                                              Officer:          Duncan Thompson
                                              Direct Telephone: (07) 5449 5175
                                              Response Address: PO Box 141, Tewantin QLD 4565
                                              Email:            [email protected]
                                              Our Reference:    2008/203
                                              Your Reference:
18 March 2008

Vynara Pty Ltd
CARE Damien Miller
6 Maher Terrace
SUNSHINE BEACH QLD 4567



Dear Sir

                                      Decision Notice
                                  Integrated Planning Act 1997
I refer to your application and advise that on 18 March 2008 Council decided to approve the
application in full subject to conditions.
Details of the decision are as follows:

1     APPLICATION DETAILS

 Application No:                     2008/203
 Street address:                     5 Bluefin Court, Noosaville
 Real property description:          Lot 2 RP 906991
 Planning Scheme:                    The Noosa Plan

2     DECISION DETAILS
The following type of approval has been issued:
    Development Permit for a Material Change of Use - Multiple Housing Type 2 - Duplex

3     REVELANT PERIOD OF APPROVAL

    This Development Permit lapses if the development has not happened by 18 March 2012,
      unless application to extend the relevant period is approved by Council.
4     ASSESSMENT MANAGER CONDITIONS

1.    Development undertaken in accordance with this approval must generally comply with the
      approved plans of development. The approved plans are titled and numbered:
       Plan /              Rev.    Plan / Document Name                         Date
       Document No.
       0885 SK01                   Level 1 Plan – Greg Gibbs Architects         Jan 2008
       0885 SK02                   Level 2 Plan – Greg Gibbs Architects         Feb 2008
       0885 SK03                   Elevations – Greg Gibbs Architects           Feb 2008



                                                                                              1 of 9
Full text of the other 8 pages

Page 2

                                                -2-


2.    The Duplex Dwelling shall be setback a minimum of 4.19m from the Reef Street boundary.
3.    The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.
4.    The open space and setback areas are to be landscaped in accordance with Council’s Policy
      on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
      qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
      the premises being occupied and maintained at all times thereafter.
5.    Existing trees on the site and within road reserves are to be retained, except where required to
      be removed due to building operations or the conduct of the approved use. These landscape
      plans required to be submitted are to denote areas of existing vegetation or existing trees
      proposed or required to be retained.
6.    All fencing shall be setback at least 1 metre from the Bluefin Court property boundary, with at
      least half of the fencing setback 2 metres. The area of land between the fence and the front
      property boundary shall be densely landscaped to screen any fencing from the street.
7.    Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like,
      thus remaining as open structures.
8.    The building shall not exceed 8m and two storeys above natural and finished ground level.
9.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
      certificate lodged with Council at completion of work confirming compliance with the maximum
      allowable building height as required by either the conditions of approval or the Planning
      Scheme.
10.   The proposed development shall have all kitchen, laundry and bathroom fittings that comply
      with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
      Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
      Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
      System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
      Dishwashers and washing machines are excluded from this requirement.
11.   All hot water systems installed shall be either solar systems; electric heat pump systems; or
      gas systems (LPG or natural).
12.   Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for operational works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
13.   The requirements of this development approval are to be effected, prior to the use of the
      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
      this approval to effect compliance with conditions.
14.   This Development Permit lapses if the development has not happened by 18 March 2012,
      unless application to extend the relevant period is approved by Council.
15.   The developer must obtain all of the other Development Permits referred to in the Decision
      Notice, prior to obtaining a Development Permit for Building Works.
Land Development

River Flooding
16.   All buildings proposed on site (and areas utilised for carparking purposes associated with the
      buildings) shall be constructed to comply with Council’s Minimum Floor Height requirements
      as defined in Council’s Planning Scheme and on Council’s Scheme Maps at the time of issue
      of the Building Permit.

                                                                                          2 of 9

Page 3

                                                -3-


      In this regard the development should have a Minimum Floor Height of RL 2.6 (AHD) and
      garages should have a Minimum Floor Height of RL 2.3 (AHD). These levels however are
      subject to change and verification shall be made to Council’s Land Development Section prior
      to obtaining a Development Permit for Building Works.

      The applicant should note that compliance with these levels does not necessarily require the
      whole site to be filled. To this extent excessive filling should be avoided to prevent any
      impacts on neighbouring properties and minimum floor levels should be strictly adhered to
      without building higher than is actually needed to prevent flooding.

