EPA Permit number: '!PCC01277908
CONDITIONS OF APPROVAL
Agency Interest — General
General
1. All excess materials associated with the construction of the works are to be removed from the site at the
completion of the works and all wastes shall be collected from the site and disposed of at a licensed
waste facility.
2. Your attention is drawn to the provisions of the Environmental Protection Act 1994 and the genera!
environmental duty of care not to pollute the environment or create a contaminated site when undertaking
works.
Site Based Management Plan
3. Prior to the commencement of works, a Site Based Management Plan (SBMP) must be prepared and be
implemented during construction of the works. The SBMP must identify all sources of environmental
harm, including but not limited to the actual and potential release of all contaminants, the potential impact
of these sources and what actions will be taken to prevent the likelihood of environmental harm being
caused. The SBMP must also provide for the review and ‘continua! improvement in the overall
environmental performance of activities to which this approval relates.
The SBMP must address the following matters:
(a) environmental commitments - a commitment by senior management to achieve specified and
relevant environmental goals;
(b) identification of environmental issues and potential impacts;
(c) control measures for routine operations to minimise likelihood of environmental harm;
(d) contingency plans and emergency procedures for non-routine situations (including but not limited to
the emergency protocol when spills occur and the amount of neutralising agent to be kept onsite);
(e) organisational structure and responsibility;
(f) effective communication;
{g) monitoring of contaminant releases;
(h) conducting environmental impact assessments;
(i) staff training;
(j) record keeping; and
{k) periodic review of environmental performance and continual improvement.
4. The SBMP must not be implemented or amended in a way that contravenes any condition of this
approval.
Prevent Release of Contaminants
5. You must ensure that all appropriate measures are taken to prevent the release of contaminants as a
result of silt runoff, chernical spills, concrete truck washout and alike. Concrete agitator wash out shall
only be conducted in a specified area to facilitate the removal of waste concrete from the area to landfill.
Wastewater from cleaning equipment shall not be discharged directly or in-directly to any waters.
Land
6. Any areas disturbed by the works are to be immediately stabilised against wind erosion and rainwater
run-off erosion.
7. All rock, stone, gravel, sand or other material used in the construction of the works must be:
(a) clean and free of silt;
(b) suitable for the purpose having regard to the location of the land and to the proposed use of the
land; and
(c) free from contaminants.
Page 4 of 6 , Environmental Protection AgencySee the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001A709D.001.pdfRelated documentPublic source context ↗
08/1787 - Referral Agency Response - EPA [As Published]Related documentApplication case desk ↗
About this file
- File size
- 423 KB (small file)
- File type
No other editions are linked here.