Appendix 4 - State development assessment provisions

Module 14: Maritime Safety

Table 14.1.1: Operational Work
Performance outcomes          Acceptable outcomes                                           Compliance Comments

Lighting

PO1 Development avoids        AO1.1 Development must ensure that at all times, all lights   Complies – Any new lighting will be appropriately shielded and comply with AS 4282–1997
lighting that has the         on or above the development site do not interfere with        Control of the obtrusive effects of outdoor lighting.
potential to interfere with   safe navigation in surrounding waterways by:
aids to navigation.           (1) Shielding lights to prevent glare or reflection
                              (2) avoiding flood lighting which may reduce the visibility
                                   of aids to navigation
                              (3) avoiding flashing or flickering lights which may be
                                   confused with aids to navigation
                              (4) avoiding coloured lights such as green, blue or red
                                   lights, which may be confused with aids to navigation.
                              AND
                              AO1.2 Lighting complies with section 3 of AS 4282–1997
                              Control of the obtrusive effects of outdoor lighting.
Aids to navigation

PO2 Development does not      AO2.1 Development must not interfere with                     Complies – The closest navigation aids are located 170m to the south and
interfere with aids to        any aid to navigation on the development                      170m to the east
navigation.
                              site. AND
                              AO2.2 Development must not create any temporary or
                              permanent obstruction of aids to navigation.
                              AND
                              AO2.3 Development must keep the sight line of any aids to
                              navigation which cross the land clear of obstructions.
                              AND
                              AO2.4 Development must allow ongoing access to aids to
                              navigation for maintenance purposes.
                              AND
                              AO2.5 Development does not result in significant electrical
                              or electro-magnetic
Performance outcomes          Acceptable outcomes
Full text of the other 3 pages

Page 2

                               emissions which may impede the operation of aids to
                               navigation.
                               AND
                              AO2.6 Development:
                              (1) is not within 40 metres of an existing aid to navigation,
                                  or
                              (2) does not, within 40 metres of an existing aid to
                                  navigation, remove any material that may destabilise
                                  the aid to navigation (including ground tackle).
Protection of navigable waterways

Page 3

O3 Development does not       AO3.1 Development is to be carried out in a manner that               Complies – The proposed jetty and pontoons do not extend beyond the existing and
encroach on the navigable     ensures the navigable waterway is open to vessel traffic at           proposed lease area. The proposal also allows or boats to be moored within the existing
waterway in a way that        all times.                                                            lease area and will not impeded the safe passage of vessels. All existing piles and the
impedes the safe passage of   Editor’s note: Where development proposes to temporarily or           majority of the existing jetty will be removed as part of the works.
vessels.                      permanently limit the depth of a navigable waterway or the size of
                              vessels which can navigate a waterway, it is recommended that a
                              vessel traffic management plan be provided. It is also
                              recommended a marine execution plan be submitted to the
                              regional harbour master 30 days prior to the commencement of
                              works.

                              AND
                              AO3.2 Development:
                              (1) does not extend beyond the quayline, or
                              (2) if there is no quayline, any structures that are part of
                                  the development do not extend beyond that of
                                  approved neighbouring structures.
                              AND
                              AO3.3 Development does not limit either the depth of a
                              navigable waterway or the size of vessels which can safely
                              navigate the waterway.
                              Editor’s note: Where development closes or impedes vessel traffic
                              in a navigable channel, the applicant must prepare a vessel traffic
                              management plan. It is also recommended a marine execution plan
                              be submitted to the Regional Harbour Master 30 days prior to the
                              commencement of works.

                              AND
                              AO3.4 Development involving the demolition of structures
                              in a navigable waterway, including piling, must ensure the
                              entire structure is removed.

                              AND
                              AO3.5 Structures, including all freestanding piles, must be
                              appropriately lit and clearly visible to approaching vessels,
                              and reflective tape must be fitted to all structures to
                              enhance visibility during the hours of darkness.
                              Editor’s note: Where necessary, the Regional Harbour Master may
                              require the installation of aids to navigation on structures.

Page 4

PO4 Development does not     AO4.1 Development, including structures and any vessel    Not Applicable - The site does not adjoin any neighbouring lease. In addition the site
adversely affect navigable   berthed at the structures:                                affords sufficient setback to not interfere with public access to the river (outside of the
access to neighbouring       (1) if the development involves a finger pontoon, boat    lease boundaries).
premises.                        ramp or abuts a park or public area — has a setback
                                 area that maintains a safe navigable access to
                                 adjoining properties, or
                             (2) otherwise — retains a 1.5 metre setback from the
                                 water allocation side boundaries.

Used in these records

About this file

File size
51 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

App4 - State Code Assessmentpdf.pdf · 51 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.