AGENDA
Services & Organisation
Committee Meeting
Tuesday, 8 March 2022
commencing at 1.30pm
Council Chambers, 9 Pelican Street, Tewantin
Committee: Crs Joe Jurisevic (Chair), Amelia Lorentson, Clare Stewart, Frank Wilkie
“Noosa Shire – different by nature”
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 16 sections
Section 2
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
TABLE OF CONTENTS
ITEM PAGE
1. ATTENDANCE & APOLOGIES 3
2. CONFIRMATION OF MINUTES 3
3. PRESENTATIONS 3
4. DEPUTATIONS 3
5. REPORTS FOR CONSIDERATION OF THE COMMITTEE 4
1 PROPOSED TELECOMMUNICATIONS LEASE 10 BARTLETT STREET,
NOOSAVILLE 4
2 CONTRACT NO. T000052 - PROVISION OF NOOSA RIVER DREDGING
SERVICES 6
6. REPORTS FOR NOTING FOR THE COMMITTEE 11
3 2021 ANNUAL DISASTER MANAGEMENT FINANCIAL REPORT 11
7. CLOSED SESSION 17
Page 2 of 17
Section 3
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
1. ATTENDANCE & APOLOGIES
2. CONFIRMATION OF MINUTES
The Minutes of the Services & Organisation Committee Meeting held on 8 February 2022 be
received and confirmed.
3. PRESENTATIONS
Nil.
4. DEPUTATIONS
Nil.
Page 3 of 17
Section 4
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
5. REPORTS FOR CONSIDERATION OF THE COMMITTEE
1 PROPOSED TELECOMMUNICATIONS LEASE 10 BARTLETT STREET, NOOSAVILLE
Author Property Officer, Hayley Jamieson
Corporate Services Department
Index ECM/ 46.01 Lease/Application/LEAS13/0029
Attachments Nil
EXECUTIVE SUMMARY
Council resolution is required to grant Vodafone Network Pty Ltd a new lease complying with the
Local Government Act 2009 and the Local Government Regulation to dispose of a valuable non-
current asset if the grant of a lease is for the purpose of a telecommunications tower. Council can
only rely on that exception if, before granting the lease, it resolves that the exception applies.
RECOMMENDATION
That Council note the report by the Property Officer to the Services and Organisation Committee
Meeting dated 8 March 2022 regarding a new telecommunications lease on Council premises 10
Bartlett Street, Noosaville and:
A. Agree to enter into a commercial lease to Vodafone Network Pty Ltd for the existing
telecommunications facility located on part of 10 Bartlett Street, Noosaville (being Lot 901
RP150345) on the core lease terms outlined in this Report;
B. Apply the exception contained in section 236(1)(c)(vi) of the Local Government Regulation
2012, given the lease is for telecommunication purposes; and
C. Authorise the Chief Executive Officer to take all action necessary including, but not limited to,
negotiating, making, amending, signing and discharging the lease and any required variations
of the lease on the Council’s behalf, as described in this report.
REPORT
The purpose of this report is to seek Council approval to enter into a new communications lease to
Vodafone Network Pty Ltd for existing telecommunications facility, on the core terms outlined in the
report (refer Table 1 below).
10 Bartlett Street, Noosaville is Council freehold land and is located at the Council Depot. The Depot
has a telecommunication compound on site comprising a Tower and equipment shelter. Vodafone
Network Pty Ltd hold the lease over the Equipment Shelter and Axicom Pty Ltd hold the adjoining
leases over the Tower. Vodafone Network Pty Ltd co-locate its equipment on the tower via separate
licensing agreement with Axicom Pty Ltd.
Vodafone Network Pty Ltd has requested a new lease for the equipment shelter. The proposed new
lease terms have been negotiated and agreed to in principle. The core commercial terms of the
proposed new lease are outlined in Table 1 below.
The proposal is not subject to a development application, as it is deemed a Low-Impact Facility under
federal communications regulations.
A Council resolution is required to grant a new lease to Vodafone Network Pty Ltd (based on the
core commercial terms outlined) to comply with the Local Government Act 2009 and the Local
Government Regulation 2012. Section 236(1)(c)(vi) of the Regulation allows Council to dispose of a
valuable non-current asset if the grant of a lease is for the purpose of a telecommunications tower.
