12.   Certification of the completed structural works must be provided to Council by the supervising
      engineer The certification shall state that the completed works conform with all aspects of the
      design and that the completed works, including on site infrastructure, will not have any
      adverse affects on the stability of proposed buildings and/or structures and/or services and/or
      lands.
13.   Further protection of the creek banks at stormwater outlets may be required as directed by
      Council’s CEO, to avoid any possibility of erosion of the creek banks occurring.
14.   Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
      installed into the first existing external downstream stormwater structure in both directions of
      Alma Way.
      These devices are to be checked and cleaned on a regular basis and specifically after each
      rain event.
      These devices are to remain in place during the civil works and construction phases of the
      development.
      The location and type of device to be installed shall be established at the “pre start” meeting
      with Council’s Construction Technical Officer and shall be installed prior to the commencement
      of any works.
15.   Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of works.
16.   The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any sub contractors also have the appropriate insurance and public liability
      documentation.
17.   Prior to the “pre start” meeting, the principal contractor must be provided with a copy
      of Council’s signed approved drawings and conditions by the applicant.
18.   The Consulting Engineers for the project shall be currently Registered Professional Engineers
      of Queensland (RPEQ).         The consulting engineers are responsible for arranging all
      inspections, with Council’s Construction Technical Officer or nominated staff.
19.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
20.   An inspection is to be carried out with the relevant Council officers, the Contractor and
      Supervising Engineer after pegging the extents of the development has been established, and
      prior to clearing being carried out. This inspection is to deal with the limits of clearing to be
      carried out for this development. This meeting is to take place prior to the “Pre-start” meeting.
21.   Council standards shall apply to these works unless otherwise modified herein.
22.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Council’s CEO and shall forthwith rectify the damage to that property or
      facility at its cost and to the satisfaction of the Council’s CEO.




                                                                                            Page 3 of 16

Used in these records

About this file

File size
88 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

001A5368.001.pdf · 88 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.