MCU14/0056 Response to SARA - Consulting Report

of 321

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Very large file (24.7 MB): may take a few minutes to open.

Log in to see the plans as drawn

Original PDF page 244, section 1. The text section number identifies this passage in the reader.

                                                                                                                Preliminary Detention Calculations
                                                                                        Date:      17/04/2014                Document No.:                14012-Detention
                                                                                            By:       AvT                        Revision No.:                    A


                                                                                                                                                 Project No: 14012

                                              PROJECT: PROPOSED MIXED USE DEVELOPMENT
                                              ADDRESS: CORNER MYALL STREET & FERRELLS ROAD COOROY QLD
                                           CATCHMENT: TOTAL SITE

   Runoff Coefficient (C10) - Undeveloped:                     0.70           (QUDM Table 4.05.3 (b))                     tc =              6 min.
   Runoff Coefficient (C10) - Developed:                       0.82           (QUDM Table 4.05.3 (a))                     tc =              6 min.
   Catchment Area - Undeveloped:                              50354     m2
                                                                         2
   Catchment Area - Developed:                                50354     m

                                                                Parameters
   ARI                                                                  2yr              5yr         10yr          20yr             50yr         100yr
   Rainfall Intensity                                         mm/hr    150.0            184.0        204.0         232.0            268.0        296.0
   Frequency Factor            fy=                                      0.85            0.95         1.00          1.05             1.15          1.20
   Undeveloped C              Cu=                                             0.60          0.67     0.70           0.74             0.81        0.84
   Developed C                Cd=                                             0.70          0.78     0.82           0.86             0.94        0.98

                                                                      Flows
   Undeveloped Flow           Qu=              C*I*A           l/s            1248      1711         1997          2385             3018         3478
   Developed Flow            Qd=Qi=            C*I*A           l/s            1462      2005         2340          2794             3535         4074
   Difference                                                  l/s            214       293          342           409              517          596

   Outlet Flow              Qo=        Max. Qu (or Q2)         l/s            1248    1711        1997             2385             3018         3478
                                                                                     Multiple Outlet Pipes

                                                               Initial Volume
   Reduction ratio             r=            (Qi-Qo)/Qi                   0.146         0.146        0.146         0.146            0.146        0.146
   Inflow Volume               Vi=            4tc*Qi/3         l/s            702           962      1123          1341             1697         1956    QUDM Equation

                              Culp      Vs=(r(1+2r)/3)*Vi      m3             44            61        71             85              107         123     QUDM Equation 5.01

                              Boyd             Vs=r*Vi         m3             103           141       164           196              248         286     QUDM Equation 5.02
   Volume to Retain
                             Carroll    Vs=(r(3+5r)/8)*Vi      m3             48            66        77             92              116         133     QUDM Equation 5.03

                             Basha         Vs=(r(2+r)/3)*Vi    m3             73            101       118           140              178         205     QUDM Equation 5.04



                            Volume to Retain =                 m3             67            92       107           128              162          187
                                                                                                                                    3
                                                                        Total Volume to Retain = 186.93 m




vT Consulting Engineers
ABN 3291 2821 849                                                                                                                                 PO Box 26, Carina QLD 4152
www.vtce.com.au                                                               Page 1 of 2                                                               [email protected]
Log in to download the original file

MCU14_0056 Response to SARA - Consulting Report.pdf · 24.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.