Council archive · source document
Decision Notice - 010.2008.00000610.001 [As Published] · 142008.610
-5-
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
(5) If an application is processed under section
The following is an extract from the Integrated 6.1.28(2), appeal rights for submitters for the
Planning Act (Chapter 4). application are available only for the aspects of the
Division 8 - Appeals to court relating to development that would have required public
development applications notification under the repealed Act.
Appeals by applicants
(6) If an application involves assessment
4.1.27.(1) An applicant for a development against a concurrence agency code, appeal rights
application may appeal to the court against any of for submitters for the application are not available
the following- against the part of the approval that represents the
(a) the refusal, or the refusal in part, of a concurrence agency’s response for the code.
development application; Appeals by advice agency submitters
(b) a matter stated in a development approval, 4.1.29.(1) An advice agency may, within the limits
including any condition applying to the of its jurisdiction, appeal to the court about the
development, and the identification of a code giving of a development approval for a
1
under section 3.1.6; development application if-
(c) the decision to give a preliminary approval (a) the development application involves impact
when a development permit was applied for; assessment; and
(d) the length of a currency period; (b) the advice agency told the applicant and the
(e) a deemed refusal. assessment manager to treat its response to
(2) An appeal under subsection (1)(a) to (d) the application as a submission for an appeal.
must be started within 20 business days (the (2) The appeal must be started within 20
“applicant’s appeal period”) after the day the business days after the day the decision notice or
decision notice or negotiated decision notice is negotiated decision notice is given to the advice
given to the applicant. agency as a submitter.
(3) An appeal under subsection (1)(e) may be Appeals for matters arising after approval given
started at any time after the last day a decision on (co-respondents)
the matter should have been made. 4.1.30.(1) For a development approval given for a
Appeals by submitters development application, a person to whom any of
4.1.28.(1) A submitter for a development the following notices have been given may appeal
application may appeal to the court about- to the court against the decision in the notice-
(a) the giving of a development approval, including (a) a notice giving a decision on a request for
any conditions (or lack of conditions) or other extension of the currency period for an
provisions of the approval; or approval;
(b) the length of a currency period for the approval. (b) a notice giving a decision on a request to make
a minor change to an approval.
(2) The appeal must be started within 20
business days (the “submitters appeal period”) (2) The appeal must be started within 20
after the day the decision notice or negotiated business days after the day the notice of the
decision notice is given to the submitter. decision is given to the person.
(3) If a person withdraws a submission before (3) Subsection (1)(a) does not apply if the
the application is decided, the person may not approval resulted from a development
appeal the decision. application (superseded planning scheme)
that was assessed as if it were an
(4) If an application involves both impact application under a superseded planning
assessment and code assessment, appeal rights scheme.
for submitters are available only for the part of the
application involving impact assessment. (4) Also, a person who has made a request
mentioned in subsection (1) may appeal to
the court against a deemed refusal of the
request.
1
Section 3.1.6 (Preliminary approval may override
local planning instrument)
Page 5 of 6
[OCR of page images]
Sunshine Coast Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated
Planning Act (Chapter 4).
Division 8 - Appeals to court relating to
development applications
Appeals by applicants
4.1.27.(1) An applicant for a development
application may appeal to the court against any of
the following-
(a) the refusal, or the refusal
development application;
(b) a matter stated in a development approval,
including any condition applying to the
development, and the identification of a code
under section 3.1.6;"
(c) the decision to give a preliminary approval
when a development permit was applied for;
(d) the length of a currency period;
(e) a deemed refusal.
(2) An appeal under subsection (1)(a) to (d)
must be started within 20 business days (the
“applicant’s appeal period”) after the day the
decision notice or negotiated decision notice is
given to the applicant.
(3) An appeal under subsection (1)(e) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals by submitters
4.1.28.(1) A submitter for a development
application may appeal to the court about-
(a) the giving of a development approval, including
any conditions (or lack of conditions) or other
provisions of the approval; or
(b) the length of a currency period for the approval.
(2) The appeal must be started within 20
business days (the “submitters appeal period”)
after the day the decision notice or negotiated
decision notice is given to the submitter.
(3) If a person withdraws a submission before
the application is decided, the person may not
appeal the decision.
(4) If an application involves both impact
assessment and code assessment, appeal rights
for submitters are available only for the part of the
application involving impact assessment.
in part, of a
' Section 3.1.6 (Preliminary approval may override
local planning instrument)
(5) If an application is processed under section
6.1.28(2), appeal rights for submitters for the
application are available only for the aspects of the
development that would have required public
notification under the repealed Act.
(6) If an application involves assessment
against a concurrence agency code, appeal rights
for submitters for the application are not available
against the part of the approval that represents the
concurrence agency’s response for the code.
Appeals by advice agency submitters
4.1.29.(1) An advice agency may, within the limits
of its jurisdiction, appeal to the court about the
giving of a development approval for a
development application if-
(a) the development application involves impact
assessment; and
(b) the advice agency told the applicant and the
assessment manager to treat its response to
the application as a submission for an appeal.
(2) The appeal must be started within 20
business days after the day the decision notice or
negotiated decision notice is given to the advice
agency as a submitter.
Appeals for matters arising after approval given
(co-respondents)
4.1.30.(1) For a development approval given for a
development application, a person to whom any of
the following notices have been given may appeal
to the court against the decision in the notice-
(a) a notice giving a decision on a request for
extension of the currency period for an
approval;
(b) a notice giving a decision on a request to make
a minor change to an approval.
(2) The appeal must be started within 20
business days after the day the notice of the
decision is given to the person.
(3) Subsection (1)(a) does not apply if the
approval resulted from a development
application (superseded planning scheme)
that was assessed as if it were an
application under a superseded planning
scheme.
(4) Also, a person who has made a request
mentioned in subsection (1) may appeal to
the court against a deemed refusal of the
request.
Page 5 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2008.00000610.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 54 KB (small file)
- File type
No other editions are linked here.