SUPERSEDED - Minor Change Existing Approval 132007 2399 02 · 132007.2399.02
46. Prior to endorsement of the Plan of Survey for Stage 1, the new parcel shall be connected
to Council’s existing sewerage reticulation systems and be constructed in accordance with
Council’s standards and requirements at no cost to Council. This work may be covered by
an uncompleted works bond at 150% of the value of the connection that can be in place for
a duration agreed to by the Manager Land Development.
47. Prior to endorsement of the Plan of Survey for Stage 2, the existing sewer main, rising main
and effluent main that traverse the site shall be relocated generally in accordance with Tate
Professional Engineers drawing No. C1732/07/J/P04 dated 19/11/07.
48. Prior to endorsement of the Plan of Survey for Stage 2, if required the applicant shall upgrade
any existing sewer services (including pumps or pump station) at no cost to Council.
49. To ensure Council’s sewer main is accessible for maintenance purposes and is protected
from risk of damage no structures requiring a building permit (eg. buildings, swimming pools,
retaining walls exceeding 1m in height, raised terraces, etc) shall be constructed within this
‘zone of influence’ or within 1.5m of the centreline of the sewer main, whichever is the greater.
As such the applicant shall amend Operational Works plans including Building plans to
ensure compliance.
50. Design for a sewerage system to connect all new lots within the site to Council's existing
sewerage reticulation system shall be to the standards and requirements set out in Council’s
Engineering Design Standards. If the design requires the construction of a pump station and
a rising main, the connection point to Council's existing system will be nominated by the
Manager - Land Development.
51. All connections to sewer system shall be carried out either by Council or by a Council
approved Contractor and at no cost to Council.
Town Water Supply
52. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
53. Prior to endorsement of the Plan of Survey for Stage 1, the newly created parcel shall have
a single water connection to the water reticulation system, which shall extend to the property
boundary and be metered. This work may be covered by an uncompleted works bond at
150% of the value of the connection that can be in place for a duration agreed to by the
Manager Land Development.
54. Prior to endorsement of the Plan of Survey for Stage 2. the development shall be served by:
• A single Body Corporate water meter to measure the total water consumption
(including fire hose reels, but excluding fire hydrants and fire sprinkler systems), and
• Individual water meters to each tenement capable of being separately rated, and
• A fire service (fully testable single detector check with metered bypass), where
applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
reels).
55. All fees for the supply of water meters shall be paid to the Council.
56. All water meters must be located outside the property boundary and in an easily assessable
location to facilitate unhindered reading by Council and/or Council’s contracted water meter
readers, and not behind fences or locked gates. In this regard approval of the water meter
configuration and location must be obtained from Council’s Water & Sewerage Capital Works
Manager prior to lodgement and approval of hydraulic drawings.
57. Fire hydrants are to be provided throughout the development in accordance with Council
Engineering Design Standards and in accordance with Queensland Fire Service Standards.
58. Any connection to a water main shall be undertaken by Council.
Service Easements (Sewer / Stormwater)
Page 8 of 18
Document Set ID: 22620408
Version: 5, Version Date: 19/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Minor Change Existing Approval 132007 2399 02.pdfRelated documentApplication case desk ↗
Minor Change Existing Approval 132007 2399 02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 211 KB (small file)
- File type
No other editions are linked here.