Amended Decision Notice MCU25 0059 & OPW25 0080
2506-46399 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b){) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)
No. | Conditions Condition timing
Development Permit — Operational work
Schedule 10, Part 17, Division 3, Table 2, Item 1 — Tidal works or work in a coastal management
district—The chief executive administering the Planning Act 2016 nominates the Director-General of
the Department of Transport and Main Roads to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter relating
to the following conditions:
Approved plan
The development must be carried out generally in accordance with
the following plan:
* Site plan and water allocation, prepared by Marine
Structures, dated 21 February 2025, drawing number MS-
05069-01, Revision D
* Layout plan, prepared by Marine Structures, dated 25
February 2025, drawing number MS-05069-02, Revision F
Lighting
2. (a) Light/mark all vessels, structures, plant and equipment For the duration of
associated with: works and for operation
i. the works, in accordance with the following to be maintained st all
specifications: times
*® any anchors deployed must be marked with yellow
buoys and fitted with FL yellow lights fitted
* lighting provided must not obscure, disguise or
otherwise interfere with the effectiveness of
navigational lighting.
ii. operations, in accordance with the following
specifications:
* section 3 of AS4282-1997 Control of the obtrusive
effects of outdoor lighting
(b) Lighting provided must not obscure, disguise or otherwise
interfere with the safe navigation of other vessels, including the
effectiveness of navigational lighting.
Protection of navigable waterways
3. The construction, operation and maintenance of the pontoon and any | For the duration of
ship berthed, moored or attached to the structure, must not: works, and at all times
(8) encroach into, pass over or under a navigation corridor
(b) be located in a high-risk maritime zone
(c) impede the safe navigation of other ships or bosts
(d) restrict safe access to or from neighbouring structures.
4. Remove and dispose of any debris or similar obstruction For the duration or
encountered whilst undertaking the work at an appropriately licensed | works
facility.
5. All piles and/or structure to be demolished both above and below the | Prior to the completion
waterline must be completely extracted/removed. of the works
State Assessment and Referral Agency Page 4 of 8
Document Set ID: 24095479
Version: 1, Version Date: 03/09/2025
Page 8 of 12