Attachment B - Construction Methodology KANE

of 19

Page text shows just the words. Original shows the document exactly as it was published.

                                HOFFMAN DRIVE MEDICAL CENTRE
                               BASEMENT AND RETENTION WORKS




Hoffman Drive Medical Centre

Construction Methodology –
Basement and Retention Works

February 2020




CONTENTS                                         PAGE 1 OF 13
Log in to download the original file

Attachment B - Construction Methodology KANE.pdf · 2.5 MB (large file)

The download may take up to a minute.

Full text of the other 18 pages

Page 2

                                                                                                             HOFFMAN DRIVE MEDICAL CENTRE
                                                                                                            BASEMENT AND RETENTION WORKS



CONTENTS
1. INTRODUCTION & TASK APPRECIATION                                                                                                                      3
2. PROGRAMME & STAGING                                                                                                                                   4
3. SITE ESTABLISHMENT                                                                                                                                    5
   3.1     Environmental Controls ........................................................................................................................6
   3.2     Traffic Management & Pedestrian Movement ......................................................................................7
4. CONSTRUCTION                                                                                                                                          9
   4.1     RETENTION SYSTEMS ......................................................................................................................9
   4.2     BULK EXCAVATION WORKS .............................................................................................................9
5. WORKPLACE HEALTH & SAFETY                                                                                                                           10
   5.1     Project Specific WH&S Risk Items .....................................................................................................10




APPENDICES
APPENDIX A           INDICATIVE WORKS PROGRAMME
APPENDIX B           SITE ESTABLISHMENT PLAN




CONTENTS                                                                                                                                 PAGE 2 OF 13

Page 3

                                                                               HOFFMAN DRIVE MEDICAL CENTRE
                                                                              BASEMENT AND RETENTION WORKS



1.          INTRODUCTION & TASK APPRECIATION
Our project methodology has been developed to provide a detailed and open insight into how Kane proposes to
execute the works and operate the site during the construction of Basement and Retentions works at the Hoffman
Drive Medical Centre project.

This Construction Methodology has been prepared to ensure;

     -   The safe completion of the works for Construction workers and members of the public,
     -   Appropriate Traffic and Pedestrian Management strategies are implemented at all times
     -   Existing access via shared Easements is maintained at all times
     -   Works are completed are in a logical sequence and in accordance with the project documentation




INTRODUCTION & TASK APPRECIATION                                                                  PAGE 3 OF 13

Page 4

                                                                                   HOFFMAN DRIVE MEDICAL CENTRE
                                                                                  BASEMENT AND RETENTION WORKS



2.          PROGRAMME & STAGING
A high level programme illustrating the proposed sequence of works is included in this submission as Appendix
A of this document. This programme broadly illustrates the sequence of construction activities and the critical path
for the works.

The general sequence of works is as follows:
 Site establishment including temporary hoardings and site accommodation.
 Pad preparation (at existing ground level) including imported material suitable to the piling equipment
 Retention installation consisting of;
       o Contiguous/secant piling to the Southern Boundary and Bunker enclosure – including temporary
           rock anchors as required
       o Sheet piling to the Northern, Eastern and Western boundaries
 Bulk excavation works to the BEL as defined in the Civil Engineering plans

The programme provided is indicative only, and will be confirmed on completion of detailed design documentation.




PROGRAMME & STAGING                                                                                    PAGE 4 OF 13

Page 5

                                                                                  HOFFMAN DRIVE MEDICAL CENTRE
                                                                                 BASEMENT AND RETENTION WORKS



3.          SITE ESTABLISHMENT
A detailed Site Establishment Plan for this phase of works can be found attached in Appendix B of this document.
In preparing the Site Establishment Plan, the following project specific requirements and risks have been taken
into consideration:

Details provided throughout the section of the report will be confirmed on completion of detailed design
documentation.

