25 July 2008
Middap Ditchfield Architects
Cnr Mary & Thomas Streets
NOOSAVILLE QLD 4566
Dear Madam
Decision Notice
Integrated Planning Act 1997
I refer to your application and advise that on 24 July 2008 Council decided to approve the application
in full subject to conditions.
Details of the decision are as follows:
1 APPLICATION DETAILS
Application No: 2008/200
Street address: 15 Duke Street, Sunshine Beach
Real property description: Lot 201 RP 48113
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
The following type of approval has been issued:
Preliminary Approval for Operational Works - Landscaping, Carparking & Access, Frontage
Works, Stormwater Drainage, Site Civil Works and Erosion & Sediment Control
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Landscaping
1. A further application for Operational Works is to be submitted to comply with the conditions of
this Preliminary Approval. The Development Permit will not be issued until all bonds and
contributions have been paid in accordance with the Material Change of Use application
07/1045.
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are numbered, titled and dated:
Page 1 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
2008/200
Plan / Rev. Plan / Document Name Date
Document
No.
Planting Plan – Winter & Co. Pty Ltd 12/3/08
3. All manholes, inspection pits and grates are to be raised to finished surface levels and kept
free of cover and be visible at all times to ensure prompt access in case of emergency.
4. The landscape construction is to be implemented in accordance with the amended landscape
plan, planting schedule and horticultural industry best practices.
5. All trees must be planted a minimum of 1 metre from all services.
6. All trees 45 litre and greater must be securely tied and staked to assist their growth during the
establishment period.
7. All native plant species located in group plantings shall not be subjected to any hedging
maintenance regimes.
8. The density of planting must achieve the set out requirements as detailed on the approved
landscape plan.
9. The applicant must ensure that all landscaping treatment does not unduly restrict/prevent
access to service meters within the site.
10. The development of the site shall be carried out in such a manner as to prevent dust and/or
sand nuisance to residents in the vicinity of the development.
11. The requirements of this development approval are to be effected, prior to the use of the
relevant premises. Council reserves the right to call upon the bond or guaranteed sum
applicable to the overall site to effect compliance with conditions.
12. This Preliminary Approval lapses if the development has not happened by 24 July 2010,
unless application to extend the currency is approved by Council.
Carparking, access, frontage works, stormwater, drainage, site civil works, erosion & sediment
control
13. The development shall be carried out in accordance with the approved plans listed below or as
modified herein.
14. Copies of the approved drawings, duly signed by the Consultant Registered Professional
Engineer, Queensland (RPEQ) shall be provided to Council’s Construction Technical Officer at
the “pre start” meeting.
15. The access driveway, turning area and visitor car-space shall be constructed so that surface
runoff is directed (falls) to the grated drain and Gross Pollutant Trap (GPT) at the Duke Street
frontage.
16. The grated drain and GPT are to be constructed wholly within the subject site.
17. Roof and surface runoff connection to Council’s drainage system shall be as shown on
drawing no. 1899-5 by Construction Hydraulic dated 17/04/08.
18. A concrete footpath 1.5 metres wide shall be constructed across the full frontage of the
development. The footpath shall have a slip resistant surface. The alignment shall be
determined on site with Council’s Construction Technical Officer. The expansion joints in any
footpath shall be “saw cut”, not trowel jointed.
19. Council’s Construction Technical Officer (ph 0410 512 505) shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting prior to the
commencement of works.
Page 2 of 8
Page 3
2008/200
20. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any sub contractors also have the appropriate insurance and public liability
documentation.
21. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
22. The Consulting Engineers for the project shall be currently Registered Professional Engineers
of Queensland (RPEQ). The consulting engineers are responsible for arranging all
inspections, with Council’s Construction Technical Officer or nominated staff. Council’s
Construction Technical Officer shall provide an inspection form for signing off by the Engineer
at appropriate stages of construction, during on-site meetings. Construction Technical Officer
will also sign the form at each stage when conditions required have been satisfied.
23. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
project. (This person will be the contact for the project).
24. Council standards shall apply to these works unless otherwise modified herein.
25. The person acting on this permit shall ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property, road pavements or facilities (such as underground drainage, water supply,
sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its
Consultants or Contractors through any cause whatsoever in the course of, directly or
indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
property or facility at its cost and to the satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the commencement of the use or,
alternatively, the Applicant may request the Council to carry out the rectification work at the
Applicant’s cost, such cost being paid by the Applicant to the Council prior to the
commencement of the use.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost
of the Applicant, such cost being paid prior to the commencement of the use.
