5.3 Year 2036 capacity analysis – Noosaville / Noosa Heads / Sunshine
Beach
Capacity analysis under predicted year 2036 peak hour conditions for both the non-holiday and
the holiday / special event periods indicates degrees of saturation (DOS) at strategic
intersections within the Noosaville / Noosa Heads / Sunshine Beach area at peak times, with
existing intersection configurations, as depicted in Figure 15.
Figure 15: Year 2036 AM and PM peak hour Degrees of Saturation in Noosaville / Noosa
Heads / Sunshine Beach
The critical traffic related issues in this part of the network, without upgrading of that network,
under projected 2036 traffic loadings are:
(i) Weyba Road / Reef St / Mary St intersection
(ii) Noosa Dr / Noosa Pde intersection
(iii) Ben Lexcen Dr / Eenie Ck Rd intersection
Each of those issues, together with recommended solutions, are discussed hereunder.
14.s.53.7 Page - 32
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.