Council may only rely on that exception if, before granting a lease, it resolves that the exception
applies.
Page 4 of 17
Section 5
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
Table 1: Core Lease Terms
Lease Provision Proposal
Premises: Lease Area V and S in Lot 901 RP150345
Commencing Date and Expiry Date Commencing 1 April 2022 and expiring 27/06/2027
First Year Rental Consideration: $20,000
Lease Document VHA standard telecommunication lease
Lease Area: 24m2
Initial Lease Terms: 3 years + 2 x 2 extension
Market Rent Reviews: Fixed increases
Outgoings: Responsibility of lessee
Permitted Use: Constructing, maintaining, operating and upgrading a
telecommunications network and telecommunications service
including but not limited to installing, storing, operating, repairing,
maintaining, altering and replacing the Equipment consistent with
the evolving nature of telecommunications services.
It is recommended Council agrees to enter a commercial lease for the telecommunications
equipment shelter in accordance with the above provisions.
Previous Council Consideration
Nil
Finance
The financial return posed by the new lease is as detailed above. Some legal and transaction costs
will be incurred estimated at $3,000. Lease revenue will be incorporated in the 2022/2023 budget.
Risks & Opportunities
The new lease poses minimal risk given this is offered to the existing lessee over an area that has
been subject to telecommunication leases for over 20 years. The lease presents an opportunity to
improve servicer provision by Vodafone Network Pty Ltd to residents of the Shire in addition to
providing a revenue stream to ratepayers.
Consultation
External Consultation - Community & Stakeholder
Argon Law
Internal Consultation
Departments/Sections Consulted:
Chief Executive Officer Community Services x Corporate Services
Executive Support Director Director
Community Development Financial Services
Community Facilities Fleet
Libraries & Galleries ICT
Local Laws Procurement
Waste & Environmental Health X Property
Revenue Services
Executive Services Environment & Sustainable Development x Infrastructure Services
Director Director Director
Community Engagement Building & Plumbing Services Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development Civil Operations
People and Culture Environmental Services Disaster Management
Strategic Land Use Planning Infrastructure Planning,
Design and Delivery
Page 5 of 17
Section 6
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
2 CONTRACT NO. T000052 - PROVISION OF NOOSA RIVER DREDGING SERVICES
Author Coastal, Foreshores and Flooding Officer, Oscar Rogers
Infrastructure Services Department
Index ECM/ Project & Contract / T000052 - Provision of Noosa River Dredging
Services – Tender Award / Council Reports
Attachments 1. Weighted Attribute Evaluation Spreadsheet
EXECUTIVE SUMMARY
• Periodic erosion of the riverbanks of Noosa River and within the Noosa Sound canals need
rectification to replace lost sand. This contract is intended to supply sand nourishment to the
identified land parcels by way of dredging and nourishment operations. Furthering the
protection of Councils assets along the river and foreshore.
• All of the relevant statutory approvals and permits required for the dredging have been
obtained by Council from State Government departments.
• This is a schedule of rates contract that will include in the rates the costs of all services and
other incidentals associated with or necessary for the execution of the works and the
performance of the contract.
• The contract is for an initial term of two (2) years expiring on 31 March 2024.
• There are two (2) term extension available to Council at Council’s sole discretion of up to two
(2) years each ending on 31 March 2028 that will be subject to satisfactory contractor
performance.
• Pre-market research within the Moreton Bay and Sunshine Coast local government areas
identified a small market of contractors capable of delivering the services sought by Council.
• In accordance with Local Government Legislation and Council Procurement Policy, an
Invitation to Tender was initiated by the Procurement Team of Council and attracted one (1)
tender response.
• The tender evaluation panel completed the evaluation process and considered Rimlex Pty Ltd
t/as Nabis Dredging to be most advantageous to Council, representing value for money based
on benchmarked pricing to previous contracts at Council.
RECOMMENDATION
That Council note the report by the Acting Project Coordinator – Flooding, Coastal and Foreshores
to the Services & Organisation Committee Meeting dated 8 March 2022 and:
A. Award a schedule of rates Contract No. T000052 for the Provision of Noosa River Dredging
Services to Rimlex Pty Ltd t/as Nabis Dredging, commencing on 1 April 2022 for a term of two
years (2), expiring on 31 March 2024; and
B. Subject to satisfactory performance by Rimlex Pty Ltd t/as Nabis Dredging, authorise the CEO
to approve the options to extend the contract at the expiry of the first two (2) year term for a
further two (2) terms of up to two (2) years each ending 31 March 2028.