Vehicle Access and Carparking Areas
17.   Concrete access and carparking areas shall be provided generally in accordance with drawing
      number 0885 SK01 dated Jan 2008 by Greg Gibbs Architects.
18.   The carparking area shall be designed to comply with the provisions of AS 2890.1-2004 for
      user class 1A with allowance for vehicles to enter and leave the site in a forward gear and with
      a minimum head clearance (headroom) at any point of 2.2m.
19.   The driveway shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
      movements along the footpath without any step or level difference. Should any driveways be
      constructed to grades that do not comply with AS2890.1-2004, Council will require that the
      driveway be removed and reconstructed to levels that do comply.
      Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
      to have the footpath continue at a constant grade to minimise the potential for pedestrians to
      trip or fall. A Development Permit for Operational Works shall be required.
20.   To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath,
      the driveway and any associated fencing or vegetation near the driveway shall comply with the
      minimum sight line requirements as defined in AS2890.1, section 3.2.4. The applicant shall
      demonstrate compliance by illustrating these sight lines on the plans submitted for both
      Operational Works approval and Building Works approval.
Frontage Works
21.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the
      Robert Street frontage of the site in accordance with Planning Scheme Policy PSP03
      Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
22.   A new 1.5m wide concrete footpath shall be constructed along the Bluefin Court frontage of
      the site in accordance with Council’s design standards and to an alignment that protects any
      significant vegetation or any underground services.
23.   All footpaths, driveways and parking areas shall be designed and constructed to ensure
      pedestrian safety using non-slip materials, to produce an evenly graded surface finish, and to
      be in accordance with the Disability Discrimination Act 1992 and Australian Standard 1428.1
      Design for Access & Mobility.
Roof Water & Stormwater Drainage
24.   Roof runoff from any new dwelling unit shall be directed to a rainwater storage system or tank
      (minimum storage 5000 litres per dwelling unit) that is installed to ensure water from the tank
      is used for external uses (such as watering gardens, irrigation, ornamental ponds, water
      features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets
      internal to the dwelling. All rainwater tanks are to be designed and installed in accordance with
      the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and shall be part of
      the plumbing application in conjunction with the building approval. The location and capacity
      of the tanks shall be clearly shown on the plans submitted for Building Works and Operational
      Works approvals and any overflow shall be directed to the road frontage or the stormwater
      drainage system located at Robert Street.

                                                                                           3 of 9

Page 4

                                                 -4-


      Rainwater storage tanks shall not be located within any sewer easements
25.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      shall be collected and discharged so there is no net increase in stormwater runoff from the
      site. Stormwater drainage permitted to drain from the site shall be discharged to Council’s:
      25.1.   kerb & channel street drainage system in Robert Street.
      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
      drainage system at any one location is 25 litres/second.
26.   All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
27.   The proposed units shall be connected to Council’s existing sewerage reticulation systems
      located in Bluefin Court and be constructed in accordance with Council’s standards and
      requirements at no cost to Council.
Town Water Supply
28.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
29.   Each individual water connection to the water reticulation system shall extend to the property
      boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
30.   All water meters must be located outside the property boundary and in an easily assessable
      location to facilitate unhindered reading by Council and/or Council’s contracted water meter
      readers, and not behind fences or locked gates. In this regard approval of the water meter
      configuration and location must be obtained from Council’s Water & Sewerage Capital Works
      Manager prior to lodgement and approval of hydraulic drawings.
      Individual water meters capable of being separately rated shall be installed for each unit.
31.   For Multiple Uses (including Building Format Plans, Group Title Plans, Duplexes etc) the
      development shall be served by:
      31.1.   A single Body Corporate water meter to measure the total water consumption, and
      31.2.   Individual water meters to each tenement capable of being separately rated, and
Earthworks
32.   Any civil works and/or earthworks carried out on site shall not affect the structural integrity of
      any of the existing fences, retaining walls or structures that border the development site.
      Fences that are affected shall be replaced prior to the Building Certifier issuing the Certificate
      of Classification. In this regard any fences to be replaced shall be clearly shown on the plans
      submitted for Operational Works approval.
Erosion and Sediment Control
33.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.

Contributions Towards Council Infrastructure
34.   Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
      upgrading various infrastructure at the rates applicable at the time of payment. An estimate
      only of the contribution amounts under the current Council policies and requirements is
      outlined in the table below:

                                                                                           4 of 9

Page 5

                                                 -5-


       Contribution Required For:                                                    Amount:
       PSP12 – Public Open Space Contributions (Park)                                          $3,034
       PSP16 – Sewerage Headworks Contributions                                                $2,064
       PSP17 – Water Supply Headworks Contributions                                            $3,088
       PSP20 – Pathway Trunk Network Contributions                                             $1,028
       TOTAL Contribution Amount =                                                           $9,214.00
       Please note, that these amounts are all subject to variations in the Consumer Price Index, All
       Groups Brisbane from DECEMBER 2007 until the date of payment.

      All contributions must be paid prior to the issue of a Development Permit for Operational
      Works.

      Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
      contributions not be paid at the due time, Council shall call upon the trading bank guarantee in
      full.

