Buildings can and often do move. This movement can be up, down, lateral or rotational. The fundamental cause of movement in
buildings can usually be related to one or more problems in the foundation soil. It is important for the homeowner to identify the
soil type in order to ascertain the measures that should be put in place in order to ensure that problems in the foundation soil can
be prevented, thus protecting against building movement.
This Building Technology File is designed to identify causes of soil-related building movement, and to suggest methods of
prevention of resultant cracking in buildings.
Soil Types Erosion
The types of soils usually present under the topsoil in land zoned for All soils are prone to erosion, but sandy soil is particularly susceptible
residential buildings can be split into two approximate groups – to being washed away. Even clay with a sand component of say 10%
granular and clay. Quite often, foundation soil is a mixture of both or more can suffer from erosion.
types. The general problems associated with soils having granular
content are usually caused by erosion. Clay soils are subject to Saturation
saturation and swell/shrink problems. This is particularly a problem in clay soils. Saturation creates a bog-
like suspension of the soil that causes it to lose virtually all of its
Classifications for a given area can generally be obtained by bearing capacity. To a lesser degree, sand is affected by saturation
application to the local authority, but these are sometimes unreliable because saturated sand may undergo a reduction in volume,
and if there is doubt, a geotechnical report should be commissioned. particularly imported sand fill for bedding and blinding layers.
As most buildings suffering movement problems are founded on clay However, this usually occurs as immediate settlement and should
soils, there is an emphasis on classification of soils according to the normally be the province of the builder.
amount of swell and shrinkage they experience with variations of
water content. The table below is Table 2.1 from AS 2870-2011, the Seasonal swelling and shrinkage of soil
Residential Slab and Footing Code. All clays react to the presence of water by slowly absorbing it, making
the soil increase in volume (see table below). The degree of increase
Causes of Movement varies considerably between different clays, as does the degree of
Settlement due to construction decrease during the subsequent drying out caused by fair weather
There are two types of settlement that occur as a result of periods. Because of the low absorption and expulsion rate, this
construction: phenomenon will not usually be noticeable unless there are
• Immediate settlement occurs when a building is first placed prolonged rainy or dry periods, usually of weeks or months,
depending on the land and soil characteristics.
on its foundation soil, as a result of compaction of the soil under
the weight of the structure. The cohesive quality of clay soil The swelling of soil creates an upward force on the footings of the
mitigates against this, but granular (particularly sandy) soil is building, and shrinkage creates subsidence that takes away the
susceptible. support needed by the footing to retain equilibrium.
• Consolidation settlement is a feature of clay soil and may take
Shear failure
place because of the expulsion of moisture from the soil or because
This phenomenon occurs when the foundation soil does not have
of the soil’s lack of resistance to local compressive or shear stresses.
sufficient strength to support the weight of the footing. There are
This will usually take place during the first few months after two major post-construction causes:
construction, but has been known to take many years in
exceptional cases. • Significant load increase.
• Reduction of lateral support of the soil under the footing due to
These problems are the province of the builder and should be taken
erosion or excavation.
into consideration as part of the preparation of the site for
construction. Building Technology File 19 (BTF 19) deals with these In clay soil, shear failure can be caused by saturation of the soil
problems. adjacent to or under the footing.
GENERAL DEFINITIONS OF SITE CLASSES
Class Foundation
A Most sand and rock sites with little or no ground movement from moisture changes
S Slightly reactive clay sites, which may experience only slight ground movement from moisture changes
M Moderately reactive clay or silt sites, which may experience moderate ground movement from moisture changes
H1 Highly reactive clay sites, which may experience high ground movement from moisture changes
H2 Highly reactive clay sites, which may experience very high ground movement from moisture changes
E Extremely reactive sites, which may experience extreme ground movement from moisture changes
Notes
1. Where controlled fill has been used, the site may be classified A to E according to the type of fill used.
2. Filled sites. Class P is used for sites which include soft fills, such as clay or silt or loose sands; landslip; mine subsidence; collapsing soils; soil subject to erosion;
reactive sites subject to abnormal moisture conditions or sites which cannot be classified otherwise.
3. Where deep-seated moisture changes exist on sites at depths of 3 m or greater, further classification is needed for Classes M to E (M-D, H1-D, H2-D and E-D).
081203 BTF 18 3pp.indd 1 25/10/12 12:40:29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Geotechnical Investigation Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.