 PROJECT               SPECIFIC        PROPOSED RESPONSE                        CMP ADDRESSES
 RISK/REQUIREMENT
 Tight, site with limited space        The proposed works methodology           Y
 available onsite                      considers the limited space available    Refer Site Management Plan
                                       around the site and ensure that works
                                       can be completed within the site
                                       boundary, with minimal impact to
                                       existing access easements and
                                       neighbours

 Site Amenities Establishment          Temporary site offices are proposed      Y
                                       within the site boundary.                Refer Site Management Plan

                                       These amenities will be appropriate to
                                       sustain the proposed workforce
                                       during the Basement and Retention
                                       works.

 Traffic Management                    Prior to commencement of works           Y
                                       detailed Traffic Management plans        Refer Site Management Plan
                                       will be prepared and submitted for
                                       approval.

                                       The indicative approach during each
                                       phase of the works is outlined within
                                       this document.


DILAPIDATION REPORT
Prior to any mobilisation, Kane will undertake a photographic survey and report indicating condition of surrounding
premises, roads, footpaths, trees and utilities.


SITE FENCING
The site fence shall be erected around the boundary of the site; the temporary site fence shall be constructed
1.8m in height and shall be constructed using site temporary fencing or hoardings in accordance with WH&S
regulations.

Construction access gates for both vehicles and pedestrians will also be constructed in accordance with
the site plans provided in Appendix b.




SITE ESTABLISHMENT                                                                                    PAGE 5 OF 13

Page 6

                                                                                 HOFFMAN DRIVE MEDICAL CENTRE
                                                                                BASEMENT AND RETENTION WORKS



3.1          ENVIRONMENTAL CONTROLS
All Kane projects require the development of a project specific Environmental Management Plan. This plan will
be developed with consideration to the site specific requirements and to ensure the project complies with EPA
guidelines and council bylaws. The project’s exposure to weather during demolition and construction emphasises
the need for rigorous management, specifically relating to water run-off and storm water control. Please note
some of the key risks and controls proposed for this project:

 ENVIRONMENTAL RISKS AND CONTROL

 RISK             SOURCE             CONTROL

 Noise               Plant             Plant /machinery maintained in accordance with manufacturer
                     Machinery          recommendations.
                     Construction      Silencers placed on large compressors / generators.
                      methods           Comply with council work hours.
                     Radios            Limit volume of radios.

 Dust                Ground            Protect areas of vegetation and minimise clearing / disturbance.
                      disturbance       Cover exposed ground with mulch or other suitable material.
                     Vehicle           Restrict vehicle movements.
                      movement          Dampen surfaces.
                     Dry powdery       Landscape and re-vegetate as soon as possible.
                      soils             Seed or cover soil stockpiles.

 Waste               Demolition        Utilise separate recycle bins for paper, steel etc (space permitting
                     Construction       onsite).
                      works             Use bin contractors who sort and recycle construction waste.
                     Packaging         Recycle demolished materials wherever possible.
                     Office            Place lids on domestic waste bins for odour and vermin control.
                      amenities

 Chemicals           Fuel              No bulk storage of fuel / oil onsite.
                     Oil               Paints, adhesives stored on site at minimum quantities in vented
                     Paint              containers/rooms.
                     Adhesives         All storage of chemicals shall comply with the Material Safety Data
                                         Sheet..
                                        Major servicing of plant e.g. where large quantities of oil requires
                                         changing shall be undertaken off site.

 Contamination       Paint             Use paint wash trough. Settled solids should be removed by an
 (from slurry /      Concrete           appropriate waste disposal company.
 wash water)          cutting           Designate a washing up and stone cutting area away from
 and soil            Paver cutting      stormwater drains. Build an earth bund to contain wash water from
 contamination       Stone cutting      concrete, stone cutting.

 Erosion and         Disturbed /       Protect and maintain natural vegetation and minimise clearing /
 sediment             cleared soils,     disturbance as much as possible.
 control              rain events       Connect downpipes to stormwater drainage as soon as possible or
                                         pipe roof water onto grassed areas.
                                        Install sediment fences close to the site boundary and drains where
                                         surface water may carry sediment off site.
                                        Place gravel sausages across pit openings.

