not
          comply with AS2890.1-1993 and AS2890.2-1989, Council will require that the driveway be removed and
          reconstructed to levels that do comply.

14.       All vehicles shall enter and leave the site in a forward direction.

15.       Carparking shall be provided within the site as shown on titled Proposed Duplex 10 Edward Street,
          Noosaville dated September 2002 by Andrew McKellar Design, except as modified herein.

16.       A minimum of 1 uncovered carpark spaces and 4 covered carpark spaces shall be provided on site.

17.       The carparking area shall be designed to comply with the provisions of AS 2890.1-1993 for user class 1
          except the minimum head clearance (headroom) at any point shall be 2.3m.

18.       A roadworks contribution of $976 towards the Coastal Major Road Network shall be paid to the Council
          prior to obtaining a Development Permit for Operational Works. This amount will be subject to variations
          in the Price Index, All Groups Brisbane from December 2002 until the date of payment.

19.       Footpath improvements such as topsoiling, grassing, and tree planting are required to the Edward Street
          frontage of the site in accordance with Planning Scheme Policy PSP1 Landscaping Guidelines. Grass
          shall be couch, free of weeds.

20.       All stormwater drainage shall be collected on site and discharged to Council’s street drainage system in
          Edward Street. In this regard, plans shall be prepared by a Registered Professional Civil Engineer and
          submitted to Council prior to obtaining a Development Permit for Operational Works.

         The maximum discharge of stormwater drainage allowable to Council’s street drainage system at any one
         location is 25 litres/second.

21.       To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
          from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
          down) collected in a grease/oil arrestor provided on site prior to being permitted to discharge into
          Council’s drainage system.

          To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors, which
          shall be submitted to the Council for approval prior to obtaining a Development Permit for Operational
          Works.

          All other clean stormwater, such as roof water, can be collected on site and discharged through a single
          underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor.

          A Development Permit for Building Works shall not be granted until a Development Permit for Operational
          Works has been issued in regard to the drainage scheme.

22.       All site stormwater drainage shall be by means of a gravity systems.

23.       A contribution of $2,612 shall be paid to Council towards the cost of the Noosaville Master Drainage Plan
          prior to obtaining a Development Permit for Operational Works. The amount of the contribution shall be
          adjusted in line with changes to the Consumer Price Index, All Groups Brisbane from December 2002
          until the date of payment.

24.       The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
          accordance with Council’s standards and requirements at no cost to Council.




H o:\database\onestop\decision.doc

Used in these records

About this file

File size
45 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED COMPILED Decision Notice [As Published].pdf · 45 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.