                                                                                                                   ADG Consulting Pty Ltd


                      7        Noise & odour management
                      7.1      Responsibility
                               The Project Manager is responsible for ensuring the appropriate management of noise and odour during
                               dewatering operations.
                      7.2      Operational policy
                               To minimise noise and odour emissions generated from the site during dewatering.
                      7.3      Performance criteria
                               The appropriate criteria to measure the performance of dewatering management at the site are provided
                               below.
                               1.    No noise or odour related complaints received from neighbouring residents or the community.
                               2.    No degradation of air quality due to fumes or odours emanating from the dewatering process.
                      7.4      Implementation strategy
                               Noise and odour emissions will be managed as described in the following sections.
                      7.4.1 Noise
                               All dewatering equipment must be operated appropriately and maintained in good working order. All
                               dewatering systems and plant must be fitted with the appropriate noise reduction equipment to comply
                               with the performance criteria. Non‐complying dewatering plant will be replaced or repaired as necessary.

                               It is proposed to employ noise mitigation strategies including use of electric pumps and dewatering
                               systems rather than diesel powered equipment. Noise attenuation blankets and screens will be installed
                               around noise generating dewatering pumps and equipment where practicable. Noise monitoring
                               equipment (unattended) will be installed by the site manager prior to commencement and monitored for
                               the duration of dewatering.
                      7.4.2 Odour
                               All dewatering plant must be fitted with the appropriate emission reduction devices. Where practicable,
                               all dewatering plant will be sealed to prevent the release of odours to the atmosphere. Fine mist odour
                               control sprays will be applied to reduce offensive odours if complaints are received from neighbouring
                               residents.
                      7.5      Monitoring
                               An inspection of the site and dewatering equipment shall be undertaken daily by the Site Manager to
                               identify the following:
                                    Excessive noise being generated by the dewatering systems and plant; and
                                    Strong or offensive odours being generated by the dewatering equipment and/or extracted
                                     groundwater.
                               Noise monitoring equipment (unattended, continuous logging) is proposed to be installed by the Site
                               Manager prior to commencement and monitored for the duration of dewatering. The Environmental
                               Protection (Noise) Policy 2019 (EPP(Noise)) identifies specific acoustic quality objectives (noise criteria)
                               to assist in preventing significant impacts on noise sensitive receptors and as a guide to long‐term
                               acoustic quality for sensitive receptors. The primary EPP(Noise) criteria relevant to this investigation is
                               outside a dwelling (i.e. adjacent dwellings), which should not have noise at levels in the daytime or
                               evenings greater than 50dB(A) LAeq,adj,1hr. This means that noise levels in the receiving environment
                               outside of nearby dwellings (i.e. on balconies) should not exceed an equivalent sound energy as would
                               be received from a one hour continuous sound of 50 decibels on the A‐weighted scale (adjusted for tonal
                               character perceptible by the human ear).




                          ADG1580.23 Dewatering Management Plan_Rev0_28.09.23                                                       Page 17




Document Set ID: 22828362
Version: 1, Version Date: 26/02/2024

Used in these records

About this file

File size
5.4 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Reference Document - Acid Sulfate Soil Report 11_2023- OPW23_0189.pdf · 5.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.