Original source · versioned page text
SUPERSEDED - Decision Notice - Approved by Delegation of Authority MCU22 0104
Officer: Georgina Schramm Direct Telephone: 07 53296569 Our Reference: MCU22/0104 & OPW22/0161 Your Reference: 220417 31 October 2022 Mahadevan-Wilson & Ramana DS Trust C/- Adams & Sparkes Town Planning PO Box 1000 BUDDINA QLD 4575 [email protected] Dear Sir/Madam, Decision Notice Planning Act 2016 I refer to your application and advise that on 27 October 2022, Council decided to approve the application, subject to conditions. Details of the decision are as follows: application details Application No: MCU22/0104 & OPW22/0161 Street address: 23 Coral Tree Ave Noosa Heads Qld 4567 Real property description: Lot 17 RP 90014 Planning Scheme: Noosa Plan 2020 (25 September 2020) Decision details Council decided to issue the following type of approval: Development Permit for Material Change of Use - Dual occupancy Development Permit for Operational Works – Landscaping, Stormwater, Earthworks, Access and Driveway CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions MATERIAL CHANGE OF USE PLANNING When Conditions must be Complied With Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues. Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 21-054-02B - Site Plan – Proposed, prepared by Icon Building Design 18 August 2022 21-054-03A - Ground Floor Plan, prepared by Icon Building Design (annotated by Council) 18 August 2022 21-054-04A - First Floor Plan, prepared by Icon Building Design 18 August 2022 21-054-05 - Elevations, prepared by Icon Building Design (annotated by Council) 18 August 2022 21-054-06 - Elevations, prepared by Icon Building Design (annotated by Council) 18 August 2022 21-054-07 - Sections, prepared by Icon Building Design 18 August 2022 21-054-08 - Boundary Fence Detail, prepared by Icon Building Design 18 August 2022 Currency Period This development approval lapses if the use has not happened by 27 October 2028, unless an application to extend the currency period is approved by Council. Building Height The maximum height of the development must not exceed 8 metres above the finished ground level and the natural ground level. Certification must be submitted to Council from a Licensed Surveyor which certifies that the buildings do not exceed the maximum height requirement of this Decision Notice. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. Street Identification The street address of the development must be clearly visible and discernible from the primary frontage of the site by the provision of a street number and, where appropriate, the building name. Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site. Building Appearance All air conditioning units or other mechanical equipment must be located at ground level, or otherwise fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties. Fencing and Walls Any street fencing must be set back an average of 1 metre from the front property boundary. Any fencing on the front boundary must either: not exceed a maximum height of 1.2m, or contain openings or materials that ensure it is 50% transparent and has a height not exceeding 1.8 metres from both finished and natural ground. The area of land between the fence and the front property boundary must be densely landscaped to screen any fencing from the street. The maximum allowable cumulative height of fencing and retaining walls along all boundaries (excluding the front fence) are not to present to the neighbouring property a height greater than 2 metres. Landscaping Works All landscape works must be to be carried out in accordance with the approved Landscaping Plans by prepared by Bird Landscape Design, dated 19 May 2022. All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. Clothes Drying Areas Each dwelling unit must be provided with access to an outdoor clothes line which is screened from public view. Protection of Privacy Should the mechanical plant (i.e. pool equipment) be located within the 2 metre side/rear boundary setbacks it is to be is to be visually integrated into the line/plane of the building, screened and baffled to ensure that there are no amenity impact to neighbouring premises. Community Management Statement Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment. Site Access and Driveways A sealed access driveway must be provided from Coral Tree Avenue to all parking and manoeuvring areas of the development. The works must be generally in accordance with Ingeniir’s drawing 221304 – C05, Revision 2, dated 26 August 2022. Car Parking The works for the uncovered visitor car parking space must be: marked for that purpose and accessible at all times for visitor use dimensions, crossfalls and gradients in accordance with Australian Standard AS2890: Parking Facilities. Stormwater Drainage The site must be provided with a stormwater drainage system connecting to a lawful point of discharge. The works must be generally in accordance with Ingeniir’s drawing 221304 – C05, Revision 2, dated 26 August 2022. Earthworks and Retaining Walls All fill and associated batters must be undertaken in accordance with an Operational Works approval, and contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. All retaining walls must be designed and constructed in accordance with the planning scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade safety fence. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. OPERATIONAL WORKS APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 221304 – C04 2 Proposed Site Layout Prepared by Ingenirr 26 August 2022 221304 – C05 2 Proposed Stormwater and Site Level Layout Prepared by Ingenirr 26 August 2022 221304 – C06 2 Proposed Earthworks Plan Prepared by Ingenirr 26 August 2022 221304 – C07 2 North Section Prepared by Ingenirr 26 August 2022 2234 (Sheet 1/5) B Landscape Operational Works Package, prepared by Bird Landscape Design 27 August 2022 2234 (Sheet 2/5) B Finishes and Planting Schedules, prepared by Bird Landscape Design 27 August 2022 2334 (Sheet 3/5) B Landscape Operational Works Package, prepared by Bird Landscape Design 27 August 2022 2234 (Sheet 4/5) B Planting Plan – Ground Floor, prepared by Bird Landscape Design 27 August 2022 2234 (Sheet 5/5) B Planting Plan – First Plan, prepared by Bird Landscape Design 27 August 2022 PRIOR TO COMMENCEMENT OF WORKS Engineering All necessary approvals from external service providers (e.g. Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; Other relevant parties A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction Maintenance of safe vehicle and pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased Proposed fencing to the site during the construction phase of the development Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice The relevant conditions of the higher order Material Change of Use approval viz. MCU22/0104 to which this approval relates All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site Works within Road Reserve/Reinstatement Safe vehicle and pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Site Access and Driveways Driveway crossovers must be constructed in accordance with council’s Standard Drawings RS-049, RS-050 and any associated addendum. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete. The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks and Retaining Walls All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development and generally in accordance with Ingeniir’s drawing 221304 – C06, Revision 2, dated 26 August 2022. Slope and batters are a maximum grade of: 1 in 6 where in proximity to waterbodies. 