Civil Package
Original PDF page 21, section 1. The text section number identifies this passage in the reader.
1. Sediment fencing downstream of the work areas within the site to prevent sediment from leaving the
disturbed construction area.
2. Providing a stabilised construction entry and washdown area to minimise sediment carried by construction
vehicles from the site.
3. Minimising disturbed areas where possible.
4. Diverting clean upstream run-off around disturbed areas within the site.
5. Protecting material and equipment stockpile areas with upstream diversion banks and downstream
sediment fencing to prevent sediment transport.
6. Providing grass filter strips within the downstream verge
7. Ensuring any loose material tracked onto roads by construction vehicles is swept and removed from the
access road before the end of the day.
Project number 20220051 Page 9 of 16
File RECOR Stormwater Management Report - 20220051.docx, 2022-05-05 Revision 0
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.