26. The development of the site shall be carried out in such a manner as to prevent dust and/or
sand nuisance to residents and/or tenants in the vicinity of the development.
27. Construction work and other associated activities are permitted only during the hours of 7.00
am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
except where extended hours are approved by the Manager, Land Development or his
nominee.
28. All signage, including that for safety during construction, shall be in accordance with the
Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
29. Safe pedestrian access on Duke Street in the vicinity of the development shall be maintained
at all times. Should footpath / road closures be necessary to carry out construction works,
Council’s Construction Technical Officer (ph 0410 512 505) must be notified prior to the
proposed closure.
Page 3 of 8
Page 4
2008/200
30. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot “fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways. Although the sediment and erosion control
measures have been approved on drawing no. 1899-6, Council’s Manager, Land
Development, may request further controls to be installed should approved measures be
inefficient.
31. These works are also to be in compliance with the relevant conditions of Development Permit
No. 2007/1045.
32. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations from Council's standards exist, then Council standards shall apply
Approved Plans
The approved plans for this development approval are listed in the following table:
Plan / Document No. Rev. Plan / Document Name Date
0724 WD 100 B 31.01.08
Working Drawings Operational Works
Site Plan - Middap Ditchfield Pty Ltd
17273 – OW1 A 20.03.08
Operational Works & Drainage – SCG
Consulting Engineers
17273 – OW2 A 20.03.08
Carparking and Driveway Plan – SCG
Consulting Engineers
1899-1 A 30-04-08
General Notes & Legend –
Construction Hydraulic)
1899-5 17-04-08
Stormwater Operational Works –
Construction Hydraulic)
1899-6 17-04-08
Sediment & Erosion Control Plan –
Construction Hydraulic)
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
A copy of any referral agency conditions is attached.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
Planting Plan – Winter & Co. Pty Ltd 12/3/08
Page 4 of 8
Page 5
2008/200
0724 WD 100 B 31.01.08
Working Drawings Operational Works
Site Plan - Middap Ditchfield Pty Ltd
17273 – OW1 A 20.03.08
Operational Works & Drainage – SCG
Consulting Engineers
17273 – OW2 A 20.03.08
Carparking and Driveway Plan – SCG
Consulting Engineers
1899-1 A 30-04-08
General Notes & Legend –
Construction Hydraulic)
1899-5 17-04-08
Stormwater Operational Works –
Construction Hydraulic)
1899-6 17-04-08
Sediment & Erosion Control Plan –
Construction Hydraulic)
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged with
this application along with the appropriate fees.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
A preliminary approval under section 3.1.6 of Integrated Planning Act 1997 has been granted and as
such the level of assessment and applicable codes for any development approval resulting from this
approval are identified in the conditions.
Page 5 of 8
Page 6
2008/200
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Operational Landscaping, Carparking & Access, Frontage Works,
Works Stormwater Drainage, Site Civil Works and Erosion &
Sediment Control
11 SELF ASSESSABLE CODES
Not applicable
12 SUBMISSIONS
Not applicable
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,
Tracy Jones
SENIOR PLANNING OFFICER
Page 6 of 8
Page 7
2008/200
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
(5) If an application is processed under section
The following is an extract from the Integrated 6.1.28(2), appeal rights for submitters for the
Planning Act (Chapter 4). application are available only for the aspects of the
development that would have required public
Division 8 - Appeals to court relating to
notification under the repealed Act.
development applications
Appeals by applicants (6) If an application involves assessment
4.1.27.(1) An applicant for a development against a concurrence agency code, appeal rights
application may appeal to the court against any of for submitters for the application are not available
the following- against the part of the approval that represents the
(a) the refusal, or the refusal in part, of a concurrence agency’s response for the code.
development application; Appeals by advice agency submitters
(b) a matter stated in a development approval, 4.1.29.(1) An advice agency may, within the limits
including any condition applying to the of its jurisdiction, appeal to the court about the
development, and the identification of a code giving of a development approval for a
1
under section 3.1.6; development application if-
(c) the decision to give a preliminary approval (a) the development application involves impact
when a development permit was applied for; assessment; and
(d) the length of a currency period; (b) the advice agency told the applicant and the
(e) a deemed refusal. assessment manager to treat its response to
the application as a submission for an appeal.