REPORT
1. Background
Council has historically engaged contractors through a request for quote process each year to
provide dredging services to the riverbanks of Noosa River and within the Noosa Sound canals.
Dredging services were last conducted by Council in October 2020. Infrastructure Services
highlighted the importance of the dredging operations through internal meetings, as the river
foreshore has been unprotected for a significant period of time and is experiencing high levels of
erosion.
Page 6 of 17
Section 7
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
2. Tender Invitation
In accordance with Part 3 of the Local Government Regulations and Council Procurement Policy,
Council invited written tenders for the provision of dredging services. The invitation to tender was
issued as a schedule of rates contract for an initial contract term of two (2) years, plus two (2) extra
terms of up to two (2) years each at Council’s sole discretion.
Council invited written tenders via the Council VendorPanel e-portal on 30 November 2021 and
included an advertisement within the Noosa Today publication on 10 December 2021, with
responses closing on 20 January 2022.
Statistics generated from VendorPanel identified 62 suppliers viewed the invitation to tender. Of this
list, approximately ten (10) firms listed where known to Council as being capable of providing the
services sought under this invitation to tender. At tender close on 20 January 2022, one (1) response
was received within the VendorPanel e-portal from Rimlex Pty Ltd t/as Nabis Dredging.
3. Tender Evaluation
The submission from Rimlex Pty Ltd t/as Nabis Dredging was deemed a conforming tender by the
Procurement Team after an initial compliance review to ensure the tender met the minimum tender
requirements.
The conforming tender was evaluated using the Council’s Weighted Attribute Evaluation
spreadsheet against the following evaluation criteria and weightings:
Criteria Weighting
Price 35.0%
Non-Price Criteria Sub-Criteria
Capability 2.5%
Capability & Resourcing
Resourcing 2.5%
Contract Experience 2.5%
Contract Experience & Capacity
Track Record 2.5%
Timeline 6.0%
Methodology
Methodology 14.0%
Quality Quality Management Systems 5.0%
Safety Management Systems 7.0%
Health & Safety
Safety Initiatives 3.0%
Environmental Management Systems 7.0%
Environment & Sustainability
Environmental Awareness / Initiatives 3.0%
Local Office Presence 5.0%
Contribution to Local Economy
Contribution to Local Economy 5.0%
The evaluation was conducted by the Evaluation Panel that consisted of the following members of
staff:
• Coastal, Foreshores and Flooding Officer (Contract Administrator)
• Acting Environment Services Manager
• Workplace Health and Safety Advisor (Safety Only)
• Acting Asset Planning Manager
• Acting Civil Operations Manager
Each member of the Evaluation Panel read and declared that they understood and accepted the
probity requirements, which includes a declaration of conflicts of interest and confidentiality.
Attachment 1 – Evaluation Spreadsheet presents the evaluation outcome of the conforming
submission against the above criteria.
Page 7 of 17
Section 8
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
The tender evaluation panel completed the evaluation process and considered Rimlex Pty Ltd t/as
Nabis Dredging to be advantageous to Council, presenting value for money. Rimlex Pty Ltd t/as
Nabis Dredging tender submission is favourable based on their tender submission demonstrating
the following:
• Very good level of experience and capability;
• Very good equipment and staff resources;
• Contractor provided detailed a methodology and timeline demonstrating their understanding
of the scope;
• Contributing to the local economy with an employee locally based;
• Proactively engaged with Chamber of Commerce & Industry Queensland (CCIQ) Ecobiz to
seek environmental performance improvements; and has suitable reporting for environmental
measures.
• The Contractor have very good management systems in place for Environment, Quality
Assurance and Occupational Health and Safety.
Rimlex Pty Ltd t/as Nabis Dredging have contracted to Council previously for Noosa River and Canal
dredging works and other foreshore works at Munna Point and have performed satisfactorily under
contract.
Previous Council Consideration
Nil
Finance
The dredging services contractor is engaged under a schedule of rates contract utilising existing
budget. Expenditure against this contract is estimated to be approximately $300k over the initial two-
year term of the contract.
