Delegated Report - Code - Planning OPW22 0299 [As Published] · OPW22/0299
DEVELOPMENT ASSESSMENT DELEGATED REPORT
Author Coordinator Engineering, Mark Lewis
Development Assessment
APPLICATION DETAILS
Application No. OPW22/0299
Applicant Mark Bain Constructions Pty Ltd
Proposal Operational Works - Drainage Works, Earthworks, Landscaping,
Roadworks, Stormwater, Clearing Vegetation under planning
scheme
Properly Made Date 30 November 2022
Information Request Date 20 December 2022
Information Response Date 1 February 2023
Decision Due Date 18 April 2023
Report Reviewed & Daniel Epps
Finalised By
PROPERTY DETAILS
Property Address 10 Natasha Ave Noosa Heads Qld 4567, 24 Katharina Street
Noosa Heads Qld 4567
RP Description Lot 2 RP 122891 & Lot 135 RP 92518
Land Area 1523 m² & 516 m²
Existing Use of Land Residential
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone Medium Density Residential
Precinct Not Applicable
Local Plan Area Noosa Heads Local Plan Area
Overlays Bushfire Hazard Overlay
Landslide Hazard Overlay
Assessment Type Code
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 16 pages
Page 2
1. PROPOSAL
The application seeks approval for Operational Works - Drainage Works, Earthworks,
Landscaping, Roadworks, Stormwater, Clearing Vegetation under planning scheme.
The locality and proposal plan are included below.
Figure 1 – Locality
Page 2 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 3
Figure 2 – Site Plan
2. SITE DETAILS
2.1. Background
The works are required to address a number of conditions of the associated higher order approval
MCU21/0231.01
3. ASSESSMENT
3.1. Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following
statutory planning instruments to the extent they are relevant to the development:
• State Planning Policy;
• South East Queensland Regional Plan;
• Planning Regulation 2017; and
• Noosa Plan 2020.
3.2. Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
• Works Codes;
• Landslide Overlay Code;
• Landscaping Code
The application has been found to generally comply with all applicable statutory instruments.
Page 3 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 4
4. CONSULTATION
4.1. Referral Agencies
Not Applicable
4.2. Internal Council Referrals
The application was forwarded to the following internal Council officers for review and/or comment:
• Senior Environment Officer
• Infrastructure (design)
5. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme and
does not raise any significant issues that cannot be addressed by reasonable and relevant
conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW22/0299 for Operational Works - Drainage Works, Earthworks,
Landscaping, Roadworks, Stormwater, Clearing Vegetation under planning scheme situated at 10
Natasha Ave Noosa Heads Qld 4567 and 24 Katharina Street Noosa Heads Qld 4567 and
described as Lot 2 RP 122891 & Lot 135 RP 92518, it is recommended the application be approved
in accordance with the following details for the Decision Notice:
1. APPLICATION DETAILS
Application No: OPW22/0299
Street address: 10 Natasha Ave Noosa Heads Qld 4567 and 24 Katharina Street
Noosa Heads Qld 4567
Real property description: Lot 2 RP 122891 & Lot 135 RP 92518
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for Operational Works - Drainage Works, Earthworks, Landscaping,
Roadworks, Stormwater, Clearing Vegetation under planning scheme
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
21617-C001 B Locality Plan & Drawing 30 January
Index prepared by TOD 2023
Page 4 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 5
Engineers and Project
Management
21617-C100 B Nominal Bulk Earthworks 30 January
prepared by TOD 2023
Engineers and Project
Management
21617-C200 B General Arrangement 30 January
prepared by TOD 2023
Engineers and Project
Management
21617-C201 B Site Sections prepared 30 January
by TOD Engineers and 2023
Project Management
21617-C202 B Roadworks Sections 30 January
prepared by TOD 2023
Engineers and Project
Management
21617-C301 B Stormwater Drainage 30 January
Details and Calculations 2023
prepared by TOD
Engineers and Project
Management
ED 22116 OPW-01 A Sheet Layout Plan 9 November
prepared by Element 2022
Design
As amended by
conditions
ED 22117 OPW-02 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-03 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-04 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-05 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
Page 5 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 6
ED 22116 OPW-06 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-07 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-08 A Details Plan prepared by 9 November
Element Design 2022
As amended by
conditions
ED 22116 OPW-09 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
ED 22116 OPW-10 A Planting Plan prepared 9 November
by Element Design 2022
As amended by
conditions
22_10_31_AIA_Markbain_Natas 1 Arboricultural Impact 31 October
ha Katharina Assessment by Consult 2022
Arborist
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 18 April 2025, unless an application to extend the currency period is
approved by Council.
Site Specific Conditions
3. All earthworks and associated retaining structures/batters, both above and below ground,
both temporary and permanent, must be contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
4. Prior to requesting a prestart meeting:
a. Submit to Council updated landscape plans that include all changes approved as part
of the higher order MCU22/0231.01amended plans approval.
b. Submit to Council the Fauna Management Plan.
c. Tree protection fencing must be installed under the supervision of the qualified person*.