      Processing of bonds for security where specific Council approval has been given for the
      bonding of contributions will incur an administration fee in accordance with Council’s Land
      Development Commercial & Regulatory Fees at the time of lodgement.

      In the event that the Development Permit for Material Change of Use of Premises lapses or is
      cancelled, the paid contributions and/or the trading bank guarantee will be returned.

General
35.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
36.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
37.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
5     REFERRAL AGENCY CONDITIONS

The referral agencies applicable to this application are:

 Referral Trigger            Referral Status     Referral Agency        Referral Address

 Site within 100m of a       Advice              Energex                GPO Box 1461
 substation                                                             BRISBANE QLD 4001

6     APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.    Plan / Document Name                      Date
 0885 SK01                         Level 1 Plan – Greg Gibbs Architects      Jan 2008
 0885 SK02                         Level 2 Plan – Greg Gibbs Architects      Feb 2008
 0885 SK03                         Elevations – Greg Gibbs Architects        Feb 2008
                                                                                           5 of 9

Page 6

                                                  -6-


7     ADVISORY NOTES

The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.    The development should be undertaken in a manner that causes no detrimental effect upon
      the amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-
      borne hazards, atmospheric pollutants (including dust or odours) nuisance or any other
      emissions in accordance with the nuisance provisions of the Environmental Protection
      Regulation 1998 or Council’s Local Law No. 12 – Control of Nuisances.
2.    In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
      cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
      where it could reasonably be expected to move into a roadside gutter, storm water drain or a
      watercourse. On the spot fines apply for such offences.
3.    The applicant is advised that development contributions and infrastructure charges applicable
      to this development approval have been based on the following Uses Class/ Uses and
      applicable quantities:-

                   Existing Development                              Approved Development
        Existing Use Class                                Approved Use Class
                                  Existing Quantity                                  Approved Quantity
               / Use                                            / Use
                                 Vacant – (One
                                                          Multiple Housing -
        Detached Housing         Detached House As                                  2X3 Bedroom Units
                                                          Type 2 – Duplex
                                 Right)

4.    The applicant is informed that approval of this development application will trigger an
      Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
      Charges Plan for the estimated amount of $1,057 and is subject to variations in the Consumer
      Price Index, All Groups Brisbane from December 2007 until the date of payment. An
      Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
      Planning Act 1997
5.    The applicant is informed that payment via credit card transaction will not be an acceptable
      method of payment for development contributions conditioned in this permit or for
      infrastructure charge notices issued separately.
6.    The applicant is advised that a Compliance Permit for all plumbing and drainage works within
      the boundaries of the development site shall be obtained from Council’s Plumbing Services
      Section prior to obtaining a Development Permit for Building Works.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.




                                                                                              6 of 9

Page 7

                                                   -7-


8      PROPERTY NOTES

Not applicable

9      PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable

10     FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required             Subject of the required Development Permit
 Development Permit for Building Works           All Building Works

 Development        Permit   for   Operational   Landscaping, Car Parking & Access, Frontage
 Works                                           Works, Stormwater Drainage & Filling of the site.

11     SELF ASSESSABLE CODES

The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Nil

12     SUBMISSIONS

Not applicable

13     REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable

14     RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).

15     OTHER DETAILS

Please note that an Infrastructure Charge in accordance with the Coastal Major Road Network
Infrastructure Charges Plan has been triggered by the approval of this development application. An
Infrastructure Charge Notice is attached in compliance with Chapter 5 of the Integrated Planning Act
1997.
Should you wish to obtain more information about Council’s decision electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,




