Minor Change Existing Approval - 51983.3225.24 (As Published)

of 26

Text shows just the words. Original shows the document exactly as it was published.

                      Landscaping
               90.    The development site must be landscaped. The works must be undertaken in accordance
                      with the Noosa Plan for that specific area and must include:
                      a.      the retention of the existing trees.
                      b.      All landscape works must be established and maintained in accordance with the
                              approved design for the life of the development, and in a manner that ensures healthy,
                              sustained and vigorous plant growth. All plant material must be allowed to grow to full
                              form and be refurbished when its life expectancy is reached.
                      c.      Any planting areas above ground level must be planted and maintained at all times,
                              with replacement planting undertaken promptly where plants fail or do not have a
                              healthy and vigorous growth.
                      Protection of Existing Vegetation
               91.    Prior to the commencement of any building works on the site, including excavation or
                      earthworks, a qualified arborist must prepare a report detailing measures to protect the
                      mature tuckeroo tree located on adjoining Lot 13 and any existing landscaping on the subject
                      site intended for retention.
                      All works in proximity to these trees must be undertaken strictly in accordance with the
                      recommendations of the approved arborist report.
                      The arborist report must be submitted to and approved by Council prior to the
                      commencement of works.
               92.    Trees to be retained must be protected from clearing or construction activities by:
                      a.      clearly marking vegetation to be retained with flagging tape
                      b.      installing protective fencing around the drip line of the vegetation
                      c.      restricting stockpiling, storage and vehicle parking to those areas which are already
                              cleared
                      d.      using low impact construction techniques around vegetation.
               Partial Demolition of Existing Building – Lot 14 GTP1154
                      Codes of Development
               93.    Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
                      solutions as contained in the Waste Management Code and Water Quality and Drainage
                      Code of the Noosa Plan 2020.
                      Works
               94.    Demolition must be undertaken in a manner that causes no detrimental effect upon the
                      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
                      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
                      in accordance with the nuisance provisions of the Environmental Protection Act 1994.
                      Waste Management
               95.    Adequate area must be provided on-site for the collection and separate storage of recyclable,
                      non-recyclable, vegetative and hazardous materials in their specific waste streams during
                      removal or demolition works.
               96.    All waste materials must be removed from the site to avoid causing unhealthy conditions,
                      with the site left clean, tidy and free from any debris.
               97.    Where a development permit has not been issued for the future use of the site, hard surfaced
                      areas including concrete slabs must be removed and disturbed areas must be revegetated
                      in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
                      be turfed within 20 business days of completing the removal or demolition work.



                                                                                                      Page 22 of 26
Document Set ID: 24914513
Version: 5, Version Date: 03/07/2026

Used in these records

About this file

File size
238 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 51983.3225.24 (As Published).pdf · 238 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.