Permit
Environmental authority P-EA-100375359
G17 Prior to the commencement of the dredging activity, a Dredge Management Plan (DMP) for the
activity must be developed and implemented, and the DMP must contain the following:
1. Clearly stated aims and objectives.
2. Description of dredging operation including:
a. type of equipment to be used in dredging;
b. volume of dredged material to be removed, and duration and timing of the dredging
campaign;
c. methods to be utilised for transporting dredged material; and
d. dredged material disposal methods.
3. Maps or plans showing:
a. legend, north arrow and scale;
b. boundaries of dredging operation;
c. estimated or modelled zone of influence of sediment plumes;
d. location of designated disposal sites;
e. location of sensitive receptors; and
f. all monitoring locations.
4. A detailed description of sediment plume-associated monitoring program including:
a. sampling regime and methods; and
b. monitoring sites.
5. A detailed description of the assessment methodology to provide data in relation to trigger
values that will define alert levels.
6. Clearly set out data handling and evaluation procedures that demonstrate how exceedance of
alert levels will be determined.
7. Management actions to be initiated if alert levels are exceeded.
8. Measures to ensure no permanent impacts to sensitive receptors outside the approved
dredge footprint.
G18 The DMP must not be implemented or amended in a way that contravenes or is inconsistent with any
condition of this authority.
G19 The DMP must be provided to the administering authority at either of the addresses below:
[email protected]; or
Department of Environment and Science
Permit and License Management
Implementation and Support Unit
GPO Box 2454
Brisbane Qld 4001
G20 The DMP must be submitted to the administering authority at least 20 business days prior to the
commencement of dredging and amended in accordance with any comments made by the
administering authority.
G21 If the DMP is amended, it must be provided to the administering authority at least 20 business days
prior to commencing activities under the amended DMP.
G22 Any comments made by the administering authority on the amended DMP provided in accordance with
condition G21 must be addressed to the satisfaction of the administering authority prior to implementing
the amended DMP.
G23 Condition G21 and G22 applies each time the DMP is amended.
G24 The dredging activity must be undertaken in accordance with the DMP required in condition G17.
_____________________________________________________________________________________________________________
Page 6 of 14 ABN 46 640 294 485
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.