Tracy Arthur
SENIOR PLANNING OFFICER



                                                                                         7 of 9

Page 8

                                                                      -8-




                                                         Appeal Rights
                                                        INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated                                 (6) If an application involves assessment against a
Planning Act (Chapter 4).                                                   concurrence agency code, appeal rights for submitters
                                                                            for the application are not available against the part of
Division 8 - Appeals                 to   court     relating    to          the approval that represents the concurrence agency’s
development applications                                                    response for the code.
Appeals by applicants                                                       Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application                       4.1.29.(1) An advice agency may, within the limits of its
may appeal to the court against any of the following-                       jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development                   development approval for a development application if-
      application;                                                          (a) the development        application   involves   impact
(b) a matter stated in a development approval, including                       assessment; and
      any condition applying to the development, and the                    (b) the advice agency told the applicant and the
      identification of a code under section 3.1.6;1                           assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a                         application as a submission for an appeal.
      development permit was applied for;                                      (2) The appeal must be started within 20 business
(d) the length of a currency period;                                        days after the day the decision notice or negotiated
                                                                            decision notice is given to the advice agency as a
(e) a deemed refusal.
                                                                            submitter.
    (2) An appeal under subsection (1)(a) to (d) must be
                                                                            Appeals for matters arising after approval given (co-
started within 20 business days (the “applicant’s
                                                                            respondents)
appeal period”) after the day the decision notice or
negotiated decision notice is given to the applicant.                       4.1.30.(1) For a development approval given for a
                                                                            development application, a person to whom any of the
    (3) An appeal under subsection (1)(e) may be
                                                                            following notices have been given may appeal to the
started at any time after the last day a decision on the
                                                                            court against the decision in the notice-
matter should have been made.
                                                                            (a) a notice giving a decision on a request for extension
Appeals by submitters
                                                                               of the currency period for an approval;
4.1.28.(1) A submitter for a development application
may appeal to the court about-                                              (b) a notice giving a decision on a request to make a
                                                                               minor change to an approval.
(a) the giving of a development approval, including any
      conditions (or lack of conditions) or other provisions                   (2) The appeal must be started within 20 business
      of the approval; or                                                             days after the day the notice of the decision is
                                                                                      given to the person.
(b) the length of a currency period for the approval.
                                                                               (3) Subsection (1)(a) does not apply if the approval
    (2) The appeal must be started within 20 business                                 resulted from a development application
days (the “submitters appeal period”) after the day                                   (superseded planning scheme) that was
the decision notice or negotiated decision notice is given                            assessed as if it were an application under a
to the submitter.                                                                     superseded planning scheme.
    (3) If a person withdraws a submission before the                          (4) Also, a person who has made a request
application is decided, the person may not appeal the                                 mentioned in subsection (1) may appeal to the
decision.                                                                             court against a deemed refusal of the request.
    (4) If an application involves both impact                                 (5) An appeal under subsection (4) may be started
assessment and code assessment, appeal rights for                                   at any time after the last day the decision on the
submitters are available only for the part of the                                   matter should have been made.
application involving impact assessment.
                                                                            Division 9 - Appeals to court about other matters
    (5) If an application is processed under section
6.1.28(2), appeal rights for submitters for the application                 Appeals for matters arising after approval given (no
are available only for the aspects of the development                       co-respondents)
that would have required public notification under the                      4.1.31.(1) A person to whom any of the following notices
repealed Act.                                                               have been given may appeal to the court against the
                                                                            decision in the notice-
                                                                            (a) a notice giving a decision on a request to change or
                                                                               cancel a condition of a development approval.
1
    Section 3.1.6 (Preliminary approval may override local planning
    instrument)




                                                                                                                     8 of 9

Page 9

                                                                      -9-


(b) a notice under section 6.1.442 giving a decision to                     (d) the length of a period mentioned in section 3.5.21
      change or cancel a condition of a development                            currency period;
      approval.                                                             (e) a deemed refusal.
      (2) The appeal must be started within 20 business                         (2) An appeal under subsection (1)(a) to (d) must be
          days after the day the notice of the decision is                  started within 20 business days (the “applicant’s
          given to the person.                                              appeal period”) after the day the decision notice or
      (3) Also, a person who has made a request                             negotiated decision notice is given to the applicant.
          mentioned in subsection (1)(a) may appeal to                          (3) An appeal under subsection (1)(e) may be
          the court against a deemed refusal of the                         started at any time after the last day a decision on the
          request.                                                          matter should have been made.
      (4) An appeal under subsection (3) may be started                     The Registrar for the Building and Development
        at any time after the last day the decision on the                  Tribunal may be contacted at the website
        matter should have been made.                                       http://www.localgovernment.qld.gov.au/
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a decision
made on an application to change the conditions
attached to an approval given under section 2.19(3)or
section 4.4 of the repealed Act may appeal to the court
against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions applied
under a local law about the use of premises or the
erection of a building or other structure permitted by the
planning scheme may appeal to the court against the
decision or the conditions applied.
   (2) The appeal must be started within 20 business
days after the day notice of the decision is given to the
applicant.
For Building Works Only
Rights of appeal conferred by Section 4.2.9 of the
Integrated Planning Act 1997 as follows:
Division 3 – Appeals to tribunals relating to
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal
against any of the following-
(a) the refusal, or the refusal in part, of a development
      application;
(b) a matter stated in a development approval, including
      any condition applying to the development, and the
      identification of a code under section 3.1.6;3
(c) the decision to give a preliminary approval when a
      development permit was applied for;

2
    Section 6.1.44 (Conditions may be changed or cancelled
    by assessment manager or concurrence agency in certain
    circumstances)
3
    Section 3.1.6 (Preliminary approval may override local planning
    instrument)




                                                                                                                  9 of 9

Used in these records

About this file

File size
67 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000203.001 [As Published].pdf · 67 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.