(Refer to Advisory Note)
*(Refer to Advisory Note)
PRIOR TO COMMENCEMENT OF WORKS
Engineering
5. Tree protection fencing must be installed under the supervision of the Project Arborist. (Refer
to Retention of Existing Trees Conditions).
Page 6 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 7
6. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
7. A condition report of the Council drainage system in Katharina Street must be completed for
agreement at the prestart meeting. The condition report is to include a CCTV inspection of
the existing pipe and structures and must include the existing pits and pipes located in the
frontage of No 22 Katharina Street and extend to the existing pits and pipes in the frontage
of No 28 Katharina Street.
8. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting / prior to any works commencing.
9. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
10. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Arboreal works.
c. Fauna management works.
d. Landscape works;
e. Erosion and sediment control works;
f. Other relevant parties
11. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe vehicle and pedestrian access across the frontages of the
site both during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining owners
and emergency services to advise of agreed construction times, impacts on traffic and
services and other relevant issues
e. Include a post out to the local residents advising of the proposed development, the
expected time frames and the site contact details
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
Page 7 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 8
i. contact details for the on-site manager
ii. dispute resolution procedures
h. details on the location of external fill/dump sites, the haulage route, type of vehicle to
be utilised during filling operations and frequency of usage. NB any damage to the
existing road system as a result of haulage operations must be fully repaired at the
applicant’s expense.
12. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
13. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
14. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
15. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
16. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. The relevant conditions of the higher order Material Change of Use approval viz.
MCU22/0299.01 to which this approval relates
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
Roadworks (External Roadworks & Road Widening Works)
17. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
18. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
19. The developer must notify Council’s Traffic Engineer for any works involving the removal or
modification of existing Council traffic signs and/or parking bays prior to such works
commencing.
20. Root barriers are required to be installed behind the back of kerb for all new kerbs within 5m
of a trunk of a tree.
Page 8 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 9
Pavement Design and Construction
21. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveways and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
22. Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
23. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
24. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Pathways
25. All pathways must be constructed in accordance with the following requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
b. Provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards.
c. All paths must have a slip resistant surface.
d. Expansion and contraction joints must provide a flush finish. Installation of joints by
saw cutting is preferred to ensure a smooth ride for cyclists.
e. The required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
26. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety.
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Site Access and Driveways
27. Driveway crossovers must be constructed in accordance with Council’s Standard Drawing
RS-049, RS-050 and any associated addendum.
28. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf, and must be maintained by the developer until established.
29. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties.
Page 9 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 10
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path.
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
30. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with the Standard.
31. Fall protection must be provided to retaining walls that are over 1m high.
32. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies
b. 1 in 4 for grassed areas.
c. 1 in 3 for planted areas.
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
33. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
34. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (eg by blocking or interfering with natural overland flows).
35. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
36. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
37. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
Page 10 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 11
38. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
39. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
40. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
41. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Landscape
Retention of Existing Trees and Vegetation
42. All trees and vegetation identified for retention must be protected in accordance with AS
4970, Protection of trees on development sites.
43. A qualified person * must be engaged for the duration of the works to:
a. Ensure works are carried out in accordance with the approved Arborist Report
b. Oversee installation of all tree protection fencing prior to commencement of any works
onsite (including any clearing).
c. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
d. Supervise and undertake necessary tree protection for all trees affected by the
development on neighbouring Lots. This includes tree identified in Appendix 3 of the
approved arborist report that are identified as outside project scope – TPZ conflict.
e. Oversee approved tree removal in proximity to retained trees.
f. Undertake a risk assessment of all trees on neighbouring properties affected by the
development within striking distance of the development works and site and carry out
hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity
trees.
*(Refer to Advisory Note)
Fauna Management
44. A qualified person* must be engaged to manage fauna in accordance with a fauna
management plan submitted prior to a prestart meeting. The fauna management plan must
include the following:
a. Ensure works are carried out in accordance the Nature Conservation Act 1992.
b. Undertake pre-clearing inspections including fauna relocation and removal or blocking
of all vacant hollows.
Page 11 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 12
c. Ensure clearing works avoids nesting times of animals and birds.
d. Co-ordinate staging and sequence of clearing with fauna protection.
e. Protect and recover fauna during clearing operations.
f. Manage the translocation of animals and recovery procedures in accordance with
relevant legislation.
g. Undertake protection works for mulching of any stockpiled vegetation.
*(Refer to Advisory Note)
Removal of Existing Trees and Vegetation
45. Removal of existing trees and vegetation must be undertaken by a qualified person* and
must include:
a. Stump grinding to below finished surface level.
b. Rectification to the finished surface levels and materials.
c. No damage to other vegetation for retention.
d. Legal disposal of all removed vegetation and debris.
e. Replanting at a ratio of 5 replacement trees of the same species for each removed
tree.
*(Refer to Advisory Note)
46. Vegetation removal, felling and lopping must:
a. Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
b. Mulch all other wood and leaf material (without root balls, soil or debris and minimising
weed seeds) for re-usable mulch.
c. Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
of three months.
d. Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
between piles.
e. Allow for existing endemic ground flora to be translocated to suitable landscaping and
rehabilitation areas.
f. Conclude with the area being stabilised against erosion, landscaped, rehabilitated and
revegetated.
