Marine Plant Assessment Dogs Beach, Noosa Spit Recreation Reserve 12
Discussion
4.2.1.2 Vegetation and Substrate Disturbance
Vegetation clearing limits should be detailed in site drawings and pegged out on site prior to
construction. This should include locations of vegetation protection zones, side-tracks and, if
required, locations for the stockpiling of site materials. No activities should occur within the
vegetation protection zones. Techniques for substrate handling and storage should be detailed in a
Construction Management Plan.
4.2.1.3 Restoration
Natural recruitment is the preferred and most cost-effective method of revegetating zones. On
completion of construction, substrate should be reprofiled where feasible to create conditions suitable
for natural recruitment of the dominant mangrove and saltmarsh species.
4.2.1.4 Signage and Access
Interpretive signage should be installed at the location of works to inform the public of construction
and to discourage access during restoration.
4.2.1.5 Maintenance and Monitoring
Maintenance and monitoring will be required to enhance restoration following construction. Regular
monitoring should be undertaken to assess the following:
• Restoration progress, assessment of substrate profile and marine plant recruitment; and
• Identify site management issues, such as low natural recruitment and weed invasion.
Site record sheets and permanent photo monitoring points should be used for recording and
monitoring restoration progress. Depending on the level of site disturbance, the monitoring schedule
may consist of weekly site visits for the first month, fortnightly visits for months 2-4, and monthly visits
thereafter.
G:\Admin\A10342.g.mpb.NoosaSpitSEMPdesign\R.A10342.001.00.marine plants.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.