MCU15/0095 & REC15/0022 PM Submission Object - Various - Petition Kelly Gerber
Very large file (14.4 MB): the original may take a few minutes to open or download. The page text below is quick to read.
b) The safety of pedestrians and cyclists is protected
c) Development reduces the reliance on private vehicles and promotes public and non-
motorised transport options;
f) Development does not adversely impact on existing public parking
78. The DA does not achieve the above overall outcomes based on the following:
(a) A significant proportion of pedestrians and cyclists will be GSLC students and
young families. A driveway being utilised by cars and heavy vehicles, particularly
at peak hours when students are entering or exiting the school, poses an
increased risk to their safety.
(b) More private vehicles are likely to enter the site for commercial purposes (re-
fuelling and retail reasons). Also, the DA is more likely to dissuade pedestrians
and cyclists from commuting to school due to the increased local vehicular
traffic and associated safety risks.
(c) Currently the site is utilised by scores of vehicles to park, particularly at school
drop-off and pick-up times. These excess vehicles will be highly likely to
contribute to further local congestion at the Goodchap Street roundabout as
outlined above, whilst some vehicles may use the service station grounds as an
ad-hoc drop-off or pick-up point for students, which is also an undesirable
outcome.
Specific outcomes - Driveways and Carparking Code
79. The DA does not achieve the specific outcomes relating to Driveways and Carparking
& Manoeuvring for the Driveways and Carparking Code (section 14.112). as set out in
the Tables below.
Table 14-49 - Driveways
SpecificOutcomes Applicant's Submitter's Response
Response
01 51.1- S1.3Complies Non-compliant
Vehicular access Vehicle accessis Instancesof vehicle versus pedestrian and vehicle
does not adversely considered to be versuscyclist collisions will be increased, particularly at
impact on safety, compliant with the peak drop-off and pick-up times.
capacity and relevant
operations of the requirements. The The proposed pedestrian pathway diversion directly
existing or planned development will from Walter HayDrive to the site and shop will also
road network, the comply where encouragechildren, particularly G5LCstudents, on to
proposed driveway, applicable. the site, increasingtheir exposure to a more
cyclewaysor concentrated area of moving standard and heavy
pedestrian pathway vehicles
systems
Table 14-50- car parking and manoeuvring
19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.