Risks & Opportunities
Safety Risks Mitigation
Prior to commencement of services, Rimlex Pty Ltd
t/as Nabis Dredging management plans, Safe Work
Method Statements, Job Hazard Analysis (or
Rimlex Pty Ltd t/as Nabis Dredging fails to ensure similar) and other documentation will be submitted,
the work is conducted safely and in reviewed, and accepted by Council.
accordance with minimum standards.
Council will undertake surveillance, regular safety
audits and inspections throughout the dredging
services period.
Environment Risks Mitigation
Rimlex Pty Ltd t/as Nabis Dredging have nominated
a highly capable team for this project and can add
additional and appropriately skilled resources as
required.
Environment
Council will undertake surveillance and inspections
throughout the dredging services period. Council
will be provided with an incident report upon any
incident occurring whilst in the river.
Resource Risks Mitigation
Rimlex Pty Ltd t/as Nabis Dredging have nominated
Quality, safety, and service are affected due to a highly capable team for this project and can add
resource shortages. additional and appropriately skilled resources as
required.
Page 8 of 17
Section 9
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
Legislative Compliance Risks Mitigation
The contractor has worked for Council previously
and shown that they are a professional contractor
that can provide a suitable final product require
Compliance Issues under this Tender. The project manager and
contractor will have update meeting to track
compliance and any issues that might be raised
under the contract.
Consultation
External Consultation - Community & Stakeholder
• International Coastal Management (Consultants) on new permits but not required on standing
dredging.
Internal Consultation
The following participated in the tender evaluation:
• Acting Environment Services Manager – (Environmental Services) Environment and
Sustainable Development;
• Workplace Health and Safety Advisor - (People and Culture - Workplace Health & Safety)
Executive Services;
• Acting Asset Planning Manager - Infrastructure Services;
• Acting Coastal Flooding and Foreshores Project Coordinator;
• Acting Civil Operations Manager - Infrastructure Services; and
• Procurement and Contracts Adviser – Corporate Services.
Departments/Sections Consulted:
Chief Executive Officer Community Services X Corporate Services
Executive Support Director Director
Community Development X Financial Services
Community Facilities Fleet
Libraries & Galleries ICT
Local Laws X Procurement
Waste & Environmental Health Property
Revenue Services
X Executive Services X Environment & Sustainable Development X Infrastructure Services
Director Director x Director
Community Engagement Building & Plumbing Services X Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development X Civil Operations
X People and Culture (Safety) X Environmental Services Disaster Management
Strategic Land Use Planning Infrastructure Planning,
Design and Delivery
Page 9 of 17
Section 10
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
Attachment 1
Page 10 of 17
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
Fost Srataton Attachment 1
NOOSA SHIRECOUNCIL Weighted Attribute Evaluation Spreadsheet - Final Evaluation (V.14-Dec-2021)
a Se
[éontorming and Aternate Tenders Oniy 1 2 3 4 s 6 7 8 3 10 a 2
[australian Business ‘Number (ABN) 69007 255 218
Se Rimiex Pty Led t/a
per Respondent Details ABN Nabis Dredging
of Submission (as per VendorPanel) 20-dan-22
Registered Address (City/State Only) Minyama, QLD
[Fendered Price exc 6s) $ 930,523.65
| PART A.- Non price elements porn! ve
fvtston nen ‘Weighting (%) ‘Weighted Score ‘Weighed Score ‘Weigmted Score Weigrted Score Weighted Score Weighted Scone Wenghted Score Weighted Scone Weighted Scone ‘Weighted Score ‘Weighted Score ‘Weigined Score
|cpatitty & Resourcing 5% 42s 0.00 0.00 0.00 0.00 0.00 0.00 o.00 a00 0.00 0.00 0.00
Contract Experience & Capacity 5% 425 0.00 0.00 0.00 0.00 0.00 0.00 00 ooo a.00 0.00 0.00
Methodology 20% 14.60 0.00 0.00 0.00 0.00 0.00 0.00 00 ooo a.00 0.00 0.00
fouasty % 4.00 0.00 0.00 0.00 0.00 0.00 0.00 00 ooo 0.00 0.00 0.00
|scattn & Safety 10% 6.00 0.00 0.00 0.00 0.00 0.00 0.00 00 a0 0.00 0.00 0.00
