Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 6 April 2023, requesting a minor change to an existing
development approval. Council decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: MCU16/0090.02
Street address: 468 Mckinnon Drive, Cooroibah
Real property description: Lot 2 RP 214534
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
The following type of approval was issued on 15 December 2016.
• Development Permit for Material Change of Use of Premises - Wellbeing Type 2 – Social
In relation to the request to make a minor change to the existing approval, Council on 20 July 2023,
decided to approve the requested changes. The changes are detailed below.
A. Approve the change.
B. Amend conditions 1 and 2.
C. Include additional conditions 27 and 28.
3. CURRENCY PERIOD OF APPROVAL
Not applicable
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 8 pages
Page 2
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
L002 A Landscape Concept Plan, prepared by Sunshine 20.9.2015
Gardens
2003- A Site Plan, prepared by Taylour’D Distinction 13 July 2020
1677
SK02 E Sunshine Butterflies Private Café – Site Plan 11 April 2023
(dated by Council)
SK04 E Sunshine Butterflies Private Café – Ground Floor Plan 11 April 2023
(dated by Council)
SK05 E Sunshine Butterflies Private Café – Elevations – Sheet 1 11 April 2023
(dated by Council)
SK06 C Sunshine Butterflies Private Café – Sections – Sheet 1 11 April 2023
(dated by Council)
Nature and Extent of Approved Use
2. The approved use is Wellbeing Type 2 – Social being for a respite centre for people living
with disabilities and their families and associated ancillary office and agricultural uses. The
approval includes an ancillary café (serving only the needs of staff and clients of the approved
use and is not to be open to the general public).
3. The maximum number of special events per year is six (6).
Landscaping
4. Existing trees on the site and within road reserves must be retained, except where required
to be removed to accommodate the approved use.
5. All native trees must be retained within the Biodiversity Overlay. The area must be
rehabilitated with koala food trees such as Eucalyptus robusta, Eucalyptus tereticornis and
Eucalyptus grandis
6. Screening vegetation must be planted along all boundaries in accordance with Council’s
Planning Scheme Policy PSP3 Landscaping Plants and Guidelines and the approved
Landscape Concept Plan. The planted vegetation must consist of native and endemic
species.
7. A minimum of 3m of screening vegetation must be provided between the boundary and any
car parking.
Built Form and Setbacks
8. The maximum height of the development must not exceed 9 metres at the pitch of the roof
above the finished ground level and the natural ground level and must not exceed 2 storeys.
Page 2 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 3
9. All buildings and structures must be setback a minimum of 6 metres from all boundaries.
Performance Bond
10. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Operational Works. The cash bond or trading bank
guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Street Identification
11. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
developments name.
ENGINEERING
Site Access and Driveways
12. Sealed access driveways must be provided from McKinnon Drive to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
the Department of Infrastructure, Local Government and Planning response reference
number SDA-0816-032888 dated 7 November 2016 and generally in accordance with
Council’s standard drawing RS-056.
13. Approval from the Department of Transport and Main Roads for the final design of the site
access and driveway works must be submitted in writing to Council prior to the issue of any
Development Permit for Operational Works.
Car Parking
14. A minimum of 21 car parking spaces must be provided and marked on the site and made
available and accessible at all times while the use is open for business. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. service vehicle parking, manoeuvring and standing spaces
b. dimensions, crossfalls and gradients in accordance with Australian Standards
AS/NZS2890.1:2004, AS/NZS2890.6:2009 and AS2890.2:2002.
15. The carparking area must be constructed with either a sealed surface or other bound material
that is suitable for the intended use. Certification of the proposed surfacing from an RPEQ
must be submitted as part of the operational works application.
16. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
17. Directional signage must be provided to direct visitors and guests to the car parking spaces
provided on site.
Traffic Management
18. A traffic management plan for both the regular operation of the development and any special
events must be submitted as part of the Operational Works application. The traffic
management plan must include but not be limited to:
a. day to day parking of the various vehicle types
b. parking for larger vehicles (buses, deliveries, waste collection etc)
c. overflow parking for special events
d. temporary traffic control measures on McKinnon Drive
e. endorsement by the Department of Transport and Main Roads.
Page 3 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 4
Stormwater Drainage
19. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. collection of runoff from the buildings and hardstand areas
b. collection of runoff from the carparking areas and access aisles
c. certification from an RPEQ that states the development of the site will not create a
worsening for downstream properties in regard to stormwater quality or quantity.
Earthworks and Retaining Walls
20. All fill and associated batters must be contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
21. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Noise
22. Mechanical plant and equipment, a/c units, motors, refrigeration equipment, compressors,
pumps etc on site should be situated within the building or suitably provided with noise
reduction measures and located as to prevent a noise nuisance beyond the boundary of the
site and not exceed the levels specified in Table 1.
