Specific outcomes, acceptable solutions and probable solutions for the Water
Sensitive Design Code
SPECIFIC OUTCOMES/ PROBALE SOLUTIONS COMMENT
Water reuse O1 S1.1 Development complies with the Complies
Development uses a water quality standards in Table 2 of the Development complies with the
combination of detention SEQ Regional Plan Implementation water quality standards in Table 2
and retention systems to Guideline No. 7 for Water Sensitive of the SEQ Regional Plan
capture run-off from areas Urban Design; Implementation Guideline No. 7
on the site; AND for Water Sensitive Urban Design;
O2 Water storage devices
must have sufficient S2.1 No solution provided
capacity having regard to
local rainfall pattern and the
catchment area of roof or
other hard standing surface;
AND
O3 Captured water is S3.1 Captured water is plumbed to be
utilised for all non-potable available for all external uses including Complies
uses on site; gardening, irrigation, ponds, filling
swimming pools and outdoor cleaning, as
AND well as all ground floor toilet cisterns and
washing machine cold taps; AND
Not Applicable
S3.2 Where the captured water is used
for toilet flushing and/or laundry use, an
automatic or manual interchange device
that allows alternate use of captured
water or the reticulated water supply is
installed to ensure that there is a
continual supply of water for sanitary
flushing and laundry use.
O4 On-site detention does Not Applicable
not adversely impact on S4.1 No solution provided
water requirements
downstream of the site
where the water is required
to sustain the ecology and
hydrology of downstream
systems (environmental
flows); AND
Not Applicable
O5 Within the Shire S5.1 No solution provided
Business Centre site, as
shown on Map SBC, on-site
detention measures are
contained within the
developed areas of the site,
clear of drainage lines and
Open Space Precincts.
Run-off treatment S6.1 & S7.1 Development complies with Complies
O6 Run-off that leaves the the water quality standards in Table 2 of
site is treated so as not to the SEQ Regional Plan Implementation
adversely impact on the Guideline No. 7 for Water Sensitive
ecology and hydrology of Urban Design.
downstream environmental
flows; AND
O7 Within the Shire Not Applicable
Business Centre site, as
shown on Map SBC— a)
run-off treatment occurs
within the site ; and b)
drainage lines are only used
for final polishing of run-off.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix 5- Response to Planning Scheme Codes.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.0 MB (small file)
- File type
No other editions are linked here.