Attachment B - Construction Methodology KANE

of 19

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                   HOFFMAN DRIVE MEDICAL CENTRE


                                                                                                INDICATIVE PROGRAMME - BASEMENT AND RETENTION WORKS

 ID   Task Name                                            Dur        Start           Finish
                                                                              April 2020                                                   May 2020                                                                     June 2020                                             July 2020
                                                                                               22   27        2            7             12           17           22             27      1            6           11               16        21            26   1   6   11           16   21        26       31
 0    HOFFMAN DRIVE MEDICAL CENTRE- BASEMENT AND           53 d   Fri 1/05/20 Mon 20/07/20
      RETENTION WORKS
 1       Project Commencement                               0d   Fri 1/05/20  Fri 1/05/20                1/05/20
 2       ONSITE WORKS                                      53 d Fri 1/05/20 Mon 20/07/20
 3          SITE ESTABLISHMENT                              6 d Fri 1/05/20 Mon 11/05/20                                               SITE ESTABLISHMENT
 4              Dilapidation Report                         1d   Fri 1/05/20  Fri 1/05/20                  Dilapidation Report
 5              Establish Site Compound and Amenities       5d   Fri 1/05/20  Fri 8/05/20                                      Establish Site Compound and Amenities
 6              External site fencing and SEC controls      5d   Fri 1/05/20  Fri 8/05/20                                      External site fencing and SEC controls
 7              Council Prestart                            1 d Mon 11/05/20 Mon 11/05/20                                             Council Prestart
 8          RETENTION WORKS                                27 d Tue 12/05/20 Fri 19/06/20                RETENTION WORKS
 9              Strip and clear site                        5 d Tue 12/05/20 Tue 19/05/20                                                                  Strip and clear site
 10             Piling Mat and Prep                         5 d Fri 15/05/20 Fri 22/05/20                                                                         Piling Mat and Prep
 11            Contig/Secant Piling Works                  14 dMon 25/05/20Thu 11/06/20                                               Contig/Secant Piling Works
 12               Bunker Enclosure                         6 d Mon 25/05/20 Mon 1/06/20                                                                                                  Bunker Enclosure
 13               Southern Boundary                        8 d Tue 2/06/20 Thu 11/06/20                                                                                                                           Southern Boundary
 14            Sheet Piling Works                          19 dMon 25/05/20Fri 19/06/20                                                       Sheet Piling Works
 15               Western Boundary                          7 d Mon 25/05/20 Tue 2/06/20                                                                                                      Western Boundary
 16               Northern Boundary                         5 d Wed 3/06/20 Tue 9/06/20                                                                                                                      Northern Boundary
 17               Eastern Boundary                          7 d Wed 10/06/20 Fri 19/06/20                                                                                                                                                Eastern Boundary
 18         BULK EXCAVATION WORKS                          25 d Fri 12/06/20 Mon 20/07/20                                                                                         BULK EXCAVATION WORKS
 19           Bulk Exc incl Rock Anchors                   25 d Fri 12/06/20 Mon 20/07/20




This programme is based on a Queensland Builder's 5-day working wee      Critical Split                  Non-Critical Task                                  Summary                                         Critical
with allowances for Public Holidays, RDO's and Shutdown periods.
                                                                         Critical Task                   Milestone                                          Project Summary

Program Date: | Last Saved: Sat 8/02/20                                                                                                         Page 1 of 2                                                                                                                                Planner: ?? Checked: ??
File: PROJECT NAME
Log in to download the original file

Attachment B - Construction Methodology KANE.pdf · 2.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.