 Air pollution       Plant and         Plant / machinery maintained in accordance with manufacturer
                      machinery          recommendations.
                                        Plant / machinery exhaust emissions monitored for smoke.




SITE ESTABLISHMENT                                                                                   PAGE 6 OF 13

Page 7

                                                                                    HOFFMAN DRIVE MEDICAL CENTRE
                                                                                   BASEMENT AND RETENTION WORKS



3.2            TRAFFIC MANAGEMENT & PEDESTRIAN MOVEMENT
A detailed Traffic Management Plan is attached in Appendix B of this document. In preparing the Site
Establishment Plans, the following project specific risks have been taken into consideration:

    PROJECT SPECIFIC                   PROPOSED RESPONSE                         CMP ADDRESSES
    RISK/REQUIREMENT
    Management of pedestrian           Development of a detailed,                Y
    access around site.                appropriate Pedestrian Strategy as a      Refer Traffic Management
                                       part of the project Traffic
                                       Management Plan.
    Traffic management including       Development of a detailed Traffic         Y
    access to neighbouring             Management Plan to ensure                 Refer Traffic Management
    properties.                        appropriate access around site.

    Offsite parking contractors.       No Contractor parking is to be            Y
                                       provided during the proposed works.       Refer ‘Contractor Parking’

                                       Contractors will be encouraged to
                                       make alternate arrangements for
                                       accessing the site.



SUMMARY OF ANTICIPATED PROJECT PERMITS
Footpath Closure: No pedestrian access via the existing access easement will be permitted during the works.

It is not anticipated that the footpath at Hoffman Drive will be affected during the works.

Works Zone: NA – all works are to be completed within the site boundary.

Road Closure: Road Closures to complete the works are not proposed. Traffic Management at the private
easement will be used for hold and release purposes to ensure that access to neighbouring properties is
maintained at all times.

Out of Hours: It is not anticipated that works will be required to occur out of hours

Should any additional permits be required Kane Constructions will seek the necessary approvals through Noosa
Council.


ACCESS ARRANGEMENTS
There will be separate access points provide for the site. As outlined in Attachment A.

     Pedestrian Access: Contractor access will be via a personnel gate adjacent Hoffman Drive. This will ensure
      separation of workers from deliveries and overhead loading.
     Vehicle Access (1): Piling/Retention works from the existing level will use a gated entry from the Access
      Easement.
     Vehicle Access (2): Following commencement of bulk excavations works, site access will be limited to a single
      gated entry immediately adjacent the Hoffman Drive crossover.




SITE ESTABLISHMENT                                                                                     PAGE 7 OF 13

Page 8

                                                                                 HOFFMAN DRIVE MEDICAL CENTRE
                                                                                BASEMENT AND RETENTION WORKS


Construction and earthwork activities (including the entry and departure of heavy vehicles) must only occur
between the hours of 6:30am to 6:30pm Monday to Saturday with no work on Sunday or Public Holidays. This
work time is to be carefully monitored and is to be varied dependent upon the assessed risk to the surrounding
residences. No work beyond management of site Erosion and Sediment Control Measures and the ongoing
management and suppression of dust is to occur outside these hours.

Deliveries will be controlled and scheduled in with the Site Manager in advance. Where a Subcontractor proposes
a delivery that clashes with another delivery the second request will be rejected and postponed to a suitable time
to ensure all trucks can pull into the site and not park in the surrounding streets.




SITE ESTABLISHMENT                                                                                   PAGE 8 OF 13

Page 9

                                                                                      HOFFMAN DRIVE MEDICAL CENTRE
                                                                                     BASEMENT AND RETENTION WORKS



4.           CONSTRUCTION

4.1          RETENTION SYSTEMS
The proposed Basement Retention systems for this project are as outlined below and in Appendix B of this
document;

     -   Northern Boundary: Sheet Piling
     -   Eastern Boundary: Sheet Piling, with Contiguous/Secant piling to the Bunker enclosure
     -   Southern Boundary (adjacent neighbour) – Contiguous/Secant piling
     -   Northern Boundary (adjacent neighbour): Sheet Piling

Following site establishment, installation of Environmental controls and satisfaction of all ‘Prior to
Commencement’ tasks, works to strip and prepare the site for piling plant and equipment are to commence.
Pending final geotechnical advice, it is anticipated that this will involve importing a layer of suitable material to the
majority of the site area.

