MCU14/0045 & OPW14/0268: Appendix D - Engineering Works codes
Appendix D: Engineering Works Codes
EARTHWORKS CODE
PERFORMANCE CRITERIA ACCEPTABLE SOLUTIONS COMMENTS
purpose of firewood. (Note: Disposal of vegetative
waste by burning off is not an acceptable method of
disposal).
Managing contamination risk S6.1 The fill material is solid clean earth, free of The proposed fill material is solid clean earth, free of
O6 Materials used as fill are suitable for development putrescible or refuse material, vegetation, acid putrescible or refuse material, vegetation, acid sulfate
of the land and filling or excavation works do not sulfate soils, building or construction material or soils, building or construction material or other material
result in the contamination of land. other material or contaminants; AND or contaminants. The site is not on the contaminated
S6.2 The site is not on the contaminated land land register.
register.
Haulage activity and amenity No solution provided Earthworks construction operations will generally occur
O7 Haulage of material to and from a site ensures— between 7am and 6pm, Monday to Saturday. Truck
a) minimal disturbance to neighbouring properties movements will not exceed 20 trips per day.
and properties along the haulage route; and b)
Council’s road infrastructure including pavements is
not adversely affected.
O8 Extent of earthworks Earthworks are contained S8.1 All earthworks, including cut and fill batters, All earthworks, including cut and fill batters, retaining
within the subject property. retaining walls etc are contained within the subject walls etc. will be contained within the subject site.
site.
Sloping sites S9.1 Cut or fill is less than 2m in depth relative to Fill is less than 2m in depth relative to the natural
O9 On sloping sites, excavation or filling are the natural ground surface. ground surface.
designed to maximise the use of natural slope and
minimise the need for cut and fill.
Environmental protection No solution provided. Earthworks operations will be carried out with due
O10 Earthworks minimise any adverse impact upon regard to minimise adverse impacts upon groundwater,
groundwater, watercourses, drainage lines, wetlands, watercourses, drainage lines, wetlands, and native
and native vegetation. vegetation.
Dams S11.1 Where the site is in the Rural Zone— Not applicable.
O11 Dam location and construction does not impact a) the land has a slope of less than 25% (1:4); and
upon neighbouring properties in terms of— b) the earthworks including cut and fill batters and
a) hydrology; retaining walls are setback a minimum of 50m from
b) alteration of existing overland flowpaths and the property boundary; and
patterns; c) the size of the lot is greater than 5 Hectares; AND
c) landslide or failure of dam wall; and S11.2 Where the site is in the Rural Settlement
d) effluent disposal areas. Zone or the Rural Zone where the lot is less than 5
CadCon Surveying & Town Planning
Page 7 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU14/0045 & OPW14/0268: Appendix D - Engineering Works codesRelated documentApplication case desk ↗
About this file
- File size
- 193 KB (small file)
- File type
No other editions are linked here.