56. Any vegetation to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape;
b. installing protective fencing around the drip line of the vegetation;
c. restricting stockpiling, storage and vehicle parking to those areas which are already
cleared; and
d. using low impact construction techniques around vegetation.
Additional Conditions specific for Lot 2 GTP 1154 – 19 May 2025
Performance Bond - Planning
57. Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
submitted to Council, to secure performance of all conditions of this approval, specifically for
Lot 2, prior to the issue of a Development Permit for Building Works. The cash bond or trading
bank guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Partial Demolition of Existing Building
Codes of Development
58. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan 2020.
Works
59. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste Management
60. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
61. All waste materials must be removed from the site to avoid causing unhealthy conditions,
with the site left clean, tidy and free from any debris.
62. Where a development permit has not been issued for the future use of the site, hard surfaced
areas including concrete slabs must be removed and disturbed areas must be revegetated
in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
be turfed within 20 business days of completing the removal or demolition work.
Water Quality and Drainage
63. Erosion and sediment control is to be undertaken in accordance with the requirements of the
Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
maintained until soils are stabilised by vegetation or sealed.
NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).
Health and Safety
64. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging, are removed from the building prior to demolition or relocation.
65. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
Page 18 of 26
Document Set ID: 24914513
Version: 5, Version Date: 03/07/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - 51983.3225.24 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Existing Approval - 51983.3225.24.pdfRelated documentApplication case desk ↗
About this file
- File size
- 238 KB (small file)
- File type
No other editions are linked here.