1 in 4 for grassed areas. 1 in 3 for planted areas. 1 in 2 for combined structural engineering and planting solutions. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Removal of Existing Trees and Vegetation Removal of existing trees and vegetation must be undertaken by a qualified person* and must include: Stump grinding to below finished surface level. Rectification to the finished surface levels and materials. No damage to other vegetation for retention. Legal disposal of all removed vegetation and debris. Replanting in accordance with the approved plans *(Refer to Advisory Note) Fauna Management A qualified person* must be engaged to manage fauna prior and during clearing to: Ensure works are carried out in accordance with the Nature Conservation Act 1992. Undertake pre-clearing inspections including fauna relocation and removal or blocking of all vacant hollows. Ensure clearing works avoids nesting times of animals and birds. Co-ordinate staging and sequence of clearing with fauna protection. Protect and recover fauna during clearing operations (not previously removed). Manage the translocation of animals and recovery procedures in accordance with relevant legislation. *(Refer to Advisory Note) Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods, Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods, Been revised to address predicted rainfall events, and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. FOLLOWING CONSTRUCTION Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act). The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act. Qualified Person, for the purpose of: Supervising landscape works and preparing a landscape certification, is considered to be a landscape architect, landscape designer or horticulturist with a minimum of three years current experience in the field of landscape design. Undertaking landscape construction and establishment works is considered to be a person with five years current experience in commercial landscape construction projects. Undertaking rehabilitation construction and establishment works is considered to be a person with five years current experience in revegetation and regeneration. Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either: International Society of Arboriculture (ISA) certification; or A Diploma of Arboriculture. Managing Fauna protection is considered to be a certified Fauna Spotter Catcher. Managing Fauna protection is considered to be an Ecologist or Environmental Scientist with a minimum of three years current experience in the field of fauna assessment and management. Managing Fauna protection, preparing Fauna reporting and certification and calculating compensatory habitat, is considered to be an Ecologist or Environmental Scientist with a minimum of three years current experience in the field of fauna assessment and management. Undertaking Fauna site works and calculating compensatory habitat is considered to be a Fauna Spotter Catcher with current certification under the Queensland Parks and Wildlife Service. As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-050 and RS-056. Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection: Methods of stabilisation are: appropriate for slopes and slope lengths; and are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. Infrastructure Charges All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges property notes Not applicable. VARIATION approval details Not applicable. further development permits required Type of Development Permit Required Subject of the required Development Permit Development Permit for Building Works All building work. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. Yours faithfully, Georgina Schramm Development Planner Enc: Appeal Rights Infrastructure Charge Notice Approved Plans/Documents cc. Unitywater Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017 Chapter 6 Dispute resolution Part 1 Appeal rights 229 Appeals to tribunal or P&E Court (1) Schedule 1 of the Planning Act 2016 states – (a) Matters that may be appealed to – (i) either a tribunal or the P&E Court; or (ii) only a tribunal; or (iii) only the P&E Court; and (b) The person- (i) who may appeal a matter (the appellant); and (ii) who is a respondent in an appeal of the matter; and (iii) who is a co-respondent in an appeal of the matter; and (iv) who may elect to be a co-respondent in an appeal of the matter. (2) An appellant may start an appeal within the appeal period. (3) The appeal period is – (a) for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or (b) for an appeal against a deemed refusal – at any time after the deemed refusal happens; or (c) for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or (d) for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or (e) for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or (f) for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person. Note – See the P&E Court Act for the court’s power to extend the appeal period. (4) Each respondent and co-respondent for an appeal may be heard in the appeal. (5) If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal. (6) To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about- (a) the adopted charge itself; or (b) for a decision about an offset or refund- (i) the establishment cost of trunk infrastructure identified in a LGIP; or (ii) the cost of infrastructure decided using the method included in the local government’s charges resolution. 230 Notice of appeal (1) An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that- (a) is in the approved form; and (b) succinctly states the grounds of the appeal. (2) The notice of appeal must be accompanied by the required fee. (3) The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to – (a) the respondent for the appeal; and (b) each co-respondent for the appeal; and (c) for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and (d) for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and (e) each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and (f) for an appeal to the P&E Court – the chief executive; and (g) for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate. (4) The service period is – (a) if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or (b) otherwise – 10 business days after the appeal is started. (5) A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6). (6) A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person. 231 Other appeals (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable. (2) The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error. (3) A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter. (4) In this section – decision includes- (a) conduct engaged in for the purpose of making a decision; and (b) other conduct that relates to the making of a decision; and (c) the making of a decision or failure to make a decision; and (d) a purported decision; and (e) a deemed refusal. non-appealable, for a decision or matter, means the decision or matter- (a) is final and conclusive; and (b) may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and (c) is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground. 232 Rules of the P&E Court (1) A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal. (2) However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court [word/footer1.xml] Page 2 of 4 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 4 [Attachment: image3.png (image text)] ee) NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original