Environment & Sustainability 10% 7.65 0.00 0.00 0.00 0.00 0.00 0.00 00 a0 0.00 0.00 0.00
Contribution to Local Economy 10% 7.00 0.00 0.00 0.00 0.00 0.00 a.00 00 a.00 0.00 0.00 0.00
|rotal rechnica Score 65% 47.75 0.00 0.00 0.00 0.00 0.00 a.00 0.00 0.00 0.00 0.00 0.00
| ‘Normalised Technical Score (Tn) 65.00
| PART 8 . Price element (Based on Average) porn! We
[rotal Fees (Pe 35% $930,523.65
[price Score 100 o ° o o o o o o o o o
Price Score (Pn) 100 o ° o o o o o o o o °
Price Score (Pw) 35.00
Total Score of price and mon price elements: 100.00
| Ranking hn
‘The Assessment Panel confirms the above scores and weightings of this evaluation and contirms the evaluation has been conducted in accordance with the Procurement Plan
Assessment Panel Position Tithe Initials Signature
Evaluation Panel Chair & Assesment Panel Member 1 Acting Project Coordinator - Flooding. Coastal and Foreshores or 8 Kez
Assesment Panel Member 2 Civil Operations Manager 80 8 ry —
‘Assesment Panel Member 3 Workplace Health & Safety Advisor PR bd Le
‘Assesment Panel Member 4 Acting Environmental Services Manager sw sz LAL —
Assesment Panel Member 5 Acting Asset Planning Manager AN x
7000082 - Weighted Ambute Evaluation Workbook (0. Master) Page 1 2au2022
Page 10 of 17Section 11
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
6. REPORTS FOR NOTING FOR THE COMMITTEE
3 2021 ANNUAL DISASTER MANAGEMENT FINANCIAL REPORT
Author Disaster Management Officer, James Ulyate
Infrastructure Services Department
Index ECM/ Subject / Disaster Management / Disaster Management & Planning
Attachments Nil
EXECUTIVE SUMMARY
This report provides an update on the expenditure of:
• Bushfire Recovery Exceptional Assistance Immediate Support Package ($1,275,000)
• Operational funding provided to disaster management during the 2020-2021 financial year.
1. Bushfire Recovery Exceptional Assistance Immediate Support Package
Following the 2019 bushfires, Council received $1,275,000 in government funding under the Bushfire
Recovery Exceptional Assistance Immediate Support Package - Funding & Activities. The allowable
time limit for expenditure of the funding is 30 June 2022.
At the time of this report 17 capital and operational projects have been completed with funding from
this grant. Examples include but are not limited to:
• Repair of damaged infrastructure at Peregian and Noosa Northshore
• Construction of an all-weather access track to the Noosa Northshore Aerodrome
• Replacement of damaged gazebos at Noosa Banks
• Implementation of novel technology solutions, including Fire Monitoring Cameras and
LoraWAN gateways
A full list of projects, their completion status and costs are detailed further in this report.
Approximately $796,000 of the original $1.25m has been carried over into the 2021/22 financial year.
At the time of this report approximately $290,000 of the 2021/22 carry over has been spent. The
approximate $500,000 in residual funding will be used to fund a range of projects, including but not
limited to:
• Provision of new disaster management risk assessments and plans
• Improving and reviewing vegetation mapping to better understand bushfire risk
• Provision of equipment and infrastructure for the Cooroibah foreshore
It is anticipated that some residual funding leading into the end of the 2020/2021 financial period will
be realised, from individual project underspend, however several standby projects with relatively
short duration outcomes have been identified and are described later in this report.
2. Operational funding 2020/2021
Council provided $71,000 in operational funding for Disaster Management in its 2020-2021 budget,
of which $59,000 relates to internal charges. $325,000 was also allocated to fund SES operations,
of which $272,000 relates to internal charges. Additional funding was provided by the State
Government, via the Get Ready program ($22,000) and a grant from QFES ($19,500), for the
delivery of resilience projects and subsidising SES activities, respectively.
Page 11 of 17
Section 12
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
RECOMMENDATION
That Council note the report by the Disaster Management Officer to the Services & Organisation
Committee Meeting dated 8 March 2022 providing an update on disaster management financial
activities for the 2020/2021 financial year.
