Davis Rd Cootharaba DA Planning Report
Attached to the e-mail MCU15/0061 Development Application - Planning report and IDAS forms Email 1 of 2.
Table 6.2 - State Planning Policy Codes
State Interest Assessment Compliance
Biodiversity – A development application where The subject site is identified
• MSES – Wildlife habitat the land relates to a matter of under the SPP mapping as
state environmental significance, containing Wildlife Habitat. The
if the application is for: proposed facility is not
a) operational work, or considered to negatively impact
b) a material change of use on Matters of State
Environmental Significance
other than for a dwelling
(MSES), for the following reasons:
house, or
• The proposed facility will be
c) reconfiguring a lot that
located south of a previously
results in more than six lots
disturbed area that has been
or lots less than five
cleared for overhead power.
hectares.
• The proposed clearing for the
300 m² compound area will
Development: not impact on EVNT species as
1. Enhances matters of state a flora and fauna survey was
environmental significance undertaken in March 2015 by
where possible, and Aurecon ecologists and no
2. Identifies any potential EVNT species were observed
significant adverse (refer to Appendix 4).
environmental impacts on • All construction activities will
matters of state be managed to avoid any
environmental significance, sediment run-off during the
and construction period in
3. Manages the significant accordance with NBN’s
adverse environmental contractor’s Construction
impacts on matters of state Environmental Management
environmental significance Plan.
by protecting the matters of
state environmental
significance from, or
otherwise mitigating, those
impacts.
Water Quality – Water quality is to ensure The proposed telecommunication
• Climatic regions: development is planned, facility will not negatively impact
stormwater designed, constructed and on water quality, for the
management design operated to manage stormwater following reasons:
objectives and wastewater in ways that • The need for drainage and
support the protection of erosion/sediment control
environmental values identified measures is unlikely given
in the Environmental Protection the minor ground
(Water) Policy 2009. disturbance during the
construction phase.
However, the NBN Co.
compound foundation will
have a gravel finish to aid in
the dissipation of
stormwater on-site; and
• The minor addition of the
NBN-4BBZ-4GYM-5125 – David Cootharaba Page 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.