1. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are titled and numbered
Level 1 Plan, SD01B, dated 12.02.07
Level 2 Plan, SD02B, dated 11.05.07
Level 3 Plan, SD03B, dated 11.05.07
Roof Plan, SD04A, dated 11.05.07
Western Elevation, SD05A, dated 12.02.07
Northern Elevation, SD06A, dated 12.07.07
Eastern Elevation, SD07A, dated 11.05.07
South Elevation, SD08A, dated 12.02.07
prepared by Bud Brannigan Architect and as may be amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
3. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
4. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to service the
detached house. The tank is to be installed to ensure water from the tank can be used both:
4.1. for external use such as watering gardens, irrigation, ornamental ponds or water features, topping
up swimming pools, outdoor cleaning; and
4.2. for use in flushing of toilets internal to the building.
5. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
constructed under overhead electricity transmission lines, or within any easements.
6. A geotechnical report, prepared by a registered professional engineer shall be obtained, and it should
either:-
6.1. certify that the site is not at risk from landslide emanating from the site or from other land; or
6.2. identify methods of stabilising all buildings, accessways and uses areas; and where the
geotechnical report identifies methods of stabilising buildings, accessways and uses areas. The
development shall implement those methods, which are recommended.
7. External colours and finishes of the building shall comprise of muted/environmental tones that blend with
the natural environment.
8. Dense landscaping, comprising a mix of native coastal species of ground cover, scrubs and trees, shall
be provided for a width of 5m from the seaward or rear boundary of the site (excluding pool area)
9. Gates must not be installed along the rear property boundary.
10. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
damage and made safe to the standard required by the regulatory authority.
11. All infrastructure must be disconnected, capped or sealed including:-
11.1. electricity meters removed and electrical wires disconnected; and
A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@4008dfaa\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00000521.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 33 KB (small file)
- File type
No other editions are linked here.