REPORT
The purpose of this report is to detail the financial activities associated with disaster management
for the 2020/2021 financial year.
1. Bushfire Recovery Exceptional Assistance Immediate Support Package – Funding &
Activities
In addition to the disaster management operational budget, Council received $1,275,000 in
government funding under the Bushfire Recovery Exceptional Assistance Immediate Support
Package - Funding & Activities. This is an immediate support payment provided to severely affected
Councils activated under Category D funding of the Disaster Recovery Funding Arrangements
(DRFA) with all funds to be reconciled by 30 June 2022.
This funding is to enhance recovery and resilience of local communities severely impacted by the
2019 fire season.
Projects and programs have been undertaken over the timeframe of the grant acquittal period, with
some completed and others continuing. Projects and programs are listed below with an update on
their progress and monetary value.
Page 12 of 17
Section 13
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
DRFA Cat D 2019 Bushfire
Project Whole of Actuals to Budget 2021/22 Completion
Life Budget 30 June Carried into YTD spend status
2021 21/22 year
102219 - Community Connection and Resilience 4,903 4,903 0 0 100%
102220 - Tourism Marketing 50,000 12,425 37,575 3,600 30%
102221 - New Disaster Management Plan/s 160,000 0 160,000 38,399 25%
102222 - Evacuation Planning for Vulnerable Communities 0 0 0 0 Alternatively
funded
102223 - Assistance with Recruitment Drive for SES and QFES Rural 10,000 2,273 7,727 0 30%
102224 - Clearly marked and Recorded Road Names (North Shore, 0 0 0 0 Not actioned
Peregian)
102225 - Technology Solutions for Bushfire Prevention and 101,888 101,888 0 0 100%
Management
102226 - Documentary of Local Fires to be Used on All Platforms 15,000 0 15,000 7,500 50%
OPERATIONAL
102227 - Psychological Fist Aid and Mental Health Training for 2,971 2,971 0 0 100%
Volunteers
102228 - Severe Wind Hazard Assessment - QFES / GA / JCU project 15,000 6,818 8,182 6,818 50%
102229 - Opt-In Notification Upgrade to Guardian 5,000 0 5,000 0 100%
102230 - Improving and Reviewing Vegetation Mapping 60,000 0 60,000 14,195 30%
102231 - Wildlife Carers Grant Funding Post Fire - Animal Rehabilitation 30,000 30,000 0 0 100%
102232 - Nesting Boxes and Tree Planting in Affected Areas 0 0 0 0 Alternatively
funded
102233 - Weed Management on Burnt Land 25,000 13,200 11,800 4,235 30%
102234 - General Clean Up, Removal and Disposal of Waste 39,135 24,135 15,000 0 100%
102235 - Multi-Agency Strategic Fire Management Framework 55,000 0 55,000 0 25%
102236 - 19/20 Noosa Shire Planned Burn Program 0 0 0 0 Alternatively
funded
102237 - 20/21 Noosa Shire Planned Burn Program 27,455 27,455 0 0 Alternatively
funded
Page 13 of 17
Section 14
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
Project Whole of Actuals to Budget 2021/22 Completion
Life Budget 30 June Carried into YTD spend status
2021 21/22 year
102238 - 20/21 Noosa Shire Fire Trail Management Program 69,791 69,791 0 0 Alternatively
funded
102239 - Supporting organisation - SE QLD Fire Consortium 22,000 11,000 11,000 0 50%
102240 - Evacuation Centre Audit 14,975 14,975 0 0 100%
102241 - Evacuation Centre upgrades 50,000 2,517 47,483 2,652 30%
102242 - Evacuation Centre - generator connection points 88,565 88,565 0 0 100%
102243 - Beach access 61-64 post and rail replacement 9,065 9,065 0 557 100%
102244 - All-weather track - Teewah 190,000 0 190,000 192,361 100%
102245 - Shipping Container for Evacuation Centre Bedding 7,618 7,618 0 0 100%
102246 - Evacuation Centre Bedding 26,451 26,451 0 0 100%
102247 - Emergent Works 0 0 0 0 10%
102285 - Radio System Survey - RADLink 3,500 3,500 0 0 100%
102363 - Minor equipment and consumables - Evacuation Centre 11,683 0 11,683 0 10%
510076 - Lake Cooroibah Foreshore - CatD2019 50,000 0 50,000 629 30%
510077 - Peregian Beach Rufous St Public Art - CatD2019 50,000 136 49,864 0 10%
CAPITAL
510078 - Replace Dune Fencing at First Cutting - CatD2019 25,000 0 25,000 19,969 100%
510079 - Replace Shade Shelters at Noosa Banks - Cat D2019 18,809 18,809 0 0 100%
510129 - VHF project 36,191 0 36,191 0 10%
Total $1,275,000 $478,495 $796,505 $290,916
Where projects are underspent, residual funds will be re-allocated to other projects and emergent works to ensure all funds are utilised prior to 30 June
2022.
