 Environmental value            Magnitude                                                                                                             Environment
                                               Duration of
 potentially affected by        of impact                        Mitigation measures proposed                                                         al value
                                               impact
 prescribed activity            (Ha)                                                                                                                  affected
                                                                 Species monitoring conducted (pre-construction, during construction and post
                                                                 construction) as specified in the DES approved SMP.
  (vii) cause disruption to     0.81ha         20+ yrs.          Stormwater Management and Erosion and Sediment Control Plan will be                      No
        ecologically                                             implemented during the construction phase of operation, with a whole of site
        significant locations                                    Stormwater Management Plan in place during the landfill operation phase.
        (breeding, feeding,
        nesting, migration or                                    All stormwater flows from the landfill and access roads will report to a Sediment
        resting sites) of a                                      Control Pond / biobasin or discharge (controlled) south of the site.
        species.                                                 Ensure silt fences, diversion drains, and other erosion controls are functioning
                                                                 effectively, particularly during high water flow periods.
                                                                 Sediment and erosion control devices to be maintained in perpetuity.
                                                                 Retained habitat will be protected from dust impacts by the implementation of
                                                                 dust controls during construction and operation of the Landfill. This will include
                                                                 the use of water trucks, dust fencing and the implementation of a dust
                                                                 management plan prohibiting dust generating site activities during dry and
                                                                 windy conditions.
                                                                 Weed management strategy will be undertaken in the retained remnant
                                                                 vegetation areas.
                                                                 Implementation of weed management strategy in areas of Essential Habitat
                                                                 and protected wildlife breeding habitat (i.e., within RE 12.3.13 and 12.5.3) to
                                                                 be conducted by an appropriately qualified weed management team to
                                                                 minimise impacts from activities such as spray drift, non-target damage and
                                                                 misidentification of weed species.
                                                                 Weed management along landfill perimeter to be conducted in perpetuity.




Noosa Landfill & RRC Expansion – MNES & MSES Significant Impact Assessment                                                                                  26
Log in to download the original file

Attachment 7A - Impact Assessment Report.pdf · 4.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.