Decision Notice - Approved by Delegation of Authority MCU25 0021 (As Published) · MCU25/0021

of 6

Text shows just the words. Original shows the document exactly as it was published.

                                                                                       Officer:            Tiani Bird
                                                                                       Direct Telephone:   07 5329 6245
                                                                                       Our Reference:      MCU25/0021
                                                                                       Your Reference:     20240964

               21 May 2025


               KM Bone
               C/- Adapt Development Management P/L
               Level 1/103 Sippy Downs Dr
               SIPPY DOWNS QLD 4556
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 16 May 2025, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU25/0021

                   Street address:              5 Park Cres, Sunshine Beach Qld 4567

                   Real property description:   Lot 452 RP 48112

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for a Material Change of Use of Premises to Establish a Dwelling
                       House (Building Setbacks, Length of Wall, Front Fence)
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                       When Conditions must be Complied With
               1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                       the use commencing, and then compliance maintained at all times while the use continues.
                       Currency Period
               2.      This development approval lapses if the use has not happened by 16 April 2031 unless an
                       application to extend the currency period is approved by Council.


               ABN 97.969.214.121                                                                PO Box 141
               noosa.qld.gov.au                                                           Tewantin QLD 4565
               [email protected]                                                           07 5329 6500
                                                                                                             Page 1 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025
Full text of the other 5 pages

Page 2

                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                        Plan No.          Rev.     Plan/Document Name                               Date

                        WD.104            DA3      Site Setout Plan, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.201            DA3      Lower Level Plan, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.202            DA3      Main Level Plan, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.203            DA3      Upper Level Plan, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.204            DA3      Roof Plan, prepared by Aboda Design Group        07/04/2025

                        WD.501            DA3      North & South Elevation, prepared by Aboda 07/04/2025
                                                   Design Group

                        WD.502            DA3      East Elevation, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.503            DA3      West Elevation, prepared by Aboda Design 07/04/2025
                                                   Group

                        WD.607            DA3      Section A, prepared by Aboda Design Group        07/04/2025

                        WD.602            DA3      Section B, prepared by Aboda Design Group        07/04/2025

                      Building Height
               4.     The maximum height of the development must not exceed 12 metres above the ground level.
               5.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
                      certifies that the building does not exceed the maximum height requirement of this Decision
                      Notice.
                      Car Parking
               6.     A minimum of 2 car parking spaces must be provided on site and made available and
                      accessible at all times for residents.
                      Environment
               7.     Sediment or any other material including building materials or waste products must not be
                      deposited or released into the road reserve, stormwater drain or adjacent properties.
                      Landscaping Works
               8.     A minimum of 20% of the site must be retained as soft landscaping.
               9.     All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               10.    All planting areas on the eaves must be planted and maintained at all times, with replacement
                      planting undertaken promptly where plants fail or do not have a healthy and vigorous growth.


                                                                                                      Page 2 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025

Page 3

                      Site Access and Driveways
               11.    A sealed access driveway must be provided from Park Crescent to all parking and
                      manoeuvring areas of the development. The works must be generally in accordance with the
                      approved plans and undertaken in accordance with an Operational Works approval. The
                      works must include in particular a driveway crossover generally in accordance with Council’s
                      Standard Drawings RS-049 and RS-050.
                      Stormwater Drainage
               12.    Stormwater runoff from the development must be discharged to Park Crescent or disposed
                      of on-site without causing scour or damage to the subject site or any adjoining property.
                      Damage to Services and Assets
               13.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      (a) where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                          or
                      (b) where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               Geotechnical Stability
               14.    All works must be carried out in accordance with a Geotechnical Report for the site prepared
                      by a qualified person*. Certification must be submitted to Council from a qualified person*
                      which certifies that the site is not at risk from landslide emanating from the site or from other
                      land.
                      *(Refer to Advisory Note)
               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Aboriginal Cultural Heritage Act 2003
               1.     There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.




                                                                                                         Page 3 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025

Page 4

                      Equitable Access and Facilities
               2.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Infrastructure Charges
               3.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      Qualified Person
               4.     For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                      for the development, a qualified person is considered to be a person who:
                      (a)     is a Registered Professional Engineer of Queensland (RPEQ); and
                      (b)     has a degree in civil engineering or engineering geology; and
                      (c)     has a minimum of 5 years experience in the field of geotechnical engineering or
                                engineering geology.
                      Sustainability
               5.     Council encourages sustainable and energy efficient building design for all development,
                      including the use of sustainable building materials, energy efficient fittings, solar hot water,
                      photovoltaic systems (including the use of inverter/charges), solar panels, water saving
                      devices and rainwater harvesting.
                      Fires in Urban Areas
               6.     In urban areas fires are prohibited except where in an appliance is used for domestic heating
                      or cooking purposes, which must comply with particular standards. Any area identified as a
                      fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
                      Law No. 3, Schedule 3. Refer to the following link for details:
                      https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
                      Road Reserve Permit
               7.     This development permit provides the applicant with written authority to undertake the
                      prescribed works. Any additional activities that are undertaken inside Council’s road reserve
                      for the purpose of acting on this development permit and any associated building permit may
                      require a Road Reserve Permit. These additional activities may include, but are not limited
                      to, hoarding, pedestrian diversions, laneway closures, etc. To apply for a Road Reserve
                      Permit, or for more information, Contact Council’s Road Reserve Officer at
                      [email protected] of Operational Works Assessment
               8.     Additional application fees apply to Operational Work applications where the different
                      aspects of the works are lodged separately. Significant savings in application fees will result
                      if all works are lodged in a single application.
               8.     PROPERTY NOTES

               Not applicable.



                                                                                                             Page 4 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025

Page 5

               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required             Subject of the required Development Permit

                Development Permit for Building Works           All building work.

                Development Permit for Operational Works        Crossover.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Tiani Bird
               Development Planner


               Enc:   Appeal Rights
                      Approved Plans/Documents




                                                                                                      Page 5 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025

Page 6

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 6 of 6
Document Set ID: 23749952
Version: 4, Version Date: 21/05/2025

Used in these records

About this file

File size
149 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Approved by Delegation of Authority MCU25 0021 (As Published).pdf · 149 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.