23122_LO_01 – 34 Elm St, Cooroy – King Group


Conclusion

The modelling suggests that for all events up to and including the 1% AEP +20%, the
provision of on-site detention will ensure peak flowrates for the proposed development do
not exceed peak flow rates from the current conditions or the natural state of the site.

Modelling of downstream flooding conditions in Opal St would not be required as the peak
flow rates from the site are reduced by the proposed development and will therefore improve
pipe network flows through private land.

This satisfies the request from Noosa Council.

This letter is issued in accordance with our standard terms of engagement. This advice shall
not be construed as relieving any other party of their legal responsibilities or contractual
obligations




Yours Faithfully,




Vincent Francis Cubis
MIEAust CPEng NER RPEQ 10086 Registered Professional Engineer - Engineers Australia (231327)
Director
Cubo Consulting Pty Ltd




Civil, Structural & Hydraulic Engineering ⬧ Water Supply and Sewerage ⬧ Heritage ⬧ Planning ⬧ Environmental   Page 4 of 4
Log in to download the original file

Reference Document MCU22_0102 Cubo Consulting Letter Final.pdf · 400 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.