PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 10 AUGUST 2021
Section 10.4 Schedule of Council Adopted Infrastructure Charges (under breakup agreement)
Update the base date to 1 July 2021 for the 2021-2022 Financial Year with Table 10.3 Schedule of
Council adopted charges updates to:
• Column 2 to the current “Planning Regulation 2017 Schedule 16 Prescribed amounts” updated
by the State Government on 1 July 2021 as inserted by the “Planning Legislation (Fees and
Other Amounts) Amendment Regulation 2021”;
• Column 3 “Council Charges” updated in accordance with the Charges breakup agreement with
Unitywater of the updated Prescribed amounts in Column 2; and
• Column 4 “Council Included Reductions” updated amounts maintaining unchanged previous
proportioned (percentage) reductions.
Previous Council Consideration
Ordinary Meeting Minutes, 28 August 2014, Item 2, Page 6
That Council note the report by the Priority Infrastructure Planning and Infrastructure Charges Officer
to the Planning & Organisation Committee dated 28 January 2014 and:
1. Adopt the “Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014”
(provided at Attachment 1 to the report) to replace the “Sunshine Coast Regional Council
Adopted Infrastructure Charges Resolution (No.4) 2011” applying to development governed
by The Noosa Plan;
2. Publicly notify the adoption of the “Noosa Shire Council Adopted Infrastructure Charges
Resolution (No.1) 2014” and forward a copy to the Chief Executive, Department of State
Development, Infrastructure and Planning in accordance with section 648D of the
“Sustainable Planning Act 2009”;
3. Adopt Noosa Council policy positions regarding Extensions to Relevant Periods (through
infrastructure agreements) and/or subsequent Infrastructure Charge Notices triggered by
Building Permits, to charge development for all networks, including those previously missing
where:
a) missing networks are to be charged at the current Adopted Infrastructure Charges; and
b) the missing network charge is limited so that it does not cause the total amount
payable for the development to exceed the total maximum adopted charge
permissible under the “Statutory Planning Regulatory Provision (adopted charges)”.
4. For development requesting to transfer to an alternative infrastructure charges regime to that
previously applied under an existing development approval, Council:
a) require a new development application to be lodged; and
b) offer a 50% reduction to the application fee for these new development applications,
provided there is no change to the development previously approved and no additional
assessment is required to that previously undertaken under The Noosa Plan; and
c) request the applicant to cancel their previous development approval under sections 379
and 380 of the “Sustainable Planning Act 2009” at no cost to the applicant, once a dew
development approval takes effect.
5. Note the State Government’s review of the current Adopted Infrastructure Charges regime is
likely to impact the level of infrastructure charges that can be levied on future development and
priority infrastructure planning requirements. A further report will be provided to Council once
the outcome is known.
Page 81 of 165
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.