Retention works will commence at the South Eastern corner of the site with the installation of Contiguous/Secant
piling to the bunker enclosure to be completed prior to continuing along the Southern boundary for the balance of
the works.

Sheet piling activities to the balance of the site will be commence during this period, subject to final coordination
with vehicle access.


4.2          BULK EXCAVATION WORKS
Following completion of the relevant retention system installation and engineering approval, bulk excavation works
will commence. Key considerations in completion of the Bulk Excavation are as follows;

     -   During Bulk Excavation works, access is to be restricted to Vehicle Gate Access Gate 2
     -   Excavation works will again commence in the South Eastern corner of the site, with works to progress
         across the site, working towards Gate 2 and the temporary ramp
     -   Should rock anchors be required, hold points will be programmed in the Bulk Excavation programme to
         allow installation at appropriate centres. Where temporary anchors are required to extend under
         neighbouring properties, consent and investigations will be completed well in advance of the scheduled
         works onsite
     -   All vehicle movements during the Bulk excavation phase of the works, including Plant deliveries and
         Truck and Dog for material removal are to maintain a forward out, forward in approach at Vehicle Gate
         2
     -   Hold and release traffic management will be implemented as required to ensure safe exit and entry to
         site, while maintaining access and minimising disruption at the shared easement.

All material to be removed from site will be disposed of in accordance with the relevant Environmental and
legislative requirements.




CONSTRUCTION                                                                                                PAGE 9 OF 13

Page 10

                                                                                     HOFFMAN DRIVE MEDICAL CENTRE
                                                                                    BASEMENT AND RETENTION WORKS



5.          WORKPLACE HEALTH & SAFETY
Kane has a comprehensive Occupational Health and Safety Management System that complies with the
requirements of, and is certified in accordance with AS/NZS 4801:2001 & the NSW OH&S Management System
Guidelines June 2004 (which is generally considered a more onerous standard than AS/NZS 4801:2001).

Kane was also one of the first builders in Australia to be certified by the Federal Safety Commission. To maintain
FSC certification, Kane are subject to a series of reaccreditation audits on an annual basis which provides our
employees and clients with the confidence that our systems are implemented on all Kane projects.

Our Occupation Health and Safety Management System on-site is commonly called ‘The Red Book’ Our Red
Book is the backbone behind the safe delivery of our projects. Implementation of our Red Book starts on award
where responsibilities are defined by our project team and sub-contractors are made aware of their obligations to
provide site specific hazard identification, risk assessment and controls associated with each trade package
(SWMS).


5.1         PROJECT SPECIFIC WH&S RISK ITEMS
Key project specific risks have been identified below. Project planning and final safety plans will address all of
these key areas.

 TRADE RISKS

 RISK IDENTIFIED             CONTROL MEASURE

 Rock during                 Although this does not seem to be a potential issue according to the geotechnical
 groundworks                 report, if rock is present our local civil works contractor will be able to deliver the
                             appropriate equipment to mitigate time loss using conventional equipment.

 Undocumented services       Prior to commencement Kane will undertake all required dial before you dig and
 during groundworks          associated investigations to ensure that all known services and located and
                             addressed.

                             In the event that any undocumented service is encountered, works will cease until
                             such a time that a plan to divert/remove those services is developed and signed off
                             by the relevant authorities.

 Suitability and safety of   All Plant and Equipment to be used during the works will be Inspected and signed
 all Plant and Equipment     off in accordance with Kane’s OH&S system. This system ensures, at a minimum,
 to be used onsite           that;
                                  - The equipment is appropriate for the proposed task
                                  - All safety controls are install and functional
                                  - All schedule maintenance is completed
                                  - Plant operators are appropriately ticketed and experienced.