(2) An appeal under subsection (1)(a) to (d)
must be started within 20 business days (the (2) The appeal must be started within 20
“applicant’s appeal period”) after the day the business days after the day the decision notice or
decision notice or negotiated decision notice is negotiated decision notice is given to the advice
given to the applicant. agency as a submitter.
(3) An appeal under subsection (1)(e) may be Appeals for matters arising after approval given
started at any time after the last day a decision on (co-respondents)
the matter should have been made. 4.1.30.(1) For a development approval given for a
Appeals by submitters development application, a person to whom any of
the following notices have been given may appeal
4.1.28.(1) A submitter for a development
to the court against the decision in the notice-
application may appeal to the court about-
(a) a notice giving a decision on a request for
(a) the giving of a development approval, including
extension of the currency period for an
any conditions (or lack of conditions) or other
approval;
provisions of the approval; or
(b) a notice giving a decision on a request to make
(b) the length of a currency period for the approval.
a minor change to an approval.
(2) The appeal must be started within 20
(2) The appeal must be started within 20
business days (the “submitters appeal period”)
business days after the day the notice of the
after the day the decision notice or negotiated
decision is given to the person.
decision notice is given to the submitter.
(3) Subsection (1)(a) does not apply if the
(3) If a person withdraws a submission before
approval resulted from a development
the application is decided, the person may not
application (superseded planning scheme)
appeal the decision.
that was assessed as if it were an
(4) If an application involves both impact application under a superseded planning
assessment and code assessment, appeal rights scheme.
for submitters are available only for the part of the
(4) Also, a person who has made a request
application involving impact assessment.
mentioned in subsection (1) may appeal to
the court against a deemed refusal of the
request.
1
Section 3.1.6 (Preliminary approval may override
local planning instrument)
Page 7 of 8
Page 8
2008/200
(5) An appeal under subsection (4) may be For Building Works Only
started at any time after the last day the Rights of appeal conferred by Section 4.2.9 of the
decision on the matter should have been Integrated Planning Act 1997 as follows:
made.
Division 3 – Appeals to tribunals relating to
development applications
Division 9 - Appeals to court about other
matters Appeals by applicants
Appeals for matters arising after approval given
(no co-respondents)
4.2.9(1) An applicant for a development application
4.1.31.(1) A person to whom any of the following may appeal to the Building and Development
notices have been given may appeal to the court Tribunal against any of the following-
against the decision in the notice-
(a) the refusal, or the refusal in part, of a
(a) a notice giving a decision on a request to development application;
change or cancel a condition of a development
approval. (b) a matter stated in a development approval,
2 including any condition applying to the
(b) a notice under section 6.1.44 giving a decision development, and the identification of a code
to change or cancel a condition of a under section 3.1.6;
3
development approval.
(c) the decision to give a preliminary approval when a
(2) The appeal must be started within 20 development permit was applied for;
business days after the day the notice of the
(d) the length of a period mentioned in section 3.5.21
decision is given to the person.
currency period;
(3) Also, a person who has made a request
(e) a deemed refusal.
mentioned in subsection (1)(a) may appeal
to the court against a deemed refusal of the (2) An appeal under subsection (1)(a) to (d) must
request. be started within 20 business days (the “applicant’s
appeal period”) after the day the decision notice or
(4) An appeal under subsection (3) may be negotiated decision notice is given to the applicant.
started at any time after the last day the
(3) An appeal under subsection (1)(e) may be
decision on the matter should have been started at any time after the last day a decision on the
made. matter should have been made.
Appeals against decisions to change approval The Registrar for the Building and Development
conditions under the repealed Act Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a http://www.localgovernment.qld.gov.au/
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
(3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to
the court against the decision or the conditions
applied.
(2) The appeal must be started within 20
business days after the day notice of the decision
is given to the applicant.
2
Section 6.1.44 (Conditions may be changed or
3
cancelled by assessment manager or concurrence Section 3.1.6 (Preliminary approval may override
agency in certain circumstances) local planning instrument)
Page 8 of 8
Used in these records
Decision Notice - 010.2008.00000200.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 60 KB (small file)
- File type
No other editions are linked here.