RFI - Engineering correspondence
Our Reference: 2023
14 October 2020
Billy Glover
Noosa Council
PO Box 141
Tewantin 4565
QLD, Australia
RESPONSE TO COUNCIL INFORMATION REQUEST
PROPOSED INDUSTRIAL SUBDIVISION DEVELOPMENT
AT 1 TAYLOR COURT,
COOROY, QLD, 4563
This correspondence is provided as a partial response to Noosa Shire Council’s Information
request for the subdivision development at the above address (Council reference OPW20-0144),
dated 24th September 2020.
Issue:
The Earthworks Erosion and Sediment Control Plan is not reflective of the requirements for the
large site and has no information on the type of soil that will be exposed, timing and staging of
works or drainage management to prevent erosion. The State Planning Policy requires that all
exposed areas greater than 2500 metres2 must be provided with sediment controls which are
designed, implemented and maintained to a standard which would achieve at least 80% of the
average annual runoff volume of the contributing catchment treated (i.e. 80% hydrological
effectiveness) to 50mg/L Total Suspended Solids (TSS) or less, and pH in the range (6.5–8.5).
Response:
The Erosion and Sediment Control drawings on sheet R05 have been updated to include a
Type D sediment basin in proposed Lot 4 for the site earthworks. Calculations for the basin size
in accordance with the IECA guidelines are included with this correspondence.
Issue:
The application proposes construction of an approximately 500m2 hardstand driveway, allotment
reshaping and redirection of sheet flows to concentrated flow outlets. Where not appropriately
managed, these cumulatively will increase scour and impact the quality of runoff via increased
peak runoff from both the hardstand and outlet pipes. Further it is unclear how runoff from the
driveway will be treated to achieve the no worsening requirement for water quality in the drinking
water supply catchment.
Response:
Lawful points of discharge are required as part of the development works for these proposed lots
1-4. Lot 4 shall utilise the existing field inlet pit in the south-western corner of the property. Lots
1-3 are proposed to have piped connections (for future roofwater and/or site runoff) to the field
inlet pits 1/1, 2/1 and 3/1 on sheet R08. In response to ensuring a non-worsening of water quality,
a turfed swale drain has been included below the batter of Lot 4 to dissipate pipe flow velocities
and provide “scrubbing” of post development discharge runoff from the driveway and hardstands.
Please note that any future development of the proposed lots would be subject to a Material
Change of Use application that would determine whether additional, use -specific treatment
devices are required on each lot before discharge. The stormwater runoff from the swale is
recollected and discharged to the drainage reserve to the south of the property. Energy dissipation
by rock scour pad will be provided as shown on the civil drawings at each outlet to the swale and
the drainage reserve.
2023 - Bullgate Page 1 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
A MUSIC Model was created to confirm non-worsening of water quality resultant from the
subdivision. The parameters for the source nodes are based on the SEQ MUSIC Modelling
Guidelines V3 from Water by Design.
These include:
· Storm and rainfall data for Cooroy Composite (Station 40059) years 1973-1982 as per
Table A1.1
· Rainfall Runoff Parameters for Commercial and Industrial Catchments as per Table A1.2
· Pollutant export parameters for Industrial Catchments as per Table 3.9,
Provision was made for a small amount of additional hardstand (post development) across the
four lots in the event of an impervious surface pad or container being located on site outside of
any formal MCU approval. This is not planned for and is incorporated in the model as incidental
use only for robustness of the modelling.
Figure 1: MUSIC Model Layout and Pre-Post Development Comparison Results.
2023 - Bullgate Page 2 of 3
Page 3
The MUSIC model file is included with this response for review of the treatment nodes, being a swale and GPT to simulate the grate on the existing field inlet pit for proposed Lot 4. This correspondence and attached documentation conclude the partial response to Council’s information request and is provided in accordance with the requirements of Part 3 of the DA Rules, Planning Act 2016. If you wish to discuss this matter further, please contact Cameron Landreth on (07) 5443 8285. Yours sincerely, CAMERON LANDRETH - Director BEng (Hons), NER, RPEQ 19358 For and behalf of; BARLOW SHELLEY CONSULTING ENGINEERS (AUST) PTY LTD Encl: Updated Civil OPW Drawings (Rev-B) Sediment Basin Calculations MUSIC Model for subdivision 2023 - Bullgate Page 3 of 3