 Traffic movement            Traffic movement will be managed in accordance with the approved Traffic
                             Management plan.


 Pedestrian movement         Pedestrian movement will be managed in accordance with the approved Traffic
                             Management plan.

                             At all times, Pedestrian Movement and access is to be separated from Traffic
                             movement.




WORKPLACE HEALTH & SAFETY                                                                               PAGE 10 OF 13

Page 11

                                                                               HOFFMAN DRIVE MEDICAL CENTRE
                                                                              BASEMENT AND RETENTION WORKS



Falls during retention   Appropriate edge protection and exclusion zones will be established at all times
excavation.              during basement excavation.

                         Site fencing will be maintained via daily inspections to ensure that no
                         unauthorised, out of hours’ access is possible onsite.




WORKPLACE HEALTH & SAFETY                                                                          PAGE 11 OF 13

Page 12

                              HOFFMAN DRIVE MEDICAL CENTRE
                             BASEMENT AND RETENTION WORKS


APPENDIX A:



INDICATIVE WORKS PROGRAMME




WORKPLACE HEALTH & SAFETY                     PAGE 12 OF 13

Page 13

                                                                                                                   HOFFMAN DRIVE MEDICAL CENTRE


                                                                                                INDICATIVE PROGRAMME - BASEMENT AND RETENTION WORKS

 ID   Task Name                                            Dur        Start           Finish
                                                                              April 2020                                                   May 2020                                                                     June 2020                                             July 2020
                                                                                               22   27        2            7             12           17           22             27      1            6           11               16        21            26   1   6   11           16   21        26       31
 0    HOFFMAN DRIVE MEDICAL CENTRE- BASEMENT AND           53 d   Fri 1/05/20 Mon 20/07/20
      RETENTION WORKS
 1       Project Commencement                               0d   Fri 1/05/20  Fri 1/05/20                1/05/20
 2       ONSITE WORKS                                      53 d Fri 1/05/20 Mon 20/07/20
 3          SITE ESTABLISHMENT                              6 d Fri 1/05/20 Mon 11/05/20                                               SITE ESTABLISHMENT
 4              Dilapidation Report                         1d   Fri 1/05/20  Fri 1/05/20                  Dilapidation Report
 5              Establish Site Compound and Amenities       5d   Fri 1/05/20  Fri 8/05/20                                      Establish Site Compound and Amenities
 6              External site fencing and SEC controls      5d   Fri 1/05/20  Fri 8/05/20                                      External site fencing and SEC controls
 7              Council Prestart                            1 d Mon 11/05/20 Mon 11/05/20                                             Council Prestart
 8          RETENTION WORKS                                27 d Tue 12/05/20 Fri 19/06/20                RETENTION WORKS
 9              Strip and clear site                        5 d Tue 12/05/20 Tue 19/05/20                                                                  Strip and clear site
 10             Piling Mat and Prep                         5 d Fri 15/05/20 Fri 22/05/20                                                                         Piling Mat and Prep
 11            Contig/Secant Piling Works                  14 dMon 25/05/20Thu 11/06/20                                               Contig/Secant Piling Works
 12               Bunker Enclosure                         6 d Mon 25/05/20 Mon 1/06/20                                                                                                  Bunker Enclosure
 13               Southern Boundary                        8 d Tue 2/06/20 Thu 11/06/20                                                                                                                           Southern Boundary
 14            Sheet Piling Works                          19 dMon 25/05/20Fri 19/06/20                                                       Sheet Piling Works
 15               Western Boundary                          7 d Mon 25/05/20 Tue 2/06/20                                                                                                      Western Boundary
 16               Northern Boundary                         5 d Wed 3/06/20 Tue 9/06/20                                                                                                                      Northern Boundary
 17               Eastern Boundary                          7 d Wed 10/06/20 Fri 19/06/20                                                                                                                                                Eastern Boundary
 18         BULK EXCAVATION WORKS                          25 d Fri 12/06/20 Mon 20/07/20                                                                                         BULK EXCAVATION WORKS
 19           Bulk Exc incl Rock Anchors                   25 d Fri 12/06/20 Mon 20/07/20




