61. The Environmental Auditor shall prepare a plan regarding the installation of fauna nesting
boxes. This plan shall be submitted to Council prior to commencement of works. Specific
detail required is number of nest boxes and target animal, and monitoring and maintenance
regimes that will be put in place to ensure nest boxes are functional and being used. A yearly
nest box monitoring report is required to be submitted to Council.
62. The use of nestbox fixtures that enter the live tissue of the host tree are not permitted (eg.
Coach bolts, tex screws etc). Alternative methods of nestbox fixing that do not harm the tree or
do not contravene Local Law No. 10 Vegetation Management 2003 are to be employed.
Water & Sewerage
63. Sewer connection and poly lined manhole as detailed in Inset A on Drawing N-B7416-C1-04-
03 B is approved for construction.
64. Internal sewerage reticulation, pump station, and rising main as detailed on Drawings N-
B7416-C1-04-01 C, N-B7416-C1-04-02 B, N-B7416-C1-04-03 B, and N-B7416-C1-04-04 B
are acceptable for connection to Council’s sewerage system. A Plumbing Compliance Permit
must be obtained from Council’s Plumbing Services Department prior to commencement of
these works.
65. Internal water reticulation, as detailed on Drawing N-B7416-C1-05-01-A is acceptable for
connection to Council’s water reticulation system. A Plumbing Compliance Permit must be
obtained from Council’s Plumbing Services Department prior to commencement of these
works.
66. A copy of the job specification is to be provided to Sunshine Coast Water’s Inspector at least
seven (7) days prior to commencement of works.
67. The names of any proposed contractors for works are to be submitted in writing, together with
copies of current Public Liability and Workers Compensation Insurances together with certificates
of currency for those policies, for consideration by the Assessment Manager seven (7) days prior
to pre-start meetings and commencement of works. A separate letter will then be issued
approving the contractor (or otherwise) for the works. No other contractor or subcontractor shall
be engaged to carry out the works or any part of the works without the written approval of the
Assessment Manager.
68. Sunshine Coast Water’s Inspector shall be given (7) days notice of intention to commence
works. A pre-start meeting shall be arranged prior to commencement of works by contacting
Sunshine Coast Water’s Inspector, Mr Trevor Mourilyan, Ph. 0417 780 830. Inspector is only
available for pre-start meetings, inspections and testing etc. between the hours of 6:30am to
4:00pm, Monday to Friday. Inspector will not be available outside these hours unless prior
approval is obtained from the Sunshine Coast Water’s Development Engineer with any costs
incurred by Council outside the hours nominated above, met by the Contractor/Developer. These
costs will be in addition to normal inspection fees.
69. Notwithstanding that Sunshine Coast Water has checked the plans with due care, where it is
found during construction that variations exist with Sunshine Coast Water’s standards, Sunshine
Coast Water standards shall apply.
70. It is the responsibility of the applicant to ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council property
or facilities (such as underground drainage, water supply and sewerage) are protected against
any damage or interference whatsoever.
Page 8 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001A5368.001.pdfRelated documentPublic source context ↗
07/2555 Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 88 KB (small file)
- File type
No other editions are linked here.