*(Refer to Advisory Note)
Landscaping Works
47. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice. Updated landscape plans
must be resubmitted prior to a prestart meeting that include all changes approved as part of
the higher order MCU22/0231.01.
(* Refer to Advisory Note)
48. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
49. Landscape works must:
a. Ensure amenity or sales signage and ancillary infrastructure is not installed within the
road reserve.
b. Ensure permanent irrigation is not installed within the road reserve.
Page 12 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 13
c. Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
applied to all planting areas to ensure a minimum 100mm depth once settled.
(* Refer to Advisory Note)
50. Public amenity trees* must:
a. Meet AS 2302 – Tree Stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
c. Be located from services and infrastructure a minimum of:
i. 6m from electricity poles and pillars.
ii. 4m from street lighting.
iii. 2m from stormwater catchment pits.
iv. 2m from any adjoining driveway.
*(Refer to Advisory Note)
51. Turfed areas must be free of pest, diseases and weeds and level with adjoining surfaces.
52. Soil for landscaping must:
a. Provide for healthy and sustained site specific vegetation performance.
b. comply with AS 4419, Soils for landscaping and garden use.
Damage to Services and Assets
53. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO COMMENCEMENT OF THE USE
Certification
54. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
55. Prior to commencement of use the following (prepared by respective qualified persons* and
certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification.
b. Arboreal certification.
c. Fauna Report documenting the findings and outcome of the fauna protection works
undertaken.
Bonds
56. Bonds must:
a. meet the requirements of council’s relevant Planning Scheme Policy for performance
and uncompleted works.
b. be calculated using a schedule of works and relevant bond equation.
c. have approval of the bond calculations and amount from Council prior to lodgement
Page 13 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 14
d. be lodged with Council and accompanied by the Bond Administration Fee/s.
e. be requested for release by writing to Council, when relevant approval requirements
have been met.
As Constructed Plans and ADAC XML Files (Council)
57. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
e. Landscaping, including all assets and improvements within parks, open space and road
reserves areas are to be shown on an accompanying separate landscape plan
(prepared in .dwg file format with accompanying hardcopy PDFs) and include a
complaint ADAC XML file. Details of the landscaping and all associated assets and
improvements may be included in the ADAC XML digital file prepared for associated
civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
containing landscape and asset information only.
On Maintenance
58. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
a. certification that all works have been undertaken and completed in accordance with the
requirements of this Permit.
b. as Constructed details in accordance with Council’s Planning Scheme Policy.
c. maintenance and operational manuals for all proprietary or site specific devices
Off Maintenance
59. Prior to requesting an Off Maintenance inspection the developer must provide a written
request for the Off Maintenance inspection.
60. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
Page 14 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 15
a. a Council inspection reveals works do not comply with approval requirements
b. submitted certification falsely states works comply with approval requirements.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. As the driveways are private structures, the owner bears full responsibly for the standard of
their construction, maintenance and any liabilities associated with their construction. It is
recommended that professional advice be sought for the construction of the driveways to
ensure that the driveways are constructed in accordance with the relevant standards.
2. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
3. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
4. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
5. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days notice of preferred inspection time.
6. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
7. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise.
Environmental Advisory Notes
8. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
9. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
10. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
Page 15 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 16
11. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the final inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
Retention of Existing Trees
12. The existing trees on adjoining properties must be retained and protected during construction
wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
13. Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
well as optimum weed seed sterilisation.
Qualified Person
14. Qualified Person, for the purpose of:
a. Supervising landscape works and preparing a landscape certification, is considered to
be a landscape architect, landscape designer or horticulturist with a minimum of three
years current experience in the field of landscape design.
b. Undertaking landscape construction and establishment works is considered to be a
person with five years current experience in commercial landscape construction
projects.
c. Undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and assessment and either:
iii. International Society of Arboriculture (ISA) certification; or
iv. A Diploma of Arboriculture.
d. Undertaking Fauna site works and calculating compensatory habitat is considered to
be a Fauna Spotter Catcher with current certification under the Queensland Parks and
Wildlife Service.
e. Preparing certification and managing declared plant pests, is considered to be:
v. an environmental consultant with a minimum of 3 years current experience in the
field of pest plant management.
f. Assessing and certifying soil quality is considered to be an Agronomist or
Horticulturalist with three years current experience in soil testing.
Landscape Works
15. The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
Register where:
a. An inspection revealed that any constructed rehabilitation/landscape works do not
comply with the conditions of the Decision Notice, Approved Plans and or Approved
Documents
b. Certification is submitted to Council falsely stating that works comply with the approved
plans, documents and or conditions of the Decision Notice.
Page 16 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Page 17
16. Public amenity trees are defined as any tree located within public streets, parks or areas that
will become publicly owned as a result of this development.
Aboriginal Cultural Heritage Act 2003
17. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Not applicable.
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Page 17 of 17
Document Set ID: 22368529
Version: 4, Version Date: 19/04/2023
Used in these records
Delegated Report - Code - Planning OPW22 0299 [As Published].pdfRelated documentApplication case desk ↗
About this file