TABLE 1
NOISE LIMITS AT A SENSITIVE RECEPTOR
Noise level at noise sensitive place measured as the adjusted
PERIOD
maximum sound pressure level (L10, adj,T)
7am – 6pm Background noise level (L90,T) plus 5 dB(A)
6pm – 10pm Background noise level plus 5 dB(A)
10pm – 7am Background noise level plus 3 dB(A)
NOISE LIMITS AT A COMMERCIAL PLACE
Noise level at a commercial place measured as the adjusted
PERIOD
maximum sound pressure level (L10, adj,T)
7am – 6pm Background noise level (L90,T) plus 10 dB(A)
6pm – 10pm Background noise level plus10 dB(A)
10pm – 7am Background noise level plus 8 dB(A)
Page 4 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 5
23. When requested by Council, a Noise Impact Assessment Report (NIAR) showing monitoring
and recording of noise levels must be undertaken to investigate any complaint (other than a
frivolous or vexatious complaint) caused by noise emissions from operations at the premises.
Such monitoring must be undertaken within a reasonable and practicable timeframe
nominated by Council and be performed by a suitably qualified person in accordance with
accepted guidelines and standards. The report must be submitted to Council detailing the
results of such monitoring and recommendations for any measures to achieve compliance
with limits outlined in Table 1 of this Decision Notice.
For the purpose of measuring and certifying relevant noise conditions and reporting (e.g.
mechanical plant and equipment, a/c units, motors, refrigeration equipment, compressors,
pumps, rooftop plant and equipment. etc) a suitably qualified person is either:
i) a Registered Professional Engineer of Queensland, or
ii) an environmental consultant with a minimum of three (3) years current experience in
the field of acoustics.
Public Health Act 2005 - Rainwater Tanks
24. In accordance with the Public Health Act 2005, rainwater tanks must be constructed with
mosquito proof screens (made from either brass, copper, aluminium or stainless steel), and
constructed with a mesh size of no more than 1mm, and must be installed in a way that does
not accelerate corrosion. Tanks that contain flap valves must be installed so that when
closed, mosquitoes cannot pass through the valve. It is unlawful under the Public Health Act
2005 to construct, install or be in possession of a tank that does not comply with these
requirements.
25. Where it is intended to use rainwater for drinking purposes, a suitable treatment system is
required to be installed to disinfect or treat the water to microbiological and physical
standards as described in the current Australian Drinking Water Guidelines 2011 to make it
fit for drinking purposes.
Refuse
26. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and
Industrial Premises”, including an external imperviously paved area correctly sized for all
refuse and recycling containers and suitably screened from public places and neighbouring
properties.
Additional Conditions
20 July 2023
27. No signage is to be provided on the development site or road reserve advertising the café.
28. Prior to the Final Certificate being issued for the building works ancillary café, a car parking
plan is to be provided demonstrating compliance with Conditions 14 -18.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
PLANNING
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
Page 5 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 6
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations
under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
3. Prior to the commencement of the use, please contact Council's DA Planning Section to
arrange a Development Compliance Inspection.
Infrastructure Charges
4. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
ENGINEERING
Building and Construction Industry (Portable Long Service Leave) Levy
5. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
Co-ordination of Operational Works Assessment
6. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
7. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Traffic management during all aspects of the construction phase including:
i. A Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
ii. Proposed fencing to the site during the construction phase of the development
iii. Approval of the Traffic Management Control Plan by the Department of Transport
and Main Roads (DTMR) for any works on State controlled roads
Page 6 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 7
iv. provision for worker car parking
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures
c. works programme identifying key components of the works and their respective
durations
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic, services and other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
It is acknowledged that the preliminary Construction Management Plan will be a draft document
requiring finalisation upon appointment of the Principal Contractor employed to construct the works
and a final document will be required to be submitted at the Pre-Start Meeting for the project.
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Driveway/Access and Stormwater Drainage
Development Permit for Building Works All Building Works
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Patrick Murphy
Manager - Development and Regulation
Page 7 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 8
Enc: Infrastructure Charge Notice
Approved Plans/Documents
cc. Unitywater
DECISION NOTICE HISTORY
• Original Decision Notice – 15 December 2016.
• Decision Notice – GIA – MCU16/0090.01 - 3 September 2020.
• Decision Notice - Minor – MCU16/0090.02 - 20 July 2023, with an amendment to conditions 1 and 2 and additional conditions 27
and 28.
Page 8 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Page 9
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 9 of 9
Document Set ID: 22519582
Version: 1, Version Date: 26/07/2023
Used in these records
Amended Notice - Council Meeting - Decision Notice - Minor Change - MCU16 0090 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 174 KB (small file)
- File type
No other editions are linked here.