The purpose of this manual is to indicate the safest and most efficient method in installing the EnviroPod units.
Personal Protective Equipment
The following personal protective equipment is required by staff for installation activities:
High visibility vest or shirt
Safety Footwear (Steel cap toe)
Gloves (leather palmed riggers gloves or similar)
Safety eyewear whilst drilling, hammering, cutting T section struts and installing tops and cages.
Hearing protection for drilling, cutting using electric or battery saws and hammering.
Note: Personnel on construction and private sites must also adhere to the specific safety requirements of each
work site.
Tools Required For Installation
1. Tape measure
2. Marking Template
3. Marking spray paint
4. 8mm masonry drill
5. 5 mm steel drill
6. Pop Riveter for 4.8mm rivets
7. Hammer
8. Stanley knife
9. Straight edge
10. 10mm socket and ratchet
11. Hacksaw
Pre-Installation Works (to be completed by others)
1. Gully pits shall be clean prior to installation by either a “Gully sucker” or manual methods.
2. All solidified material and debris within the gully pit shall be broken-out and removed.
3. Cleaning shall be carried out up to 1 week immediately prior to installation.
4. Any standing water shall be removed from the gully pit.
5. Any pipe penetrations within the gully pit must cut off flush with pit walls and rendered prior to installation.
Installation
The aim of all EnviroPod installations is to install the largest unit into each pit, without influencing the
hydraulic performance of the pit or drainage system. To provide clarification on certain aspects of the
installation the following tolerances are included:
©2013 Stormwater360 | EnviroPod Installation Manual 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.