Aurecon Australia Pty Ltd ABN 54 005 139 873 T +61 7 3173 8000 32 Turbot Street F +61 7 3173 8001 (Locked Bag 331 Brisbane QLD E [email protected] 4001) W aurecongroup.com Brisbane Queensland 4000 Australia 6 November 2013 Attn: Jack Lewis Sunshine Coast Regional Council Locked Bag 72 Sunshine Coast Mail Centre, QLD, 4560 Application Number: MCU13/0052 Response to Information Request for MCU13/0052 - Material Change of Use (Impact Assessable) for a ‘Service & Utility Type 3 Tower’ located at 153 Lake Flat Road, Boreen Point 4565 (Lot 2 on RP126723) I refer to your letter dated 23 April 2013 requesting further information for a Telecommunications Facility at 153 Lake Flat Road, Boreen Point 4565 (Lot 2 on RP126723). A response to each of the matters raised in your letter is provided below. Visual Amenity The Specific Outcome O39 of the Infrastructure Uses Code requires the proposed monopole is visually integrated with its landscape so as not to be visually dominant or obtrusive. 1. Please provide a photomontage of the proposed monopole adjacent to the site along Lake Flat Rd looking towards the proposed monopole. Response One photomontage has been prepared to illustrate how the proposed facility will appear when viewed from along Lake Flat Road looking east towards the proposed monopole. As can be seen in the attached photomontage, the visual and landscape character of the locality will be maintained with the addition of the proposed facility. It is therefore considered that the proposed facility meets Specific Outcome O39 of the Infrastructure Uses Code. It is our recommendation that the monopole is painted ‘pale eucalypt’ in order to blend with the mature vegetation on site and existing power poles. This is requested to be conditioned by Council. Reasons for Approval Despite the Conflict with the Scheme Section 326(1)(b) of the Sustainable Planning Act 2009 seeks the assessment manager’s decision must not conflict with the Planning Scheme, unless there are sufficient grounds to justify the decision, despite the conflict. The Service & Utility Type 3 use is identified as an inconsistent use on the proposed site. 1. Please provide at least three succinct reasons for approval of the proposed development, despite this conflict with The Noosa Plan. Response Despite conflicts with The Noosa Plan, NBN Co considers Council should approve the proposed development for the following reasons: 1. The Boreen Point North facility is necessary to relay data out from the proposed Boreen Point & Cootharaba facilities back into the broader NBN network.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 2 pages
Page 2
2. The proposed facility is considered to meet the desired environmental outcomes of The Noosa
Plan as the installation of the proposal will result in the introduction of the National Broadband
Network into Boreen Point and areas of Cootharaba. This will ultimately assist in facilitating
opportunities for economic, commercial and tourism growth. In addition the provision of
reliable broadband services will have a significant impact on the availability of good quality
communications for day-to-day life, in times of emergency and the general public safety of
residents. This is particularly important in rural based localities.
3. The proposed facility will not impact on the scenic views of the Boreen Point or Cootharaba
locality as it has been located on a modified rural allotment that contains similar infrastructure
such as the electricity network, which runs from north to south through the property.
Additionally, the proposal benefits from significant tree screening from the immediate
neighbours, and is also offset from the community as much as possible (where only three (3)
residential dwellings are located within a 500 m radius of the facility).
Proposed Wireless Infrastructure Catchment Map
Council requires confirmation of the area this tower is to service as part of the proposed NBN wireless
network rollout.
2. Please provide a map showing the area/houses intended to utilise the proposed wireless
infrastructure. In addition, include the proposed service area overlayed with topographical
mapping.
Response
NBN Co proposes to erect two new monopoles, each on the opposite ends of the large pine plantation
property at 153 Lake Flat Rd, Boreen Point (Lot 2 on RP126723). These two proposed facilities work
in tandem to provide a Fixed Wireless service to the community at Boreen Point, and parts of
Cootharaba.
The Boreen Point facility (MCU13/0053) is designed to provide a service to the township, and the
Boreen Point North facility (the subject of this application MCU13/0052) provides a service to parts of
Cootharaba. It also acts as the key transmission link for the Boreen Point facility and another facility
further south west at Davis Road, Cootharaba, connecting them to the broader NBN network.
At Boreen Point, NBN Co advises that more than 630 properties, households and businesses, will be
serviced either directly or indirectly by the proposed facilities.
The Development Application has been submitted on the strength of the number of premises present
that can be serviced. This is the driving factor behind the submission of the DA; the number of
properties that can access a Fixed Wireless service, and not necessarily the coverage area.
NBN Co does not release data such as coverage maps that effectively make a commitment to
residents by specifying exactly which premises may receive the Fixed Wireless service before the
network is built and tested. There will always be some premises on the fringe of the service capability
that may indeed have to connect to the NBN satellite service instead, and NBN Co does not issue
documents that might mislead individuals in the community.
However, as above, NBN Co has provided to Council a detailed written description of the coverage
objective of the proposed facilities at Boreen Point.
Landscaping Plan
A Landscaping Plan is required to be submitted to camouflage any proposed equipment shelters and
the majority of the monopole’s height. Ideally trees will be able to achieve up to 20m+ in mature
height, though inclusion of fast growing species is also desirable to achieve early visual screening.
3. Please provide a detailed landscaping plan, indicating vegetation buffers to be established at the
base of the monopole. The plan shall be drawn up in accordance with The Noosa Plan’s Planning
Scheme Policy 3 – Landscaping Plants and Guidelines and include appropriately selected tree
Page 3
species and understorey plantings to achieve dense visual screening of the monopole and
associated equipment shelters. Landscape planting details and a minimum 12 month maintenance
schedule shall also be included.
Response
NBN Co does not consider a landscaping plan is pertinent to the assessment of the application. Also,
given the proposed location is within close proximity to existing mature vegetation and adjacent to
power lines and poles. For these reasons, NBN Co does not consider a landscaping plan or conditions
are necessary for this site.
Co-location
Include confirmation that co-location by other network providers will be actively encouraged
4. Please provide details as to how other telecommunications providers will be facilitated and
encouraged to co-locate other wireless antennas on the proposed monopole.
Response
NBN Co has established and put in place a number of framework agreements with third party as well
as mobile network operators which outlines the process and procedures in relation to co-location on
NBN Co’s network infrastructure sites. These agreements address operational, commercial and
technical requirements for all incoming site share requests.
5. A Written Undertaking that the facility will be made available for the mounting of other
communication providers’ antennas and that no restrictive provisions form part of any contract,
agreements or other documentation associated with the development.
Response
It is a requirement under the Telecommunications Act that all telecommunication providers make their
facilities available for the purposes of collocation. In addition to this, the frame work agreement allows
telecommunication provider’s to co-locate their equipment on NBN Co’s facilities and NBN Co is happy
to work with the Telecommunication providers to ensure that where possible our facilities can be
accessed to improve mobile coverage.
It is considered that the information above provides an adequate response to all of the information
requested by Council.
Should you require further information, please do not hesitate to contact Claire Harris on 3173 8738,
or alternatively by e-mail [email protected]
Yours faithfully
James Irwin
Project Leader