Page 14 of 17
Section 15
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
2. Operational funding for Disaster Management (2020-2021)
Council has provided the following operational funding for Disaster Management in its 2020-2021
budget:
Disaster Management Annual Actuals Comments
Operations (CC 1700) Budget FY20/21
FY20/21
Revenue (Get Ready QLD Grant income from QLD State -
$22,000 $23,893
Grant) recurring in nature
Expenditure
Reduced from $10,000 due to
COVID savings measures in
Employee Benefits - Training $5,000 $2,440
FY21. Limited training
opportunities as well.
Grant expenditure ($22k) +
materials, equipment and
Materials & Services $24,500* $24,250*
catering/venue hire for training
and meetings ($2,500)
Internal Charges # $57,548 $57,615
Budget Result $65,048 $60,412 Expenditure
Annual Actuals Comments
SES Operations (CC 1701) Budget FY20/21
FY20/21
Annually recurring for comparable
Revenue (QFES Grant) $19,500 $19,584
amounts
Expenditure
Slightly over budget with higher
Materials & Services $31,600 $34,012 than anticipated need for
materials
Actual D&A amount at financial
Depreciation and amortization $19,655 $29,336
year end as calculated
Other Expenses $874 $885 SEM Levy charged
Internal Charges # $255,264 $221,285
Budget Result (deficit) $287,892 $269,664 Income -/- Expenditure
* Excluding any expenditure associated with the CAT D 2019 Bushfire Recovery Funding allocation.
# Internal Charges are incurred by use of Council owned plant, labour or fleet and the cost centre utilising
those assets is charged on the basis of underlying financial allocation models e.g. rate per hour. These charges
zero out at Council level as there is no “profit” objective.
Queensland Reconstruction Authority “Get Ready” Funding & Activities
Council received approx. $24,000 in government funding under the Get Ready program.
Page 15 of 17
Section 16
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
The funding aims to improve community resilience to disaster events. Projects completed during the
year were:
• Update of the JBP Noosa weather forecasting system
• Development of the Emergency Action Guide Version 1
Risks & Opportunities
Risks
As the final expenditure date for the grant approaches i.e., 30 June 2022, there is a risk that some
projects may not commence and therefore allocated funding is not expended appropriately. This
may be attributed to several reasons including:
• Impacts of COVID-19 on capacity to deliver the project in a timely manner
• Funding of the project via other means including Cat C funding, Bushfire Levy, Budget etc
Opportunities
There is an opportunity to reallocate unspent project funds into emergent works that can be delivered
prior to June 30. This may include projects such as:
• Additional infrastructure to support the Firetech Connect LivingLab - $60,000
• Installation of new or maintenance of existing fire trails - $60,000
• Purchasing equipment to support the Fire Management Team
o Two slip-on fire units - $70,000
o Side by side all-terrain vehicle - $30,000
Consultation
External Consultation - Community & Stakeholder
Community consultation was undertaken to determine priority projects for the Category D funding.
Internal Consultation
• Financial Services
Departments/Sections Consulted:
Chief Executive Officer Community Services X Corporate Services
Executive Support Director Director
Community Development X Financial Services
Community Facilities Fleet
Libraries & Galleries ICT
Local Laws Procurement
Waste & Environmental Health Property
Revenue Services
Executive Services Environment & Sustainable Development X Infrastructure Services
Director Director X Director
Community Engagement Building & Plumbing Services Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development Civil Operations
People and Culture Environmental Services X Disaster Management
Strategic Land Use Planning Infrastructure Planning,
Design and Delivery
Page 16 of 17
Section 17
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 MARCH 2022
7. CLOSED SESSION
Nil.
Page 17 of 17