Council archive · source document
Decision Notice DBW23 0125 · DBW23/0125
Currency Period
2. This development approval lapses if the use has not happened by 15 April 2026, unless an
application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below. The plans must be amended to incorporate
the amendments listed within the table below and resubmitted to Council prior to the issue
of any Development Permit for Building Works*
Plan No. Rev. Plan/Document Name Date
- - - -
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
C1.0 - Site Plan prepared by Chris Clout Design 18.01.2024
Amendments In accordance with the conditions of the Development Permit for
Building Works Assessable against the Planning Scheme.
*(Refer to Advisory Note)
Flood Immunity and Earthworks
4. The minimum floor levels of all habitable rooms must be at least 300 millimetres above the
Defined Flood Event – 1% AEP.
Engineering
5. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
6. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Acid Sulfate Soils
7. The disturbance and release of Acid Sulphate Soils (ASS) must be avoided by:
a. Undertaking an Acid Sulfate Soils investigation and soil analysis pursuant to the
National Acid Sulfate Soils Guidance.
b. Not Excavating or otherwise removing soil or sediment containing ASS.
c. Not permanently or temporarily extracting groundwater that results in the aeration of
previously saturated ASS; and
d. Not undertaking filling on land at or below 5 meters AHD that results in:
i. Actual ASS being moved below the water table; or previously saturated ASS
being aerated.
Page 2 of 5
Document Set ID: 22946517
Version: 3, Version Date: 17/04/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice DBW23 0125.pdfRelated documentApplication case desk ↗
About this file
- File size
- 147 KB (small file)
- File type