2018-11-06 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 6 NOVEMBER 2018
Risks & Opportunities
Risk Description Likelihood Consequence
SEMP and proposed actions are not complete before Possible Implementation of
intervention is required. At current erosion rates there is unplanned/emergency
sufficient time; however, delays to implementation or works required.
large storm events will increase this risk.
Remediation costs will continue to grow until a solution Certain Increased costs to
can be implemented. replace lost sand and
habitat.
A failure to remediate may expose Council to a risk of Possible Legal costs and/or
litigation from properties that are currently protected by costs awarded as
the Dog Beach peninsula damages if it is found
Council failed in their
duty of care.
Reputational damage, due to a perception of poor Likely Reputational.
response to current erosion.
Opportunities
While the primary purpose of this work is to inform and assess future management solutions for
Noosa Spit, including future capital works, there are potential opportunities for using the
information and model for other projects, such as:
1. Use the information collected in this project, in conjunction with a coastal process study
undertaken of the Eastern Beaches in 2013, to work towards a shire-wide SEMP in future.
2. Provide a better understanding of coastal processes for Noosa Main Beach and improve
the efficiency of sand pumping operations through the Sand Recycling System.
3. Provide an understanding of river mouth dynamics which may aid in understanding the
migration of Hinksia algae.
Finance
The cost to prepare a Shoreline Erosion Management Plan has been estimated at $240,000
excluding GST. This estimate has been prepared in conjunction with external consultants and
includes data collection, preparation of the SEMP, stakeholder consultation and project
contingency.
It is proposed that the $240,000 budget be allocated over two financial years to reflect timing of
project milestones as per the table below.
Year Amount
2018/19 (BR2) $80,000
2019/20 $160,000
Total $240,000
The 2018/19 allocation of $80,000 is to be included in budget review 2 (BR2) to enable
commencement of the work as soon as practical, with the remaining $160,000 (estimated) to be
incorporated into the build-from-base budget in 2019/20.
Page 17 of 97
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.