Original source · versioned page text
Refernce Documents - RAL25 0001
Very large file (28.3 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Table 2: Rehabilitation Procedures RCP04: Rehabilitation
Procedures
Activity Management Response Responsible Party Planting 6 Planting pit is to have roughened sides and decompacted base. Contractor
Appointment 1 Appointment of contractor with demonstrated experience in bushland rehabilitation. Relevant Project Manager 7 Install water retention crystals to manufacturer’s specifications (approximately 5 grams per plant). Contractor
of contractor qualifictions include a certificate in Conservation Land Management - Natural Area Restoration or a 8 Remove the plant from the container with minimum disturbance to the rootball, ensure that the rootball is moist
degree in a related field such as ecology or vegetation management. Contractors must hold applicable and place it in its final position, in the centre of the hole and plumb, and with the top soil level of the plant rootball Contractor
licences such as: level with the finished surface of the surrounding soil.
- Commercial operator's licence (ground appliaction of herbicides) issued under the Agricultural 9
Chemicals Distribution Control Act 1966 ; Backfill with topsoil mixture. Lightly tamp and water to eliminate air pockets. Ensure that topsoil is not placed over
Contractor
- Senior First Aid certificate; the top of the rootball, so that the plant stem remains the same height above ground as it was in the container.
- White Card i.e. General Safety Induction (Construction Industry); and,
Weed control 1 Prior to the commencement of weed control, contractor to inspect site to confirm weed species and/or extents for
- Relevant Ecoaccess pemits issued by the relevant State department. Contractor
control.
Review Plan 1 Project Manager,
Rehabilitation Concept Plan must be reviewed by contractor prior to commencement of site work. 2 Weed species / extents are flagged (as required). Contractor
Contractor
2 All relevant personnel sign a register noting that they have reviewed and will comply with the Project Manager, 3 Weed control, subject to site monitoring, undertaken every 3 months following planting and carried out in
Contractor
requirements of the Rehabilitation Concept Plan. Contractor accordance with requirements listed in this Rehabilitation Concept Plan.
Site 1 4 During the establishment and maintenance period, all rehabilitation treatments shall be maintained in a weed
Bare topsoil in rehabilitation areas will be appropriately prepared prior to planting. Contractor Contractor
preparation free condition.
2 Bare soil in rehabilitation areas affected by earthworks is to be tined to a minimum depth of 300mm prior
Contractor 5 Weed control will be undertaken in a manner which does not promote erosion or instability of soil, especially in
to planting and covered with 200mm reclaimed topsoil. Contractor
waterways or high velocity flow zones.
3 Import topsoil similar to naturally occurring topsoil, suitable for the establishment and ongoing viability of
6 Avoid application of herbicides on windy days or if rain is likely to follow within 12 hours. Contractor
the selected vegetation, free of weed propagules and contaminants, and which achieves the Contractor
requirements of AS 4419 Soils for landscaping and garden use . 7 Apply herbicides: Contractor
4 Avoid differential subsidence and excess compaction and produce a finished topsoil surface which has the a To the manufacturer’s instructions and material data and safety sheets. Contractor
Contractor
following characteristics:
b When the weather is humid with moderate temperatures and maximum sunlight. Contractor
a Finished to design levels. Contractor
c When the ground has adequate soil moisture. Contractor
b Smooth and free from stones or lumps of soil. Contractor
c
d Where in close proximity to waterways, undertake weed control in accordance with the following guidelines: NOT FOR CONSTRUCTION
Graded to drain freely, without pending, to catchment points. Contractor 1. Do not spray herbicides over waterbody.
d Graded evenly into adjoining ground surfaces. Contractor 2. Direct spray away from waterbody where possible.
3. Spray only to the extent of covering foliage with droplets. Contractor This drawing has been prepared by, or compiled from information provided by,
e Ready for planting. Contractor persons other than Litoria Consulting, who retain copyright and liability
4. Spray when weather is calm. associated with their content:
5 Biodegradable geofabric Matting must be installed for prior to planting. Contractor 5. Use a flat fan nozzle and low pump pressure to reduce likelihood of spray drift. 1. Nearmap (2024)
6 Matting characteristics, including type, weight and thickness is to be determined by the contractor. 6. Do not spray when rain is forecast within 12 hours. 2. Rural Residential Concept Sketch Option 3 (Innovative Planning Solution,
Drawing no GA2022-085-CS-005, Issue A, 9/12/2024)
7 For pegs, U-shape galvanized steel is to be used, at 1000 x 1000 mm intervals generally and 250 mm at 8 Undertake any ‘make good’ works arising from meetings with either Council or Litoria Consulting. Contractor
Contractor Litoria Consulting takes no responsibility for and makes no representations in
overlaps. Watering 1 Thoroughly water the plants before planting, immediately after planting, and as required to maintain growth relation to the completeness, accuracy or quality of any information contained in
Contractor
Erosion and 1 rates free of stress. this drawing. Each user of this drawing releases Litoria Consulting from all and
Temporary erosion and sediment control fencing to be installed in accordance with Best Practice Erosion any loss, damage, cost, expense or liability in relation to the use of, or any
sediment Contractor 2 Subject to prevailing weather conditions, watering to occur: Contractor reliance on, this drawing or the information contained in it. Features on this plan
and Sediment Control (IECA Australia, November 2008) (if required). have been located to accuracy suitable for assessment and hence should not be
control
a Daily for first week (5 waterings) Contractor used for exact measurements. Areas and dimensions shown are indicative only
Plant 1 Plant species and sizes to be supplied in accordance with Table 1. Contractor and subject to final survey. Users should independently verify the accuracy,
procurement b 3/week for weeks 2-4 (9 waterings) Contractor fitness for purpose and application of information contained in these drawings.