This programme is based on a Queensland Builder's 5-day working wee      Critical Split                  Non-Critical Task                                  Summary                                         Critical
with allowances for Public Holidays, RDO's and Shutdown periods.
                                                                         Critical Task                   Milestone                                          Project Summary

Program Date: | Last Saved: Sat 8/02/20                                                                                                         Page 1 of 2                                                                                                                                Planner: ?? Checked: ??
File: PROJECT NAME

Page 14

                             HOFFMAN DRIVE MEDICAL CENTRE
                            BASEMENT AND RETENTION WORKS


APPENDIX B:



SITE ESTABLISHMENT PLAN




WORKPLACE HEALTH & SAFETY                    PAGE 13 OF 13

Page 15

                                                                                                                                                  STAGING & SITE ESTABLISHMENT PLANNING



                                                                                                     HOFFMAN DRIVE MEDICAL CENTRE - NOOSAVILLE
Rev No.   Revision Description   Date                                     Project:                        Drawing:                                               Kane Job No          -
01        Preliminary Only       4/02/2020                                HOFFMAN DRIVE MEDICAL           SMP 00                                                 Drawn     Approved   Rev
                                                                                                                                                                 PM        --         A
                                             Kane Constructions Pty Ltd   CENTRE - NOOSAVILLE             SITE ESTABLISHMENT PLANNING – RETENTION AND BASEMENT
                                             14 Fox Street                                                WORKS
                                             Albion QLD 4010 Australia    Ribarja Property Development

Page 16

                                                                          Hoffman Drive, NOOSAVILLE




Rev No.   Revision Description   Date                                         Project:                       Drawing:             Kane Job No          -
01        Preliminary Only       4/02/2020                                    HOFFMAN DRIVE MEDICAL          SMP 01               Drawn     Approved   Rev
                                                                                                                                  PM        --         01
                                             Kane Constructions Pty Ltd       CENTRE - NOOSAVILLE            SITE LOCATION PLAN
                                             14 Fox Street
                                             Albion QLD 4010 Australia        Ribarja Property Development

Page 17

Rev No.   Revision Description   Date                                     Project:                       Drawing:                             Kane Job No          -
01        Preliminary Only       4/02/2020                                HOFFMAN DRIVE MEDICAL          SMP 02                               Drawn     Approved   Rev
                                                                                                                                              PM        --         01
                                             Kane Constructions Pty Ltd   CENTRE - NOOSAVILLE            SCOPE OF WORKS – RETENTION SYSTEMS
                                             14 Fox Street
                                             Albion QLD 4010 Australia    Ribarja Property Development

Page 18

Rev No.   Revision Description   Date                                     Project:                       Drawing:                           Kane Job No          -
01        Preliminary Only       4/02/2020                                HOFFMAN DRIVE MEDICAL          SMP 03                             Drawn     Approved   Rev
                                                                                                                                            PM        --         01
                                             Kane Constructions Pty Ltd   CENTRE - NOOSAVILLE            SITE ESTABLISHMENT PLAN - MASTER
                                             14 Fox Street
                                             Albion QLD 4010 Australia    Ribarja Property Development

Page 19

Rev No.   Revision Description   Date                                     Project:                       Drawing:                                            Kane Job No          -
01        Preliminary Only       4/02/2020                                HOFFMAN DRIVE MEDICAL          SMP 04                                              Drawn     Approved   Rev
                                                                                                                                                             PM        --         01
                                             Kane Constructions Pty Ltd   CENTRE - NOOSAVILLE            SITE ESTABLISHMENT PLAN – DURING EXCAVATION WORKS
                                             14 Fox Street
                                             Albion QLD 4010 Australia    Ribarja Property Development

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.