Original source · versioned page text
Appendix A - Code Assessment
Performance outcomes Acceptable outcomes Compliance
the site being developed for a
dwelling house. The dwelling is
appropriately size for the site and
is set back appropriately from all
the boundaries.
Safety and amenity
PO9 AO9 Complies
Development does not result in No acceptable outcome provided The proposed development
environmental harm or complies.
environmental nuisance to
sensitive land uses.
PO10 AO10 Complies
Development does not Safe vehicular access is provided The proposed vehicular access
compromise the safety, capacity to and from the site without complies.
or operation of the road network. adversely impacting on the safety
of the road network.
Environment, heritage and scenic amenity
PO11 AO11.1 Complies
Development does not have a Development does not result in Construction of the dwelling will
significant adverse impact on the sediment, soil or other material be appropriately managed.
natural values of the site including building materials or
including through: waste products being released
loss of biodiversity values, fauna into the road reserve, stormwater
habitat and fish passage; drains, waterways or adjacent
changes to natural drainage; properties.
disturbance to any wetland
AO11.2 Complies
systems;
Natural Vegetation is retained The dwelling is located outside of
erosion and the transport of
wherever possible. the Biodiversity overlay.
sediments off site (including
pollutants and other AO11.3 Not Appliable
contaminants which would affect Where there is a nominated A nominated building envelope
the capacity of agricultural lands); building envelope on the lot, does not exist.
worsening of landslide or fire risk; clearing of native vegetation and
on-site effluent disposal; building works do not extend
creation of dust and air beyond the building envelope,
pollutants; except for the purposes of a
disturbance of buildings and driveway access.
features, including natural
features, of cultural heritage
significance.
PO12 AO12 Complies
Development and associated site Development and associated site The development is not located
works do not directly, indirectly works, including filling and within the flood overlay.
or cumulatively cause adverse excavation are designed and
impacts external to the constructed to ensure overland
development site by: flow and/or flooding is not
causing ponding of water; worsened, impeded, or otherwise
increasing flooding, which diverted to adversely affect other
adversely affects the safety or use properties.
of any land upstream and
downstream;
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.