2 Plants will be supplied in weed-free containers of the required size. Open rooted stock is not to be All written dimensions take precedence over scaled dimensions. The currency of
supplied. All plants are to be healthy and vigorous. Root bound, diseased and poor stock will not be Contractor c 2/week for weeks 5-8 (8 waterings) Contractor these drawings should be checked prior to use. This drawing is provided only
for the information of the person or organisation to which Litoria Consulting
accepted. 3 Manually water all planting areas, soaking to a depth of 300 mm. Avoid frequent dampening of the surface. Allow provides it. It may not be provided to, or used by, any other person without
Contractor Litoria Consulting's prior written consent. Do not scale drawing. should
3 Supply plants with foliage size, texture and colour at time of delivery consistent with the size, texture and the surface of the soil to partially dry out between waterings. dimensions be conflicting or missing, notify Litoria Consulting and await further
Contractor
colour shown in healthy specimens of the nominated species. 4 Water at times of day to minimise water evaporation loss. Do not water during the hottest period of summer instruction.
Contractor
4 Supply plants with extension growth consistent with that exhibited in vigorous specimens of the days. © copyright - This document is and shall remain the property of litoria
Contractor consulting*. This document may only be used for the purpose for which it was
nominated species. Maintenance 1 Maintain appropriate planting densities and replace dead / dying / diseased stock every 3 months. Contractor commisioned and in accordance with the terms of the engagement for the
5 Supply plants free from damage and from restricted habit due to growth in nursery rows. Contractor commision. Unauthorised use of this document in any way is prohibited.
2 Provide replacement plants as follows: Contractor
6 Supply plants free from stress resulting from inadequate watering, excessive shade or excessive sunlight
Contractor a Of the same species and size listed in Table 1. Contractor
experienced at any time during their development.
7 Supply plants that have been grown and hardened off to suit the conditions that could reasonably be b Of uniformly high quality stock equal to the best commercially available. Contractor
Contractor Drawing Scale NA
anticipated to exist on site at the time of delivery. c Representative of optimum growth for the species as restricted by the container size. Contractor
8 Supply plants with foliage free from attack by pests or disease. Contractor d With a balanced root system in relation to the size of the plant and conducive to successful transpiration. Inspect Drawn By JM
Contractor
9 No single species shall constitute more than 30% of the total individuals planted. Contractor the root conditions of plants by knocking plants from their containers. Issue A
10 e Without signs of having been stressed at any stage during their development due to inadequate watering, DWG Ref. 24120 RCP04
All plant material is to be sourced from local provenance stock. Contractor Contractor
excessive shade / sunlight, suffered physical damage or have restricted habit due to growth in nursery rows.
11 Plant substitution is not permitted and alternative species must be confirmed with Litoria Consulting
Contractor f Date Created 18/12/2024
Healthy, well grown, hardened off specimens of good shape and free from pests and disease. Contractor
and/or Council prior to planting.
Planting 1 Do not plant in unsuitable weather conditions such as extreme heat, cold, wind or rain. Suspend g Well rooted and without any indication of having been restricted (pot bound) or damaged at any time. Contractor
Contractor
excavation when the soil is wet (except sandy soils), or during frost periods. h Been grown in their final containers for not less than twelve (12) weeks. Contractor
2 Planting of designated areas in accordance with the planting schedule, densities and planting detail
Contractor 3 Water to a depth of 300 mm. Avoid frequent dampening of the surface. Allow the surface of the soil to partially
described in this Rehabilitation Concept Plan.
dry out between waterings. Water at times of day to minimise water evaporation loss. Do not water during the Contractor
3 Planting layout of designated areas requires a random planting layout, in accordance with the Sample
hottest period of Summer days.
Planting Layout shown in this Rehabilitation Concept Plan.
4 Provide progress report to Council at minimum 12 months after acceptance on-maintenance. Contractor
4 Planting in accordance with Tubestock Planting Detail shown in this Rehabilitation Concept Plan ABN: 42 677 357 201
lvl 3 22 wandoo st fortitude valley
po box 461 paddington qld 4064
p: +61 7 3852 4855 f: +61 7 3319 8953
e: [email protected]
Document Set ID: 23448649
Version: 1, Version Date: 13/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.