Amended Stormwater Plan · MCU18/0019
Attached to the e-mail Response to Info Request (Amended Proposal Plans Part 2 & Amended Stormwater Plan) - MCU18/0019.
Plans and drawings: the text below has words only, no drawings.
SC7440 – Goodchap St, Noosa 12
4.3.5 Outlet Condition
The subject site is not impacted by regional flooding, refer Section 5.0. The Val Crescent gully inlets have
been modelled with an assumed upstream catchment to estimate the HGL rise through the different storm
events.
4.3.6 On-Site Detention
It is calculated from the development site plan that the proposed development will increase impervious
areas on the site from 24% to 72%. The proposed increase in impervious areas has the potential to
increase peak flow rates to the existing drainage system. To mitigate potential increases in flow rates it is
planned to detain stormwater flows on-site and discharge at a mitigated rate to the existing swale.
Mitigation of flow is provided by the following volume:
Approximately 225kL of total detention volume within an underground tank. Flows from this storage
volume will be throttled by a reduced cross-sectional area connection at the outlet (2/225mm), and
high level overflow pipes. Refer to Figure 4.1 for the detention tank details modelled.
Figure 4.1 – Detention Tank Parameters
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Amended Stormwater Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.